5509-5509 1/2 E MERIDIAN ST 90042
Certificate Information: 5509-5509 1/2 E MERIDIAN ST 90042
- Application / Permit
- 25014-10000-01718
- Plan Check / Job No.
- B25LA15529
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan: Add 2-story ADU to existing duplex LAMC 12.22A.33(c)(e)
- Permit Issued
- Issued on 8/27/2025
- Issuing Office
- Current Status
- Issued on 8/27/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/20/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/8/2025 | SAM CHANG |
| Corrections Issued | 5/29/2025 | SAM CHANG |
| Quality Review Completed | 6/2/2025 | EUGENE BARBEAU |
| Applicant returned to address corrections | 7/28/2025 | SAM CHANG |
| Plan Check Approved | 8/21/2025 | SAM CHANG |
| Issued | 8/27/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 6/10/2025 | MICHAEL BROWN |
| Roof/Waste drainage to street | Cleared | 6/10/2025 | MICHAEL BROWN |
| Sewer availability | Cleared | 6/24/2025 | MICHAEL BROWN |
| Eng Process Fee Ord 176,300 | Cleared | 6/26/2025 | MICHAEL BROWN |
| Grading Pre-Inspection | Cleared | 6/27/2025 | MICHAEL TEMPLE |
Contact Information
| Contractor | Lomeli Construction Inc; Lic. No.: 892903-B | , |
| Contractor | Lomeli Construction; Lic. No.: 892903-B | , |
| Engineer | Garcia,, Francisco Javier; Lic. No.: NA76510 | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/2/2025 | Partial Approval | DAVID WILLIAMS |
| Deputy Drilled-In Anchors | 9/15/2025 | Conditional Approval | DAVID WILLIAMS |
| Footing/Foundation/Slab | 9/16/2025 | Approved | DAVID WILLIAMS |
| Sewer | 10/1/2025 | Approved | DAVID WILLIAMS |
| Underground Mechanical | 10/1/2025 | Approved | DAVID WILLIAMS |
| Deputy Wood Construction | 12/9/2025 | Conditional Approval | GEM DE OCAMPO |
| Floor/Roof Diaphrgm/Shear Wall | 12/9/2025 | Corrections Issued | JEFFREY MEAD |
| BUILDING-Rough-Frame | 12/11/2025 | Not Ready for Inspection | DAVID WILLIAMS |
| Floor/Roof Diaphrgm/Shear Wall | 12/11/2025 | Approved | DAVID WILLIAMS |
| ELECTRICAL-Rough | 1/16/2026 | Approved | DAVID WILLIAMS |
| HVAC-Rough | 1/16/2026 | Approved | DAVID WILLIAMS |
| PLUMBING-Rough | 1/16/2026 | Approved | DAVID WILLIAMS |
| BUILDING-Rough-Frame | 1/28/2026 | Approved | DAVID WILLIAMS |
| Floor/Roof Diaphrgm/Shear Wall | 1/28/2026 | Approved | DAVID WILLIAMS |
| Insulation | 1/28/2026 | Approved | DAVID WILLIAMS |
| Shower Pan | 1/28/2026 | Approved | DAVID WILLIAMS |
| Drywall Nailing | 2/5/2026 | Approved | DAVID WILLIAMS |
| Interior/Exterior Lathing | 2/5/2026 | Approved | DAVID WILLIAMS |
| Sewer | 2/13/2026 | Partial Approval | DAVID WILLIAMS |
| Underground Mechanical | 2/13/2026 | Partial Approval | DAVID WILLIAMS |
| Sewer | 3/20/2026 | Approved | GEM DE OCAMPO |
| HVAC-Final | 5/19/2026 | Corrections Issued | NICHOLAS LOPEZ |
| PLUMBING-Final | 5/19/2026 | Corrections Issued | NICHOLAS LOPEZ |
| Service/Power Release | 7/17/2026 | Corrections Issued | DAVID WILLIAMS |