648 N ROBINSON ST 1-3 90026

Certificate Information: 648 N ROBINSON ST 1-3 90026

Application / Permit
25014-10000-01780
Plan Check / Job No.
B25LA16113
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
eplan: Convert attached garage and unconditioned crawl space in a 2-story duplex with one level of garage basement to an accessory dwelling unit. Footprint of building to remain the same.
Permit Issued
Issued on 6/6/2025
Issuing Office
Current Status
CofO Issued on 12/23/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/24/2025 APPLICANT
Assigned to Plan Check Engineer 5/1/2025 JAD BASMA
Corrections Issued 5/3/2025 JAD BASMA
Quality Review Completed 5/15/2025 HERNAN ARREOLA
Plan Check Approved 6/5/2025 JAD BASMA
Issued 6/6/2025 APPLICANT
CofO in Progress 12/23/2025 FREDDIE RIVERA
Permit Finaled 12/23/2025 DEROLD HAUFF
CofO Issued 12/23/2025 DEROLD HAUFF
Permit Finaled 12/23/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/22/2025 TREVOR QUAN
Sewer availability Cleared 5/22/2025 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 5/30/2025 TREVOR QUAN
Tenant Habitability Plan Cleared 6/4/2025 RICARDO BOHORQUEZ
Grading Pre-Inspection Cleared 6/5/2025 MICHAEL TEMPLE

Contact Information

Contractor Owner-Builder       ,

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/17/2025 Approved FREDDIE RIVERA
Footing/Foundation/Slab 6/23/2025 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 7/22/2025 Partial Inspection FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 7/22/2025 Partial Approval FREDDIE RIVERA
METHANE-Rough 7/22/2025 Approved FREDDIE RIVERA
ELECTRICAL-Rough 7/30/2025 Approved FREDDIE RIVERA
Interior/Exterior Lathing 7/30/2025 Corrections Issued FREDDIE RIVERA
Interior/Exterior Lathing 8/13/2025 Corrections Issued FREDDIE RIVERA
Interior/Exterior Lathing 8/19/2025 Partial Approval FREDDIE RIVERA
BUILDING-Rough-Frame 8/20/2025 Partial Inspection FREDDIE RIVERA
ELECTRICAL-Rough 8/20/2025 Approved FREDDIE RIVERA
HVAC-Rough 8/20/2025 Partial Inspection FREDDIE RIVERA
PLUMBING-Rough 8/20/2025 Corrections Issued FREDDIE RIVERA
Wood Frame 8/20/2025 Partial Inspection FREDDIE RIVERA
BUILDING-Rough-Frame 8/27/2025 Approved FREDDIE RIVERA
Green Building Rough 8/27/2025 Approved FREDDIE RIVERA
PLUMBING-Rough 8/27/2025 Approved FREDDIE RIVERA
Pre-Inspection 9/4/2025 No Access for Inspection FREDDIE RIVERA
Insulation 9/8/2025 Approved FREDDIE RIVERA
Drywall Nailing 9/17/2025 Approved FREDDIE RIVERA
Final 11/7/2025 No Access for Inspection SCOTT FINNILA
SGSOV-Seismic Gas S/O Valve 11/7/2025 SGSOV Not Ready SCOTT FINNILA
Smoke Detectors 11/7/2025 No Access for Inspection SCOTT FINNILA
Final 12/8/2025 Corrections Issued FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 12/8/2025 SGSOV Approved FREDDIE RIVERA
Smoke Detectors 12/8/2025 Approved FREDDIE RIVERA
Final 12/23/2025 OK to Issue CofO FREDDIE RIVERA