7601 N CHIMINEAS AVE 91335

Certificate Information: 7601 N CHIMINEAS AVE 91335

Application / Permit
25014-10000-01701
Plan Check / Job No.
B25LA15378
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
[ePlan] CONVERING AND ADDING TO THE (E) GARAGE TO PROPOSE A NEW 1-STORY SFD PER SB-9 (UNDER TWO UNIT DEVELOPMENT) -BLDG SPRINKLERED THRU-OUT
Permit Issued
Issued on 7/26/2025
Issuing Office
Current Status
Issued on 7/26/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/21/2025 APPLICANT
Assigned to Plan Check Engineer 5/8/2025 MAHNAZ NOURHASHEMI
Corrections Issued 5/15/2025 MAHNAZ NOURHASHEMI
Quality Review Completed 6/5/2025 HERNAN ARREOLA
Plan Check Approved 7/24/2025 MAHNAZ NOURHASHEMI
Issued 7/26/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 6/21/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 6/24/2025 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 6/24/2025 BIAINA HARITUNIAN
Senate Bill 9 Cleared 6/24/2025 BRENNEN OBETO
Sewer availability Cleared 6/24/2025 BIAINA HARITUNIAN
ZA Case Cleared 6/24/2025 BRENNEN OBETO

Contact Information

Contractor Owner-Builder       ,
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/2/2025 Partial Inspection ARUTYUN MADATYAN
Footing/Foundation/Slab 11/10/2025 Not Ready for Inspection JUAN ALVARADO
Underground Mechanical 11/10/2025 Partial Approval JUAN ALVARADO
Footing/Foundation/Slab 11/19/2025 Corrections Issued ARUTYUN MADATYAN
Footing/Foundation/Slab 12/1/2025 Not Ready for Inspection JUAN ALVARADO
Footing/Foundation/Slab 12/17/2025 Approved JUAN ALVARADO
BUILDING-Rough-Frame 1/30/2026 Not Ready for Inspection JUAN ALVARADO
Floor/Roof Diaphrgm/Shear Wall 1/30/2026 Corrections Issued JUAN ALVARADO
Green Building Rough 1/30/2026 Not Ready for Inspection JUAN ALVARADO
PLUMBING-Rough 1/30/2026 Approved JUAN ALVARADO
Floor/Roof Diaphrgm/Shear Wall 2/3/2026 Not Ready for Inspection GEVORK IPCHYAN
BUILDING-Rough-Frame 2/18/2026 Corrections Issued ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 2/18/2026 Not Ready for Inspection ROBERT GOLD
Green Building Rough 2/18/2026 Not Ready for Inspection ROBERT GOLD
Rough-Elec/Plmb/HVAC 2/18/2026 Corrections Issued ROBERT GOLD
BUILDING-Rough-Frame 2/23/2026 Partial Approval JUAN ALVARADO
Floor/Roof Diaphrgm/Shear Wall 2/23/2026 Approved JUAN ALVARADO
Green Building Rough 2/23/2026 Not Ready for Inspection JUAN ALVARADO
HVAC-Rough 2/23/2026 Not Ready for Inspection JUAN ALVARADO
BUILDING-Rough-Frame 2/27/2026 Approved JUAN ALVARADO
ELECTRICAL-Rough 2/27/2026 Approved JUAN ALVARADO
Green Building Rough 2/27/2026 Approved JUAN ALVARADO
HVAC-Rough 2/27/2026 Approved JUAN ALVARADO
Interior/Exterior Lathing 2/27/2026 Partial Approval JUAN ALVARADO
Verify Sprinkler Sign Off 2/27/2026 Approved JUAN ALVARADO
Wood Frame 2/27/2026 Approved JUAN ALVARADO
Insulation 3/3/2026 Approved JUAN ALVARADO
Drywall Nailing 3/5/2026 Approved TROY SANDERS
Gas Test 3/5/2026 Approved TROY SANDERS
Interior/Exterior Lathing 3/13/2026 Not Ready for Inspection JUAN ALVARADO
Sewer 3/13/2026 Approved JUAN ALVARADO
Shower Pan 3/13/2026 Approved JUAN ALVARADO
Underground Mechanical 3/13/2026 Partial Approval JUAN ALVARADO
Interior/Exterior Lathing 3/17/2026 Approved JUAN ALVARADO
Interior/Exterior Lathing 3/26/2026 Partial Approval JEFFREY HARTLINE