2043 N HOLLY DR 90068
Certificate Information: 2043 N HOLLY DR 90068
- Application / Permit
- 25014-10000-01937
- Plan Check / Job No.
- B25LA17696
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: CONVERT (E) DETTACHED GARAGE WITH ADDITION TO ACCESSORY DWELLING UNIT PER LAMC 12.22A.33(b)(1),(c),(d),(h) and (k)
- Permit Issued
- Issued on 11/11/2025
- Issuing Office
- Current Status
- Issued on 11/11/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/1/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/22/2025 | RACHEL BEYENE |
| Corrections Issued | 5/28/2025 | RACHEL BEYENE |
| Quality Review Completed | 6/11/2025 | HERNAN ARREOLA |
| Applicant returned to address corrections | 7/30/2025 | RACHEL BEYENE |
| Plan Check Approved | 8/6/2025 | RAHEL BEYENE |
| Issued | 11/11/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 6/17/2025 | MICHAEL BROWN |
| Eng Process Fee Ord 176,300 | Cleared | 6/17/2025 | MICHAEL BROWN |
| Roof/Waste drainage to street | Cleared | 6/17/2025 | MICHAEL BROWN |
| Sewer availability | Cleared | 6/17/2025 | MICHAEL BROWN |
| Grading Pre-Inspection | Cleared | 6/25/2025 | ROBERT PINA |
Contact Information
| Contractor | Smart Eye Construction Corp; Lic. No.: 1077004-B | , |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/12/2025 | Approved | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 12/12/2025 | Approved | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 12/12/2025 | Approved | CRAIG VAUGHAN |
| Underground Mechanical | 12/12/2025 | Partial Approval | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 2/24/2026 | Approved | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/24/2026 | Partial Approval | CRAIG VAUGHAN |
| HVAC-Rough | 2/24/2026 | Approved | CRAIG VAUGHAN |
| PLUMBING-Rough | 2/24/2026 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 3/10/2026 | Approved | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/10/2026 | Approved | CRAIG VAUGHAN |
| Green Building Rough | 3/10/2026 | Approved | CRAIG VAUGHAN |
| MERV13>=Rough | 3/10/2026 | Approved | CRAIG VAUGHAN |
| Insulation | 3/13/2026 | Approved | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 3/13/2026 | Corrections Issued | BRIAN SULLIVAN |
| Drywall Nailing | 3/19/2026 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 3/19/2026 | Approved | CRAIG VAUGHAN |