625 S ORANGE DR 90036
Certificate Information: 625 S ORANGE DR 90036
- Application / Permit
- 25014-10000-01819
- Plan Check / Job No.
- B25LA16496
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Eplan:Addition and remodel (E) SFD. Per engineering design.
- Permit Issued
- Issued on 6/9/2025
- Issuing Office
- Current Status
- Issued on 6/9/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/24/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/29/2025 | ALFREDO JARA |
| Corrections Issued | 4/29/2025 | ALFREDO JARA |
| Plan Check Approved | 5/27/2025 | ALFREDO JARA |
| Issued | 6/9/2025 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/19/2025 | MICHAEL BROWN |
| Sewer availability | Cleared | 5/19/2025 | MICHAEL BROWN |
| Roof/Waste drainage to street | Cleared | 5/20/2025 | MICHAEL BROWN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Kim,, Hong Kook; Lic. No.: C64529 | 3600 WILSHIRE BLVD STE 1903 LOS ANGELES, CA 90010 |
| Engineer | Kim,, Hong Kook; Lic. No.: NA64529 | , |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/13/2025 | Conditional Approval | RONNIE MINDANAO |
| METHANE-Barrier | 11/13/2025 | Approved | RONNIE MINDANAO |
| METHANE-Subgrade | 11/13/2025 | Approved | RONNIE MINDANAO |
| Footing/Foundation/Slab | 1/21/2026 | Corrections Issued | RONNIE MINDANAO |
| ELECTRICAL-Rough | 3/17/2026 | Approved | JEFFREY MEAD |
| HVAC-Rough | 3/17/2026 | Approved | JEFFREY MEAD |
| METHANE-Rough | 3/17/2026 | Approved | JEFFREY MEAD |
| PLUMBING-Rough | 3/17/2026 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 3/19/2026 | Approved | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 3/19/2026 | Approved | RONNIE MINDANAO |
| Insulation | 5/6/2026 | Approved | RONNIE MINDANAO |
| Interior/Exterior Lathing | 5/6/2026 | Partial Approval | RONNIE MINDANAO |
| Interior/Exterior Lathing | 5/19/2026 | Corrections Issued | RONNIE MINDANAO |
| Interior/Exterior Lathing | 5/21/2026 | Approved | JOSH MEISTER |
| Shower Pan | 5/26/2026 | Approved | RONNIE MINDANAO |