10836 W WESTMINSTER AVE 90034

Certificate Information: 10836 W WESTMINSTER AVE 90034

Application / Permit
25014-10000-01709
Plan Check / Job No.
B25LA15424
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW REAR ADDITION TO THE (E) SINGLE FAMILY DWELLING.
Permit Issued
Issued on 7/13/2025
Issuing Office
Current Status
CofO Issued on 11/6/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/17/2025 APPLICANT
Assigned to Plan Check Engineer 4/22/2025 GIOVANNY CHAVEZ
Corrections Issued 4/23/2025 GIOVANNY CHAVEZ
Applicant returned to address corrections 7/10/2025 GIOVANNY CHAVEZ
Plan Check Approved 7/12/2025 GIOVANNY CHAVEZ
Issued 7/13/2025 APPLICANT
CofO in Progress 10/30/2025 WILBER ROSALES
Permit Finaled 11/6/2025 RICHARD STEINBACH
CofO Issued 11/6/2025 RICHARD STEINBACH
Permit Finaled 11/6/2025 RICHARD STEINBACH

Permit Application Clearance Information

Grading Pre-Inspection Cleared 6/20/2025 LANNY MERRICK
Roof/Waste drainage to street Cleared 7/5/2025 SAFA JAVANMARDI
Eng Process Fee Ord 176,300 Cleared 7/7/2025 SAFA JAVANMARDI

Contact Information

Contractor Owner-Builder       ,
Engineer Ursu,, Dragos; Lic. No.: C79963 343 S MADISON AVE APT 19      PASADENA, CA 91101

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/25/2025 Corrections Issued KIRK SANDERS
Footing/Foundation/Slab 7/28/2025 Approved KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 8/1/2025 Partial Approval MICHAEL ALLEN
Green Building Rough 8/1/2025 Not Ready for Inspection MICHAEL ALLEN
PLUMBING-Rough 8/1/2025 Partial Approval MICHAEL ALLEN
Wood Frame 8/1/2025 Not Ready for Inspection MICHAEL ALLEN
BUILDING-Rough-Frame 8/18/2025 Not Ready for Inspection KIRK SANDERS
ELECTRICAL-Rough 8/18/2025 Approved KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 8/18/2025 Corrections Issued KIRK SANDERS
Green Building Rough 8/18/2025 Not Ready for Inspection KIRK SANDERS
HVAC-Rough 8/18/2025 Approved KIRK SANDERS
PLUMBING-Rough 8/18/2025 Approved KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 8/20/2025 Approved KIRK SANDERS
Interior/Exterior Lathing 8/22/2025 Partial Approval JAYLIN GRAVITTE
BUILDING-Rough-Frame 8/25/2025 Approved MEL KHACHATOURIAN
Green Building Rough 8/25/2025 Approved MEL KHACHATOURIAN
Insulation 8/25/2025 Approved MEL KHACHATOURIAN
Wood Frame 8/25/2025 Approved MEL KHACHATOURIAN
Drywall Nailing 8/28/2025 Approved KIRK SANDERS
Gas Test 8/28/2025 Not Ready for Inspection KIRK SANDERS
Interior/Exterior Lathing 8/28/2025 Partial Approval KIRK SANDERS
Shower Pan 8/28/2025 Approved KIRK SANDERS
Special/Order Compliance 8/28/2025 Corrections Issued KIRK SANDERS
Interior/Exterior Lathing 9/25/2025 Approved JAYLIN GRAVITTE
Special/Order Compliance 9/25/2025 Approved JAYLIN GRAVITTE
ELECTRICAL-Final 10/24/2025 Corrections Issued KIRK SANDERS
Final 10/24/2025 Corrections Issued KIRK SANDERS
Green Building Final 10/24/2025 Approved KIRK SANDERS
PLUMBING-Final 10/24/2025 Corrections Issued KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 10/24/2025 SGSOV Not Ready KIRK SANDERS
Smoke Detectors 10/24/2025 Corrections Issued KIRK SANDERS
ELECTRICAL-Final 10/29/2025 Approved WILBER ROSALES
Final 10/29/2025 OK to Issue CofO WILBER ROSALES
Grounding or Bonding 10/29/2025 Approved WILBER ROSALES
HVAC-Final 10/29/2025 Approved WILBER ROSALES
PLUMBING-Final 10/29/2025 Approved WILBER ROSALES
SGSOV-Seismic Gas S/O Valve 10/29/2025 SGSOV Approved WILBER ROSALES
Smoke Detectors 10/29/2025 Approved WILBER ROSALES