22320 W ITASCA ST 91311
Certificate Information: 22320 W ITASCA ST 91311
- Application / Permit
- 25014-10000-01809
- Plan Check / Job No.
- B25LA16413
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION AT REAR ( APPROX 7'-1.5" X 24'-6") AND REMODEL (E) SINGLE FAMILY DWELLING WITH ATTACHED GARAGE. ENCLOSE (E) COVERED PATIO TO CREATE LIVING AREA (APPROX 8'7" X 10' )
- Permit Issued
- Issued on 5/21/2025
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/24/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/29/2025 | AUNG SOE |
| Corrections Issued | 5/1/2025 | AUNG SOE |
| Building Plans Picked Up | 5/2/2025 | APPLICANT |
| Plan Check Approved | 5/21/2025 | LUKE GONZALES |
| Issued | 5/21/2025 | APPLICANT |
| CofO in Progress | 11/18/2025 | JEFFREY HARTLINE |
| Permit Finaled | 12/9/2025 | MICHAEL PELHAM |
| CofO Issued | 12/9/2025 | MICHAEL PELHAM |
| Permit Finaled | 12/9/2025 | MICHAEL PELHAM |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 5/9/2025 | ALEXANDER HELFER |
| Eng Process Fee Ord 176,300 | Cleared | 5/13/2025 | SAFA JAVANMARDI |
| Roof/Waste drainage to street | Cleared | 5/13/2025 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 5/13/2025 | SAFA JAVANMARDI |
| Watercourse | Cleared | 5/13/2025 | SAFA JAVANMARDI |
| Specific Plan | Cleared | 5/16/2025 | CORREY KITCHENS |
Contact Information
| Contractor | Working Hands Builders Inc; Lic. No.: 1059742-B | 22778 CASS AVENUE WOODLAND HILLS, CA 91364 |
| Engineer | Deihimi,, Amir; Lic. No.: C78194 | 201 E SANDPOINTE AVE STE 400 SANTA ANA, CA 92707 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/3/2025 | Conditional Approval | CHRIS CHRISTENSEN |
| Excavation/Setback/Form/Re-Bar | 6/5/2025 | Approved | JEFFREY HARTLINE |
| Footing/Foundation/Slab | 6/5/2025 | Approved | JEFFREY HARTLINE |
| Underground Mechanical | 6/5/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| Underground Mechanical | 6/11/2025 | Approved | JEFFREY HARTLINE |
| Floor/Roof Diaphrgm/Shear Wall | 7/31/2025 | Approved | JEFFREY HARTLINE |
| Rough-Elec/Plmb/HVAC | 7/31/2025 | Approved | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 8/8/2025 | Partial Approval | SCOTT SOBEL |
| Interior/Exterior Lathing | 8/8/2025 | Partial Approval | SCOTT SOBEL |
| Insulation | 9/4/2025 | Approved | JEFFREY HARTLINE |
| Drywall Nailing | 9/16/2025 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 9/18/2025 | Partial Approval | JEFFREY HARTLINE |
| Underground Mechanical | 9/18/2025 | Approved | JEFFREY HARTLINE |
| Special/Order Compliance | 9/19/2025 | Corrections Issued | JEFFREY HARTLINE |
| ELECTRICAL-Final | 10/29/2025 | Approved | JEFFREY HARTLINE |
| HVAC-Final | 10/29/2025 | Approved | JEFFREY HARTLINE |
| PLUMBING-Final | 10/29/2025 | Approved | JEFFREY HARTLINE |
| ELECTRICAL-Final | 10/30/2025 | Approved | JEFFREY HARTLINE |
| HVAC-Final | 10/30/2025 | Approved | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 11/5/2025 | Partial Approval | JEFFREY HARTLINE |
| FLOOD-Proofing Certificate | 11/5/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| Final | 11/5/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| Green Building Final | 11/5/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| Green Building Rough | 11/5/2025 | Approved | JEFFREY HARTLINE |
| SGSOV-Seismic Gas S/O Valve | 11/5/2025 | SGSOV Not Ready | JEFFREY HARTLINE |
| Smoke Detectors | 11/5/2025 | Approved | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 11/18/2025 | Approved | JEFFREY HARTLINE |
| FLOOD-Proofing Certificate | 11/18/2025 | Approved | JEFFREY HARTLINE |
| Final | 11/18/2025 | OK to Issue CofO | JEFFREY HARTLINE |
| Green Building Final | 11/18/2025 | Approved | JEFFREY HARTLINE |
| SGSOV-Seismic Gas S/O Valve | 11/18/2025 | SGSOV Approved | JEFFREY HARTLINE |