3862 S REDONDO BLVD 90008

Certificate Information: 3862 S REDONDO BLVD 90008

Application / Permit
25014-10000-01759
Plan Check / Job No.
B25LA15923
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED IRREG.-SHAPED KITCHEN AND NEW LAUNDRY ROOM ADDITION
Permit Issued
Issued on 9/23/2025
Issuing Office
Metro
Current Status
Issued on 9/23/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/22/2025 APPLICANT
Assigned to Plan Check Engineer 4/24/2025 LAWRENCE QUIRANTE
Corrections Issued 4/26/2025 LAWRENCE QUIRANTE
Building Plans Picked Up 5/2/2025 APPLICANT
Plan Check Approved 9/12/2025 NEHEMIAS RAMOS
Issued 9/23/2025 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 6/6/2025 JESSICA OPINION
Eng Process Fee Ord 176,300 Cleared 6/13/2025 JESSICA OPINION
Grading Pre-Inspection Cleared 9/7/2025 JONATHAN HOM

Contact Information

Contractor 7 Day Builders Inc; Lic. No.: 1106832-B 8929 S SEPULVEDA BLVD STE 403      LOS ANGELES, CA 90045
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/21/2025 Corrections Issued LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 10/28/2025 Corrections Issued LUIS CASTRO
PLUMBING-Rough 10/28/2025 Partial Approval LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 10/31/2025 Partial Approval LUIS CASTRO
Insulation 10/31/2025 Partial Approval LUIS CASTRO
BUILDING-Rough-Frame 11/20/2025 Not Ready for Inspection LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 11/20/2025 Partial Approval LUIS CASTRO
Green Building Rough 11/20/2025 Not Ready for Inspection LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 11/24/2025 Approved LUIS CASTRO
Deputy Drilled-In Anchors 12/3/2025 Conditional Approval DEVON JACKSON
Interior/Exterior Lathing 12/5/2025 Approved DEVON JACKSON
BUILDING-Rough-Frame 12/23/2025 Approved LUIS CASTRO
ELECTRICAL-Rough 12/23/2025 Corrections Issued LUIS CASTRO
Green Building Rough 12/23/2025 Approved LUIS CASTRO
HVAC-Rough 12/23/2025 Corrections Issued LUIS CASTRO
PLUMBING-Rough 12/23/2025 Partial Approval LUIS CASTRO
ELECTRICAL-Rough 12/29/2025 Approved ANTHONY RAMOS
HVAC-Rough 12/29/2025 Approved ANTHONY RAMOS
Insulation 12/29/2025 Approved ANTHONY RAMOS
Drywall Nailing 1/6/2026 Approved LUIS CASTRO
ELECTRICAL-Final 6/8/2026 Approved LUIS CASTRO
Final 6/8/2026 Corrections Issued LUIS CASTRO
Footing/Foundation/Slab 6/8/2026 Approved LUIS CASTRO
Green Building Final 6/8/2026 Not Ready for Inspection LUIS CASTRO
HVAC-Final 6/8/2026 Approved LUIS CASTRO
PLUMBING-Final 6/8/2026 Approved LUIS CASTRO
SGSOV-Seismic Gas S/O Valve 6/8/2026 SGSOV Approved LUIS CASTRO
Smoke Detectors 6/8/2026 Approved LUIS CASTRO