3712 S BUCKINGHAM ROAD 90016

Certificate Information: 3712 S BUCKINGHAM ROAD 90016

Application / Permit
25014-10000-01827
Plan Check / Job No.
B25LA16546
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Eplan. Addition and remodel (E) SFD. Per engineering design.
Permit Issued
Issued on 7/1/2025
Issuing Office
Current Status
CofO Issued on 2/7/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/25/2025 APPLICANT
Assigned to Plan Check Engineer 4/30/2025 ALFREDO JARA
Corrections Issued 5/1/2025 ALFREDO JARA
Plan Check Approved 5/12/2025 ALFREDO JARA
Issued 7/1/2025 APPLICANT
CofO in Progress 2/6/2026 LUIS CASTRO
Permit Finaled 2/7/2026 DEROLD HAUFF
CofO Issued 2/7/2026 DEROLD HAUFF
Permit Finaled 2/7/2026 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/8/2025 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 5/8/2025 LEE GUILBEAUX
Sewer availability Cleared 5/8/2025 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 5/8/2025 LEE GUILBEAUX

Contact Information

Contractor Lemette Construction Design; Lic. No.: 1044314-B       ,
Engineer Nagovitsyn,, Evgeny; Lic. No.: C93527 17436 ARMINTA ST      NORTHRIDGE, CA 91325

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 8/1/2025 Not Ready for Inspection LUIS CASTRO
Excavation/Setback/Form/Re-Bar 8/1/2025 Approved LUIS CASTRO
Footing/Foundation/Slab 8/1/2025 Approved LUIS CASTRO
PLUMBING-Rough 8/1/2025 Partial Approval LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 8/28/2025 Partial Approval LUIS CASTRO
Green Building Rough 8/28/2025 Not Ready for Inspection LUIS CASTRO
ELECTRICAL-Rough 9/11/2025 Not Ready for Inspection LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 9/11/2025 Partial Approval LUIS CASTRO
Green Building Rough 9/11/2025 Not Ready for Inspection LUIS CASTRO
PLUMBING-Rough 9/11/2025 Partial Approval LUIS CASTRO
BUILDING-Rough-Frame 10/15/2025 Corrections Issued LUIS CASTRO
ELECTRICAL-Rough 10/15/2025 Approved LUIS CASTRO
Green Building Rough 10/15/2025 Approved LUIS CASTRO
HVAC-Rough 10/15/2025 Approved LUIS CASTRO
Interior/Exterior Lathing 10/15/2025 Partial Approval LUIS CASTRO
PLUMBING-Rough 10/15/2025 Approved LUIS CASTRO
BUILDING-Rough-Frame 10/29/2025 Approved LUIS CASTRO
Insulation 10/29/2025 Approved LUIS CASTRO
Interior/Exterior Lathing 10/29/2025 Approved LUIS CASTRO
Drywall Nailing 11/4/2025 Approved LUIS CASTRO
ELECTRICAL-Final 1/27/2026 Approved LUIS CASTRO
Final 1/27/2026 Corrections Issued LUIS CASTRO
Green Building Final 1/27/2026 Not Ready for Inspection LUIS CASTRO
HVAC-Final 1/27/2026 Approved LUIS CASTRO
PLUMBING-Final 1/27/2026 Approved LUIS CASTRO
SGSOV-Seismic Gas S/O Valve 1/27/2026 SGSOV Approved LUIS CASTRO
Smoke Detectors 1/27/2026 Approved LUIS CASTRO
Final 2/5/2026 OK to Issue CofO LUIS CASTRO
Green Building Final 2/5/2026 Approved LUIS CASTRO