eplan: convert portion of detached garage to Accessory Dwelling Unit per LAMC 12.22 A.33(c) and (d) Work per engineer.
Permit Issued
Issued on 7/28/2025
Issuing Office
Current Status
CofO Issued on 4/8/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/22/2025 APPLICANT
Assigned to Plan Check Engineer 4/25/2025 PINANK PATEL
Corrections Issued 4/28/2025 PINANK PATEL
Plan Check Approved 7/23/2025 PINANK PATEL
Issued 7/28/2025 APPLICANT
CofO in Progress 4/7/2026 HAMIK HARTOUNIAN
Permit Finaled 4/8/2026 DEROLD HAUFF
CofO Issued 4/8/2026 DEROLD HAUFF
Permit Finaled 4/8/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/28/2025 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 4/28/2025 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 4/28/2025 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 4/29/2025 LEE GUILBEAUX
Sewer availability Cleared 4/29/2025 LEE GUILBEAUX
Construction near power lines Cleared 7/21/2025 RIDWAN HARDY
Construction within easement Cleared 7/21/2025 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Valdez,, Edgar Guadalupe; Lic. No.: E23558 1133 N SIESTA AVE      LA PUENTE, CA 91746
Engineer Vasquez,, Luis Fernando; Lic. No.: C56232       ,

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 8/19/2025 Partial Approval HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 8/26/2025 Corrections Issued ALIZAH MAYAGOITIA
Footing/Foundation/Slab 8/26/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Excavation/Setback/Form/Re-Bar 8/28/2025 Corrections Issued HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 9/2/2025 Approved HAMIK HARTOUNIAN
Sewer 9/3/2025 Approved HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 10/6/2025 Approved HAMIK HARTOUNIAN
ELECTRICAL-Rough 10/31/2025 Approved HAMIK HARTOUNIAN
PLUMBING-Rough 10/31/2025 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 11/14/2025 Approved HAMIK HARTOUNIAN
Green Building Rough 11/14/2025 Approved HAMIK HARTOUNIAN
HVAC-Rough 11/14/2025 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 11/14/2025 Partial Approval HAMIK HARTOUNIAN
Insulation 12/4/2025 Corrections Issued ALEX COLIN
Shower Pan 12/4/2025 Approved ALEX COLIN
Drywall Nailing 12/18/2025 Not Ready for Inspection HAMIK HARTOUNIAN
Insulation 12/18/2025 Conditional Approval HAMIK HARTOUNIAN
Interior/Exterior Lathing 12/18/2025 Not Ready for Inspection HAMIK HARTOUNIAN
Drywall Nailing 1/9/2026 Approved HAMIK HARTOUNIAN
Insulation 1/9/2026 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 1/9/2026 Partial Approval HAMIK HARTOUNIAN
Final 3/25/2026 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 3/25/2026 Approved HAMIK HARTOUNIAN
Green Building Final 3/25/2026 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 3/25/2026 SGSOV Approved HAMIK HARTOUNIAN
Smoke Detectors 3/25/2026 Corrections Issued HAMIK HARTOUNIAN
Final 4/3/2026 OK to Issue CofO HAMIK HARTOUNIAN
Smoke Detectors 4/3/2026 Approved HAMIK HARTOUNIAN