2407 E FERNLEAF ST 90031
Certificate Information: 2407 E FERNLEAF ST 90031
- Application / Permit
- 25014-10000-01771
- Plan Check / Job No.
- B25LA16021
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- eplan: convert portion of detached garage to Accessory Dwelling Unit per LAMC 12.22 A.33(c) and (d) Work per engineer.
- Permit Issued
- Issued on 7/28/2025
- Issuing Office
- Current Status
- CofO Issued on 4/8/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/22/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/25/2025 | PINANK PATEL |
| Corrections Issued | 4/28/2025 | PINANK PATEL |
| Plan Check Approved | 7/23/2025 | PINANK PATEL |
| Issued | 7/28/2025 | APPLICANT |
| CofO in Progress | 4/7/2026 | HAMIK HARTOUNIAN |
| Permit Finaled | 4/8/2026 | DEROLD HAUFF |
| CofO Issued | 4/8/2026 | DEROLD HAUFF |
| Permit Finaled | 4/8/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/28/2025 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 4/28/2025 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 4/28/2025 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 4/29/2025 | LEE GUILBEAUX |
| Sewer availability | Cleared | 4/29/2025 | LEE GUILBEAUX |
| Construction near power lines | Cleared | 7/21/2025 | RIDWAN HARDY |
| Construction within easement | Cleared | 7/21/2025 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Valdez,, Edgar Guadalupe; Lic. No.: E23558 | 1133 N SIESTA AVE LA PUENTE, CA 91746 |
| Engineer | Vasquez,, Luis Fernando; Lic. No.: C56232 | , |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 8/19/2025 | Partial Approval | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 8/26/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 8/26/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Excavation/Setback/Form/Re-Bar | 8/28/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 9/2/2025 | Approved | HAMIK HARTOUNIAN |
| Sewer | 9/3/2025 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/6/2025 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 10/31/2025 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 10/31/2025 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 11/14/2025 | Approved | HAMIK HARTOUNIAN |
| Green Building Rough | 11/14/2025 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 11/14/2025 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 11/14/2025 | Partial Approval | HAMIK HARTOUNIAN |
| Insulation | 12/4/2025 | Corrections Issued | ALEX COLIN |
| Shower Pan | 12/4/2025 | Approved | ALEX COLIN |
| Drywall Nailing | 12/18/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Insulation | 12/18/2025 | Conditional Approval | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 12/18/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Drywall Nailing | 1/9/2026 | Approved | HAMIK HARTOUNIAN |
| Insulation | 1/9/2026 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 1/9/2026 | Partial Approval | HAMIK HARTOUNIAN |
| Final | 3/25/2026 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 3/25/2026 | Approved | HAMIK HARTOUNIAN |
| Green Building Final | 3/25/2026 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 3/25/2026 | SGSOV Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 3/25/2026 | Corrections Issued | HAMIK HARTOUNIAN |
| Final | 4/3/2026 | OK to Issue CofO | HAMIK HARTOUNIAN |
| Smoke Detectors | 4/3/2026 | Approved | HAMIK HARTOUNIAN |