1115 W YOSEMITE DR 90041
Certificate Information: 1115 W YOSEMITE DR 90041
- Application / Permit
- 25014-10000-01673
- Plan Check / Job No.
- B25LA15120
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED 2-STORY ADDITION TO EXISTING ACCESSORY DWELLING TO CREATE NEW BEDROOM AND BATHROOM ON SECOND FLOOR AND CREATE A 1-CAR GARAGE ON FIRST LEVEL. 1 OF 2
- Permit Issued
- Issued on 8/20/2025
- Issuing Office
- Metro
- Current Status
- Issued on 8/20/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/16/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/17/2025 | MICHAEL LOPEZ |
| Corrections Issued | 4/24/2025 | MICHAEL LOPEZ |
| Quality Review Completed | 4/29/2025 | KEN GILL |
| Building Plans Picked Up | 5/2/2025 | APPLICANT |
| Applicant returned to address corrections | 6/27/2025 | MICHAEL LOPEZ |
| Plan Check Approved | 8/12/2025 | MICHAEL LOPEZ |
| Issued | 8/20/2025 | APPLICANT |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 5/19/2025 | RUSSELL BONVOULOIR |
| Sewer availability | Cleared | 5/27/2025 | JESSICA OPINION |
| Eng Process Fee Ord 176,300 | Cleared | 6/3/2025 | JESSICA OPINION |
| Roof/Waste drainage to street | Cleared | 6/3/2025 | JESSICA OPINION |
| GPI Written Notices | Cleared | 6/27/2025 | RAMAZANALI ALMASI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Jung,, Jason; Lic. No.: C80569 | 1032 PALM AVE SAN GABRIEL, CA 91776 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/20/2025 | Approved | RONNIE MEDINA |
| PLUMBING-Rough | 10/20/2025 | Partial Approval | RONNIE MEDINA |
| Footing/Foundation/Slab | 10/24/2025 | Approved | DAVID WILLIAMS |
| BUILDING-Rough-Frame | 11/25/2025 | Not Ready for Inspection | RONNIE MEDINA |
| ELECTRICAL-Rough | 11/25/2025 | Corrections Issued | RONNIE MEDINA |
| Green Building Rough | 11/25/2025 | Approved | RONNIE MEDINA |
| HVAC-Rough | 11/25/2025 | Corrections Issued | RONNIE MEDINA |
| PLUMBING-Rough | 11/25/2025 | Approved | RONNIE MEDINA |
| Deputy Wood Construction | 12/2/2025 | Conditional Approval | GEM DE OCAMPO |
| BUILDING-Rough-Frame | 12/3/2025 | Approved | RONNIE MEDINA |
| ELECTRICAL-Rough | 12/3/2025 | Approved | RONNIE MEDINA |
| HVAC-Rough | 12/3/2025 | Approved | RONNIE MEDINA |
| Insulation | 12/9/2025 | Approved | GEM DE OCAMPO |
| Interior/Exterior Lathing | 12/9/2025 | Partial Approval | GEM DE OCAMPO |
| Drywall Nailing | 12/16/2025 | Approved | RONNIE MEDINA |
| Interior/Exterior Lathing | 1/2/2026 | Approved | RONNIE MEDINA |
| ELECTRICAL-Final | 3/3/2026 | Approved | RONNIE MEDINA |
| HVAC-Final | 3/3/2026 | Approved | RONNIE MEDINA |