410-412 S LORENA ST 90063
Certificate Information: 410-412 S LORENA ST 90063
- Application / Permit
- 25014-10000-01879
- Plan Check / Job No.
- B25LA17029
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: INTERIOR REMODEL AND CONVERT PORTION OF (E) SINGLE FAMILY DWELLING TO JUNIOR ACCESSORY DWELLING UNIT PER GC 66323(a)(1) and 66333
- Permit Issued
- Issued on 8/20/2025
- Issuing Office
- Current Status
- Issued on 8/20/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/29/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/2/2025 | EDWIN MARTINEZ |
| Corrections Issued | 5/5/2025 | EDWIN MARTINEZ |
| Applicant returned to address corrections | 6/16/2025 | DANIEL YIP |
| Plan Check Approved | 8/12/2025 | DANIEL YIP |
| Issued | 8/20/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 5/15/2025 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 5/15/2025 | RYAN CASTRO |
| Roof/Waste drainage to street | Cleared | 5/15/2025 | RYAN CASTRO |
| Sewer availability | Cleared | 5/15/2025 | RYAN CASTRO |
Contact Information
| Contractor | Tech Master Construction Inc; Lic. No.: 1054601-B | , |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21731 VENTURA BLVD SUITE 110 WOODLAND HILLS, CA 91364 |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/17/2025 | Conditional Approval | FREDDIE RIVERA |
| Footing/Foundation/Slab | 9/24/2025 | Approved | FREDDIE RIVERA |
| Special/Order Compliance | 9/24/2025 | Corrections Issued | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 9/29/2025 | Partial Approval | WILLIAM SIERRA |
| Special/Order Compliance | 9/29/2025 | Corrections Issued | WILLIAM SIERRA |
| Insulation | 9/30/2025 | Partial Approval | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 3/24/2026 | Approved | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 3/31/2026 | Partial Inspection | FREDDIE RIVERA |
| Green Building Rough | 3/31/2026 | Partial Inspection | FREDDIE RIVERA |
| Rough-Elec/Plmb/HVAC | 3/31/2026 | Partial Approval | FREDDIE RIVERA |
| Special/Order Compliance | 3/31/2026 | Partial Inspection | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 4/2/2026 | Approved | FREDDIE RIVERA |
| Green Building Rough | 4/2/2026 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 4/2/2026 | Approved | FREDDIE RIVERA |
| Special/Order Compliance | 4/2/2026 | Partial Inspection | OSVALDO PARAMO |
| Insulation | 4/6/2026 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 4/10/2026 | Partial Approval | FREDDIE RIVERA |
| Shower Pan | 4/10/2026 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 4/27/2026 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 4/27/2026 | Approved | JUSTIN HAWLEY |
| Gas Test | 5/28/2026 | No Access for Inspection | FREDDIE RIVERA |
| Service/Power Release | 5/28/2026 | Not Ready for Inspection | FREDDIE RIVERA |
| Gas Test | 6/1/2026 | Approved | FREDDIE RIVERA |
| Service/Power Release | 6/1/2026 | Corrections Issued | FREDDIE RIVERA |
| Final | 6/8/2026 | No Result Entered | FREDDIE RIVERA |
| Green Building Final | 6/8/2026 | No Result Entered | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 6/8/2026 | No Result Entered | FREDDIE RIVERA |
| Smoke Detectors | 6/8/2026 | No Result Entered | FREDDIE RIVERA |