5509-5509 1/2 E MERIDIAN ST 90042

Certificate Information: 5509-5509 1/2 E MERIDIAN ST 90042

Application / Permit
25014-10000-01718
Plan Check / Job No.
B25LA15529
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan: Add 2-story ADU to existing duplex LAMC 12.22A.33(c)(e)
Permit Issued
Issued on 8/27/2025
Issuing Office
Current Status
Issued on 8/27/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/20/2025 APPLICANT
Assigned to Plan Check Engineer 5/8/2025 SAM CHANG
Corrections Issued 5/29/2025 SAM CHANG
Quality Review Completed 6/2/2025 EUGENE BARBEAU
Applicant returned to address corrections 7/28/2025 SAM CHANG
Plan Check Approved 8/21/2025 SAM CHANG
Issued 8/27/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 6/10/2025 MICHAEL BROWN
Roof/Waste drainage to street Cleared 6/10/2025 MICHAEL BROWN
Sewer availability Cleared 6/24/2025 MICHAEL BROWN
Eng Process Fee Ord 176,300 Cleared 6/26/2025 MICHAEL BROWN
Grading Pre-Inspection Cleared 6/27/2025 MICHAEL TEMPLE

Contact Information

Contractor Lomeli Construction Inc; Lic. No.: 892903-B       ,
Contractor Lomeli Construction; Lic. No.: 892903-B       ,
Engineer Garcia,, Francisco Javier; Lic. No.: NA76510       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/2/2025 Partial Approval DAVID WILLIAMS
Deputy Drilled-In Anchors 9/15/2025 Conditional Approval DAVID WILLIAMS
Footing/Foundation/Slab 9/16/2025 Approved DAVID WILLIAMS
Sewer 10/1/2025 Approved DAVID WILLIAMS
Underground Mechanical 10/1/2025 Approved DAVID WILLIAMS
Deputy Wood Construction 12/9/2025 Conditional Approval GEM DE OCAMPO
Floor/Roof Diaphrgm/Shear Wall 12/9/2025 Corrections Issued JEFFREY MEAD
BUILDING-Rough-Frame 12/11/2025 Not Ready for Inspection DAVID WILLIAMS
Floor/Roof Diaphrgm/Shear Wall 12/11/2025 Approved DAVID WILLIAMS
ELECTRICAL-Rough 1/16/2026 Approved DAVID WILLIAMS
HVAC-Rough 1/16/2026 Approved DAVID WILLIAMS
PLUMBING-Rough 1/16/2026 Approved DAVID WILLIAMS
BUILDING-Rough-Frame 1/28/2026 Approved DAVID WILLIAMS
Floor/Roof Diaphrgm/Shear Wall 1/28/2026 Approved DAVID WILLIAMS
Insulation 1/28/2026 Approved DAVID WILLIAMS
Shower Pan 1/28/2026 Approved DAVID WILLIAMS
Drywall Nailing 2/5/2026 Approved DAVID WILLIAMS
Interior/Exterior Lathing 2/5/2026 Approved DAVID WILLIAMS
Sewer 2/13/2026 Partial Approval DAVID WILLIAMS
Underground Mechanical 2/13/2026 Partial Approval DAVID WILLIAMS
Sewer 3/20/2026 Approved GEM DE OCAMPO
HVAC-Final 5/19/2026 Corrections Issued NICHOLAS LOPEZ
PLUMBING-Final 5/19/2026 Corrections Issued NICHOLAS LOPEZ
Service/Power Release 7/17/2026 Corrections Issued DAVID WILLIAMS