217-217 1/2 W 113TH ST 90061

Certificate Information: 217-217 1/2 W 113TH ST 90061

Application / Permit
25014-10000-01679
Plan Check / Job No.
B25LA15193
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
[ePlan] PROPOSED MAJOR REMODEL AND ADDITION TO CONVERT (E) 1-STORY SFD TO (N) 2-STORY DUPLEX. -BLDG SPRINKLERED THRU-OUT
Permit Issued
Issued on 7/2/2025
Issuing Office
Current Status
CofO Issued on 7/10/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/21/2025 APPLICANT
Assigned to Plan Check Engineer 4/24/2025 MAHNAZ NOURHASHEMI
Corrections Issued 4/30/2025 MAHNAZ NOURHASHEMI
Quality Review Completed 5/15/2025 HERNAN ARREOLA
Applicant returned to address corrections 6/13/2025 MAHNAZ NOURHASHEMI
Plan Check Approved 7/1/2025 MAHNAZ NOURHASHEMI
Issued 7/2/2025 APPLICANT
CofO in Progress 7/10/2026 ANSON MAGLASANG
Permit Finaled 7/10/2026 ANSON MAGLASANG
Permit Finaled 7/10/2026 ANSON MAGLASANG
CofO Issued 7/10/2026 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 5/19/2025 DAVID LOPEZ
Roof/Waste drainage to street Cleared 5/19/2025 DAVID LOPEZ
Eng Process Fee Ord 176,300 Cleared 5/20/2025 DAVID LOPEZ
Permit Cleared 5/21/2025 WALLIE JONG
Sewer availability Cleared 5/21/2025 WALLIE JONG
Trees in Parkway Cleared 5/27/2025 BRANDON WONG

Contact Information

Contractor Pacific Coast Builders; Lic. No.: 834794-B       ,
Engineer Salto,, Alvaro; Lic. No.: C83859 2543 E NORMAN AVE      WEST COVINA, CA 91791

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/8/2025 Conditional Approval BEN MOLSTAD
Deputy Other (see comments) 10/8/2025 Conditional Approval BEN MOLSTAD
Footing/Foundation/Slab 10/10/2025 Corrections Issued BEN MOLSTAD
Footing/Foundation/Slab 10/21/2025 Approved ANTHONY EGSON
Excavation/Setback/Form/Re-Bar 10/30/2025 Approved BEN MOLSTAD
Pre-Inspection 10/30/2025 Approved BEN MOLSTAD
BUILDING-Rough-Frame 11/7/2025 Partial Approval BEN MOLSTAD
Floor/Roof Diaphrgm/Shear Wall 11/7/2025 Not Ready for Inspection BEN MOLSTAD
PLUMBING-Rough 11/7/2025 Partial Approval BEN MOLSTAD
Floor/Roof Diaphrgm/Shear Wall 11/10/2025 Partial Approval JOSEPH MCGARRY
Underground Mechanical 11/10/2025 Not Ready for Inspection JOSEPH MCGARRY
Wood Frame 11/10/2025 Not Ready for Inspection JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 11/24/2025 Partial Approval JOSEPH MCGARRY
Deputy Wood Construction 12/11/2025 Conditional Approval BEN MOLSTAD
Floor/Roof Diaphrgm/Shear Wall 12/11/2025 Approved ARTHUR NEGRETE
BUILDING-Rough-Frame 3/2/2026 Approved ARTHUR NEGRETE
ELECTRICAL-Rough 3/2/2026 Approved ARTHUR NEGRETE
Green Building Rough 3/2/2026 Approved ARTHUR NEGRETE
HVAC-Rough 3/2/2026 Approved ARTHUR NEGRETE
MERV13>=Rough 3/2/2026 Approved ARTHUR NEGRETE
PLUMBING-Rough 3/2/2026 Approved ARTHUR NEGRETE
Insulation 3/6/2026 Approved BEN MOLSTAD
Interior/Exterior Lathing 3/6/2026 Partial Approval BEN MOLSTAD
Drywall Nailing 3/18/2026 Approved ARTHUR NEGRETE
Interior/Exterior Lathing 3/18/2026 Approved ARTHUR NEGRETE
Sewer 4/13/2026 Approved ARTHUR NEGRETE
Underground Mechanical 4/13/2026 Approved ARTHUR NEGRETE
Underground Mechanical 4/16/2026 Approved BEN MOLSTAD
Shower Pan 4/20/2026 Corrections Issued BEN MOLSTAD
Shower Pan 4/21/2026 Approved JOSEPH MCGARRY
ELECTRICAL-Final 6/30/2026 Approved ARTHUR NEGRETE
Final 6/30/2026 OK to Issue CofO ARTHUR NEGRETE
Gas Test 6/30/2026 Approved ARTHUR NEGRETE
Green Building Final 6/30/2026 Approved ARTHUR NEGRETE
HVAC-Final 6/30/2026 Approved ARTHUR NEGRETE
MERV13>=Final 6/30/2026 Approved ARTHUR NEGRETE
PLUMBING-Final 6/30/2026 Approved ARTHUR NEGRETE
SGSOV-Seismic Gas S/O Valve 6/30/2026 SGSOV Approved ARTHUR NEGRETE
Service/Power Release 6/30/2026 Approved ARTHUR NEGRETE
Smoke Detectors 6/30/2026 Approved ARTHUR NEGRETE