5920 W SUNSET BLVD 90028

Certificate Information: 5920 W SUNSET BLVD 90028

Application / Permit
25014-10000-01792
Plan Check / Job No.
B25LA16208
Group
Building
Type
Bldg-Addition
Sub-Type
Commercial
Primary Use
(17) Restaurant
Work Description
ePlan PARTIAL DEMOLITION, RENOVATION, AND CONVERSION OF AN EXISTING ONE STORY RESTAURANT BUILDING TO A QUICK SERVE RESTAURANT WALK-UP RESTAURANT WITH OUTDOOR COVERED PATIO SEATING AREA, DRIVE THRU LANE
Permit Issued
Issued on 11/20/2025
Issuing Office
Current Status
Issued on 11/20/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/23/2025 APPLICANT
Assigned to Plan Check Engineer 4/24/2025 FARSHAD ALIMOHAMADI
Assigned to Zoning Architect 4/24/2025 FRANCIS AHN
Corrections Issued 4/26/2025 FARSHAD ALIMOHAMADI
Quality Review Completed 5/20/2025 HERNAN ARREOLA
Applicant returned to address corrections 7/8/2025 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 7/22/2025 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 8/7/2025 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 8/8/2025 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 8/12/2025 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 8/28/2025 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 9/5/2025 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 10/20/2025 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 10/21/2025 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 11/12/2025 FARSHAD ALIMOHAMADI
Plan Check Approved 11/14/2025 FARSHAD ALIMOHAMADI
Issued 11/20/2025 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/27/2025 DAVID LOPEZ
DAS Clearance Cleared 6/30/2025 Lawrence Quirante
Green Code Cleared 7/30/2025 Lawrence Quirante
Sewer availability Cleared 8/28/2025 DAVID LOPEZ
Low Impact Development (LID) Cleared 9/2/2025 MARTIN FRAGOSO
Work Adjacent to Public Way Cleared 9/4/2025 XIAOZHE ZHANG
Roof/Waste drainage to street Cleared 9/8/2025 DAVID LOPEZ
ZI Cleared 10/15/2025 LAMBERT GIESSINGER
Miscellaneous Cleared 10/17/2025 YASMINE BASHIRI
"Q" conditions Cleared 10/22/2025 MAIRA SANCHEZ
Miscellaneous Cleared 10/22/2025 MAIRA SANCHEZ
Miscellaneous Cleared 10/22/2025 MAIRA SANCHEZ
Miscellaneous Cleared 10/22/2025 MAIRA SANCHEZ
Highway dedication Cleared 11/4/2025 CELINA MORENO
Zoning Plan Check Cleared 11/10/2025 FRANCIS AHN
Food Service Establishment Cleared 11/14/2025 WARREN TAN
Food establishment approval Cleared 11/14/2025 LACDHS APPROVED

Contact Information

Architect Liederman,, Jeffrey Steven; Lic. No.: C29534 11812 COLONY DRIVE      SANTA ANA, CA 92705
Contractor Timberline Construction Inc; Lic. No.: 732308-B       ,
Contractor Timberline Interiors General Contractor; Lic. No.: 732308-B       ,
Engineer Ferrer,, Eric Joseph Rabano; Lic. No.: C97020 12651 ARTESIA BLVD APT 340      CERRITOS, CA 90703

Inspector Information

TIMOTHY POWELL, (213) 482-0360 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/1/2025 Approved MARTIN TAVITIAN
Excavation/Setback/Form/Re-Bar 1/21/2026 Partial Inspection CHRISTOPHER BLACKWOOD
Reinforced Concrete Frame 2/11/2026 Not Ready for Inspection LUIS CCAMACHO
Special/Order Compliance 2/23/2026 Partial Approval LUIS CCAMACHO
Footing/Foundation/Slab 2/27/2026 Partial Approval LUIS CCAMACHO
Excavation/Setback/Form/Re-Bar 3/6/2026 Partial Approval LUIS CCAMACHO
Footing/Foundation/Slab 3/6/2026 Partial Approval LUIS CCAMACHO
Piling/Pier/Caisson 3/14/2026 Partial Approval JAMES POWERS
Piling/Pier/Caisson 3/16/2026 Partial Approval LUIS CCAMACHO
Floor/Roof Diaphrgm/Shear Wall 3/25/2026 Partial Approval LUIS CCAMACHO
Footing/Foundation/Slab 3/25/2026 Partial Approval LUIS CCAMACHO
Green Building Rough 3/25/2026 Approved LUIS CCAMACHO
Reinforced Concrete Frame 3/25/2026 Partial Approval LUIS CCAMACHO
Wood Frame 3/25/2026 Partial Approval LUIS CCAMACHO
Wood Frame 4/10/2026 Partial Approval LUIS CCAMACHO
Insulation 4/17/2026 Partial Approval MARTIN TAVITIAN
Drywall Nailing 5/6/2026 Partial Approval RONALD JIMENEZ
Reinforced Concrete Frame 5/22/2026 Partial Approval LUIS CCAMACHO