4013 S HARVARD BLVD 90062
Certificate Information: 4013 S HARVARD BLVD 90062
- Application / Permit
- 25014-10000-01711
- Plan Check / Job No.
- B25LA15427
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: Addition to and conversion of (e) detached garage to ADU per LAMC 12.22 A.33(b)(1)
- Permit Issued
- Issued on 9/17/2025
- Issuing Office
- Current Status
- CofO Issued on 3/20/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/17/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/22/2025 | ALFREDO JARA |
| Corrections Issued | 4/22/2025 | ALFREDO JARA |
| Plan Check Approved | 9/14/2025 | HOOMAN HAJIZADEH |
| Issued | 9/17/2025 | APPLICANT |
| CofO in Progress | 3/19/2026 | JEFFREY MEAD |
| Permit Finaled | 3/20/2026 | DEROLD HAUFF |
| Permit Finaled | 3/20/2026 | DEROLD HAUFF |
| CofO Issued | 3/20/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction near power lines | Cleared | 8/16/2025 | RIDWAN HARDY |
| Construction within easement | Cleared | 8/16/2025 | RIDWAN HARDY |
| Address approval | Cleared | 8/23/2025 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 8/25/2025 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 8/25/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 8/25/2025 | BIAINA HARITUNIAN |
| ZI | Cleared | 8/27/2025 | FIPE LEILUA |
| Flood clearance | Cleared | 9/4/2025 | SAMSON WONG |
Contact Information
| Contractor | Build Tuff Construction; Lic. No.: 1076283-B | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
| Engineer | Burnazyan,, Gegam; Lic. No.: NA76761 | , |
| Engineer | Zhong,, Raymond; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/1/2025 | Conditional Approval | SABAS ALONSO |
| Excavation/Setback/Form/Re-Bar | 10/1/2025 | Partial Approval | SABAS ALONSO |
| Sewer | 10/1/2025 | Corrections Issued | SABAS ALONSO |
| Underground Mechanical | 10/1/2025 | Corrections Issued | SABAS ALONSO |
| Deputy Drilled-In Anchors | 10/6/2025 | Conditional Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 10/7/2025 | Approved | SABAS ALONSO |
| Sewer | 10/21/2025 | Approved | SABAS ALONSO |
| Sewer | 10/22/2025 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 10/29/2025 | Not Ready for Inspection | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 10/31/2025 | Corrections Issued | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 11/7/2025 | Partial Approval | LUIS CASTRO |
| ELECTRICAL-Rough | 11/25/2025 | Not Ready for Inspection | SABAS ALONSO |
| HVAC-Rough | 11/25/2025 | Not Ready for Inspection | SABAS ALONSO |
| PLUMBING-Rough | 11/25/2025 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Rough | 12/1/2025 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 12/1/2025 | Partial Approval | SABAS ALONSO |
| HVAC-Rough | 12/1/2025 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 12/1/2025 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 12/4/2025 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 12/8/2025 | Approved | SABAS ALONSO |
| Green Building Rough | 12/8/2025 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 12/8/2025 | Partial Approval | SABAS ALONSO |
| Insulation | 12/11/2025 | Approved | ANTHONY RAMOS |
| Drywall Nailing | 12/22/2025 | Approved | DEVON JACKSON |
| Interior/Exterior Lathing | 12/22/2025 | Approved | DEVON JACKSON |
| Shower Pan | 12/22/2025 | Approved | DEVON JACKSON |
| Underground Mechanical | 1/29/2026 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 2/23/2026 | Approved | SABAS ALONSO |
| Final | 2/23/2026 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 2/23/2026 | Approved | SABAS ALONSO |
| HVAC-Final | 2/23/2026 | Approved | SABAS ALONSO |
| PLUMBING-Final | 2/23/2026 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 2/23/2026 | SGSOV Not Ready | SABAS ALONSO |
| Smoke Detectors | 2/23/2026 | Approved | SABAS ALONSO |
| Final | 3/12/2026 | Corrections Issued | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 3/12/2026 | SGSOV Approved | SABAS ALONSO |
| Final | 3/18/2026 | OK to Issue CofO | JEFFREY MEAD |