2273 W DUANE ST 90039
Certificate Information: 2273 W DUANE ST 90039
- Application / Permit
- 25014-10000-01851
- Plan Check / Job No.
- B25LA16879
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: Convert detached garage to ADU plus addition to ADU per 12.22A33 of LAMC. Work per engineer and soils report.
- Permit Issued
- Issued on 9/18/2025
- Issuing Office
- Current Status
- Issued on 9/18/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/28/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/15/2025 | SALVADOR QUINTANILLA |
| Corrections Issued | 5/17/2025 | SALVADOR QUINTANILLA |
| Quality Review Completed | 5/19/2025 | PETER KIM |
| Applicant returned to address corrections | 6/23/2025 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 7/7/2025 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 7/14/2025 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 7/21/2025 | SALVADOR QUINTANILLA |
| Plan Check Approved | 7/24/2025 | SALVADOR QUINTANILLA |
| Issued | 9/18/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 6/27/2025 | DAVID LOPEZ |
| Roof/Waste drainage to street | Cleared | 6/27/2025 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/30/2025 | DAVID LOPEZ |
| Sewer availability | Cleared | 6/30/2025 | DAVID LOPEZ |
Contact Information
| Architect | Bambrough,, Patrick; Lic. No.: C34299 | 1590 ANDERSON AVE. APT 5J FORT LEE, NJ 07024 |
| Contractor | Beckley Juan Miguel; Lic. No.: 1014693-B | , |
| Engineer | Shubeck,, Christopher Robert; Lic. No.: C66775 | 23705 VANOWEN ST 101 WEST HILLS, CA 91307 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| HVAC-Rough | 6/9/2026 |
| ELECTRICAL-Rough | 6/9/2026 |
Inspection Request History
| Underground Mechanical | 12/3/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Underground Mechanical | 12/10/2025 | Approved | ALEX COLIN |
| Excavation/Setback/Form/Re-Bar | 1/8/2026 | Approved | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 1/8/2026 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/27/2026 | Partial Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/15/2026 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 5/15/2026 | Corrections Issued | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 5/15/2026 | Approved | HAMIK HARTOUNIAN |