1849 W 80TH ST 90047

Certificate Information: 1849 W 80TH ST 90047

Application / Permit
25014-10000-01767
Plan Check / Job No.
B25LA15985
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan Convert a portion of the (e) 4 car garage to create a recreation room and 1 car garage on the 1st story. New 2nd story addition to create an ADU per LAMC 12.22A.33(b)(1)
Permit Issued
Issued on 10/23/2025
Issuing Office
Current Status
Issued on 10/23/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/23/2025 APPLICANT
Assigned to Plan Check Engineer 5/15/2025 MARCELA FRANQUEZ
Corrections Issued 5/23/2025 MARCELA FRANQUEZ
Quality Review Completed 6/11/2025 HERNAN ARREOLA
Applicant returned to address corrections 8/8/2025 MARCELA FRANQUEZ
Applicant returned to address corrections 9/23/2025 MARCELA FRANQUEZ
Plan Check Approved 10/23/2025 MARCELA FRANQUEZ
Issued 10/23/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 7/8/2025 DAVID LOPEZ
Eng Process Fee Ord 176,300 Cleared 7/8/2025 DAVID LOPEZ
Roof/Waste drainage to street Cleared 7/8/2025 DAVID LOPEZ
Sewer availability Cleared 7/8/2025 DAVID LOPEZ
Flood clearance Cleared 7/11/2025 ELYSE GREPO
Construction near power lines Cleared 10/6/2025 RIDWAN HARDY
Construction within easement Cleared 10/6/2025 RIDWAN HARDY

Contact Information

Contractor J B Builders Fire Protection Inc; Lic. No.: 923970-B       ,
Contractor J B New Construction Inc; Lic. No.: 923970-B       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

Drywall Nailing 6/8/2026   

Inspection Request History

Deputy Drilled-In Anchors 11/14/2025 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Rough 11/14/2025 Corrections Issued SALVADOR MARTINEZ
Special/Order Compliance 11/14/2025 Corrections Issued SALVADOR MARTINEZ
Footing/Foundation/Slab 12/11/2025 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Rough 12/11/2025 Partial Approval SALVADOR MARTINEZ
Footing/Foundation/Slab 12/15/2025 Corrections Issued SALVADOR MARTINEZ
Deputy Drilled-In Anchors 12/16/2025 Conditional Approval SALVADOR MARTINEZ
Footing/Foundation/Slab 12/17/2025 Partial Approval SALVADOR MARTINEZ
Footing/Foundation/Slab 12/22/2025 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 1/13/2026 Corrections Issued SALVADOR MARTINEZ
Special/Order Compliance 1/13/2026 Corrections Issued SALVADOR MARTINEZ
Deputy Wood Construction 1/16/2026 Conditional Approval SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 1/16/2026 Partial Approval MICHAEL LEWIS
Sewer 1/16/2026 Approved MICHAEL LEWIS
HVAC-Rough 3/12/2026 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Rough 3/12/2026 Corrections Issued SALVADOR MARTINEZ
ELECTRICAL-Rough 3/16/2026 Corrections Issued SALVADOR MARTINEZ
Sewer 3/16/2026 Partial Inspection SALVADOR MARTINEZ
Underground Mechanical 3/16/2026 Corrections Issued SALVADOR MARTINEZ
ELECTRICAL-Rough 3/24/2026 Approved SALVADOR MARTINEZ
Underground Mechanical 3/24/2026 Approved SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 4/30/2026 Corrections Issued SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 5/4/2026 Approved SALVADOR MARTINEZ
Deputy Wood Construction 5/5/2026 Conditional Approval ALEX COLIN
Interior/Exterior Lathing 5/11/2026 Partial Approval ALEX COLIN
Insulation 5/15/2026 Corrections Issued SALVADOR MARTINEZ
ELECTRICAL-Rough 5/19/2026 Approved JOHN QUINTANILLA
HVAC-Rough 5/19/2026 Approved JOHN QUINTANILLA
BUILDING-Rough-Frame 5/22/2026 Approved RAUL BARAJAS
Green Building Rough 5/22/2026 Approved RAUL BARAJAS
PLUMBING-Rough 5/22/2026 Approved RAUL BARAJAS
Insulation 5/28/2026 Approved ALEX COLIN