7708 S HOBART BLVD 90047
Certificate Information: 7708 S HOBART BLVD 90047
- Application / Permit
- 25014-10000-01928
- Plan Check / Job No.
- B25LA17574
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan ADDITION TO EXISTING GARAGE & CONVERT TO ADU PER LAMC 12.22 A.33(b)(1),(c),(d),(h) and (k)
- Permit Issued
- Issued on 4/3/2026
- Issuing Office
- Current Status
- Issued on 4/3/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/2/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/6/2025 | ALEC MOUSAKHANIAN |
| Corrections Issued | 5/6/2025 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 8/26/2025 | ALEC MOUSAKHANIAN |
| Issued | 4/3/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 5/13/2025 | SAFA JAVANMARDI |
| Roof/Waste drainage to street | Cleared | 5/13/2025 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 5/16/2025 | SAFA JAVANMARDI |
| Eng Process Fee Ord 176,300 | Cleared | 6/2/2025 | SAFA JAVANMARDI |
| Construction near power lines | Cleared | 8/22/2025 | RIDWAN HARDY |
| Construction within easement | Cleared | 8/22/2025 | RIDWAN HARDY |
Contact Information
| Contractor | 7 Day Builders Inc; Lic. No.: 1106832-B | , |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/26/2026 | Corrections Issued | SALVADOR MARTINEZ |
| Footing/Foundation/Slab | 6/8/2026 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 6/8/2026 | Partial Approval | SALVADOR MARTINEZ |
| Deputy Drilled-In Anchors | 7/17/2026 | Approved | SALVADOR MARTINEZ |
| Footing/Foundation/Slab | 7/17/2026 | Corrections Issued | SALVADOR MARTINEZ |