3121 W MADERA AVE 90039

Certificate Information: 3121 W MADERA AVE 90039

Application / Permit
25014-10000-01909
Plan Check / Job No.
B25LA17398
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
addition and remodel to (E) 1-story SFD AND MAKING DETACHED GARAGE TO ATTACHED GARAGE
Permit Issued
Issued on 11/6/2025
Issuing Office
Current Status
Issued on 11/6/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/2/2025 APPLICANT
Assigned to Plan Check Engineer 5/6/2025 SUNMIN LEE
Corrections Issued 5/7/2025 SUNMIN LEE
Applicant returned to address corrections 6/30/2025 SUNMIN LEE
Applicant returned to address corrections 7/15/2025 SUNMIN LEE
Plan Check Approved 8/20/2025 SUNMIN LEE
Issued 11/6/2025 APPLICANT

Permit Application Clearance Information

Sewer availability Cleared 5/13/2025 MICHAEL BROWN
Eng Process Fee Ord 176,300 Cleared 5/27/2025 MICHAEL BROWN
Roof/Waste drainage to street Cleared 6/27/2025 MICHAEL BROWN
ZI Cleared 7/15/2025 MAYELA VILLA

Contact Information

Architect Garrison,, Catherine; Lic. No.: C31638 5109 MONTEZUMA      LOS ANGELES, CA 90042
Contractor Jung Christopher; Lic. No.: 704277-B       ,
Engineer Phillips,, Craig; Lic. No.: C69673 2123 VESTAL AVE      LOS ANGELES, CA 90026

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/24/2025 Partial Inspection NICHOLAS LOPEZ
Deputy Drilled-In Anchors 12/10/2025 Conditional Approval GEM DE OCAMPO
Excavation/Setback/Form/Re-Bar 12/19/2025 Approved NICHOLAS LOPEZ
Deputy Wood Construction 1/30/2026 Conditional Approval NICHOLAS LOPEZ
Floor/Roof Diaphrgm/Shear Wall 2/6/2026 Approved NICHOLAS LOPEZ
PLUMBING-Rough 2/23/2026 Partial Approval NICHOLAS LOPEZ
PLUMBING-Rough 3/20/2026 Approved NICHOLAS LOPEZ
ELECTRICAL-Rough 4/6/2026 Approved NICHOLAS LOPEZ
HVAC-Rough 4/6/2026 Conditional Approval NICHOLAS LOPEZ
Underground Mechanical 4/21/2026 Partial Approval ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 4/22/2026 Conditional Approval NICHOLAS LOPEZ
BUILDING-Rough-Frame 5/6/2026 Approved NICHOLAS LOPEZ
Interior/Exterior Lathing 5/6/2026 Partial Approval NICHOLAS LOPEZ
Insulation 5/15/2026 Approved ALEX COLIN