2865-2867 S FORRESTER DR 90064
Certificate Information: 2865-2867 S FORRESTER DR 90064
- Application / Permit
- 25014-10000-01908
- Plan Check / Job No.
- B25LA17393
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN 1-STORY ATTACHED ADU
- Permit Issued
- Issued on 7/9/2025
- Issuing Office
- Current Status
- CofO Issued on 2/20/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/3/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/7/2025 | JOSE VELAZQUEZ |
| Corrections Issued | 5/8/2025 | JOSE VELAZQUEZ |
| Applicant returned to address corrections | 6/11/2025 | NEHEMIAS RAMOS |
| Applicant returned to address corrections | 6/18/2025 | NEHEMIAS RAMOS |
| Applicant returned to address corrections | 6/23/2025 | JOSE VELAZQUEZ |
| Applicant returned to address corrections | 7/1/2025 | LAWRENCE QUIRANTE |
| Plan Check Approved | 7/8/2025 | JOSE VELAZQUEZ |
| Issued | 7/9/2025 | APPLICANT |
| CofO in Progress | 2/20/2026 | RYAN SALAZAR |
| Permit Finaled | 2/20/2026 | RICHARD STEINBACH |
| CofO Issued | 2/20/2026 | RICHARD STEINBACH |
| Permit Finaled | 2/20/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 5/27/2025 | DERRICK MAGEE |
| Eng Process Fee Ord 176,300 | Cleared | 5/27/2025 | DERRICK MAGEE |
| Roof/Waste drainage to street | Cleared | 5/27/2025 | DERRICK MAGEE |
| Sewer availability | Cleared | 5/27/2025 | DERRICK MAGEE |
| Specific Plan | Cleared | 5/29/2025 | RICHARD WOO |
| Grading Pre-Inspection | Cleared | 6/2/2025 | LANNY MERRICK |
| GPI Written Notices | Cleared | 6/26/2025 | JOSE VELAZQUEZ |
Contact Information
| Contractor | Century West Construction Inc; Lic. No.: 877578-B | , |
| Engineer | Rhee,, Kyle; Lic. No.: NA78215 | , |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/1/2025 | Partial Inspection | BOBBY KEY |
| METHANE-Subgrade | 8/19/2025 | Approved | ASHLEY THOMPSON |
| PLUMBING-Rough | 8/19/2025 | Corrections Issued | ASHLEY THOMPSON |
| Deputy Drilled-In Anchors | 8/28/2025 | Conditional Approval | ASHLEY THOMPSON |
| Excavation/Setback/Form/Re-Bar | 9/2/2025 | Approved | ASHLEY THOMPSON |
| Footing/Foundation/Slab | 9/2/2025 | Approved | ASHLEY THOMPSON |
| METHANE-Barrier | 9/2/2025 | Approved | ASHLEY THOMPSON |
| PLUMBING-Rough | 9/2/2025 | Partial Approval | ASHLEY THOMPSON |
| Deputy Wood Construction | 9/25/2025 | Conditional Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 9/30/2025 | Corrections Issued | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/2/2025 | Partial Approval | ASHLEY THOMPSON |
| ELECTRICAL-Rough | 10/22/2025 | Approved | ASHLEY THOMPSON |
| HVAC-Rough | 10/22/2025 | Corrections Issued | ASHLEY THOMPSON |
| PLUMBING-Rough | 10/22/2025 | Approved | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 11/14/2025 | Corrections Issued | ASHLEY THOMPSON |
| Green Building Rough | 11/14/2025 | Approved | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 11/14/2025 | Partial Approval | ASHLEY THOMPSON |
| METHANE-Rough | 11/14/2025 | Corrections Issued | ASHLEY THOMPSON |
| Wood Frame | 11/14/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 11/19/2025 | Approved | ASHLEY THOMPSON |
| Insulation | 11/19/2025 | Corrections Issued | ASHLEY THOMPSON |
| METHANE-Final | 11/19/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| METHANE-Rough | 11/19/2025 | Approved | ASHLEY THOMPSON |
| Drywall Nailing | 11/25/2025 | Approved | ASHLEY THOMPSON |
| Insulation | 11/25/2025 | Approved | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 11/25/2025 | Partial Approval | ASHLEY THOMPSON |
| Shower Pan | 11/25/2025 | Corrections Issued | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 12/2/2025 | Approved | ANTHONY EGSON |
| Shower Pan | 12/2/2025 | Corrections Issued | ANTHONY EGSON |
| Shower Pan | 12/3/2025 | Approved | ASHLEY THOMPSON |
| Underground Mechanical | 12/30/2025 | Partial Approval | ASHLEY THOMPSON |
| Sewer | 1/14/2026 | Approved | ARAM AVEDISIAN |
| Final | 2/5/2026 | Corrections Issued | ARAM AVEDISIAN |
| Green Building Final | 2/5/2026 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 2/5/2026 | SGSOV Gas Company | ARAM AVEDISIAN |
| Smoke Detectors | 2/5/2026 | Approved | ARAM AVEDISIAN |
| Final | 2/10/2026 | OK to Issue CofO | RYAN SALAZAR |