1683 W 266TH ST 90710

Certificate Information: 1683 W 266TH ST 90710

Application / Permit
25014-10000-01763
Plan Check / Job No.
B25LA15964
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
eplan 1. 441 sq. ft. garage/storage addition to (e) detached garage
Permit Issued
Issued on 7/9/2025
Issuing Office
Current Status
CofO Issued on 12/30/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/22/2025 APPLICANT
Assigned to Plan Check Engineer 4/25/2025 NGHI SU
Corrections Issued 4/26/2025 NGHI SU
Applicant returned to address corrections 6/3/2025 NGHI SU
Applicant returned to address corrections 6/11/2025 NGHI SU
Plan Check Approved 6/25/2025 NGHI SU
Issued 7/9/2025 APPLICANT
CofO in Progress 12/30/2025 EUGENE CASSIDY
Permit Finaled 12/30/2025 ANSON MAGLASANG
CofO Issued 12/30/2025 ANSON MAGLASANG
Permit Finaled 12/30/2025 ANSON MAGLASANG

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 5/11/2025 BRYAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 5/22/2025 BRYAN GODINEZ
Grading Pre-Inspection Cleared 6/3/2025 NGHI SU
Construction near power lines Cleared 6/24/2025 ENRIQUE ACOSTA

Contact Information

Contractor Owner-Builder       ,
Engineer Yates,, Gerald; Lic. No.: C73972 6309 DEL AMO BLVD      LAKEWOOD, CA 90713

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/25/2025 Conditional Approval ANSON MAGLASANG
Footing/Foundation/Slab 9/3/2025 Partial Approval EUGENE CASSIDY
Footing/Foundation/Slab 9/11/2025 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 9/25/2025 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 9/25/2025 Approved EUGENE CASSIDY
Green Building Rough 9/25/2025 Approved EUGENE CASSIDY
Interior/Exterior Lathing 10/7/2025 Approved EUGENE CASSIDY
Final 12/23/2025 Not Ready for Inspection EUGENE CASSIDY
Green Building Final 12/23/2025 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 12/23/2025 SGSOV Approved EUGENE CASSIDY
Smoke Detectors 12/23/2025 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Final 12/26/2025 Approved EUGENE CASSIDY
Final 12/26/2025 OK to Issue CofO EUGENE CASSIDY
HVAC-Final 12/26/2025 Approved EUGENE CASSIDY
PLUMBING-Final 12/26/2025 Approved EUGENE CASSIDY
Smoke Detectors 12/26/2025 Approved EUGENE CASSIDY