1500-1502 S LOUELLA AVE 90291

Certificate Information: 1500-1502 S LOUELLA AVE 90291

Application / Permit
25014-10000-01671
Plan Check / Job No.
B25LA15092
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Eplan. Major remodel and addition to existing 1-story SFD. Two story addition with new attached ADU per LAMC 12.22 A.33 (c) and (e) + two car garage. Entire home to be fully sprinklered NFPA 13D.
Permit Issued
Issued on 8/22/2025
Issuing Office
Current Status
CofO Issued on 7/15/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/16/2025 APPLICANT
Assigned to Plan Check Engineer 4/17/2025 MARCELA FRANQUEZ
Corrections Issued 4/19/2025 MARCELA FRANQUEZ
Quality Review Completed 5/2/2025 GARO TELMI
Applicant returned to address corrections 7/29/2025 MARCELA FRANQUEZ
Plan Check Approved 8/22/2025 MARCELA FRANQUEZ
Issued 8/22/2025 APPLICANT
CofO in Progress 7/15/2026 DAVID FEILER
Permit Finaled 7/15/2026 RICHARD STEINBACH
CofO Issued 7/15/2026 RICHARD STEINBACH
Permit Finaled 7/15/2026 RICHARD STEINBACH

Permit Application Clearance Information

Hydrant and Access approval Cleared 5/23/2025 JOHN CONNEALLY
Address approval Cleared 5/28/2025 DERRICK MAGEE
Permit Cleared 5/28/2025 DERRICK MAGEE
Roof/Waste drainage to street Cleared 5/28/2025 DERRICK MAGEE
Eng Process Fee Ord 176,300 Cleared 5/29/2025 DERRICK MAGEE
Sewer availability Cleared 5/29/2025 DERRICK MAGEE
Grading Pre-Inspection Cleared 6/3/2025 LANNY MERRICK
Specific Plan Cleared 6/16/2025 PEDRO AYALA
GPI Written Notices Cleared 6/27/2025 MARCELA FRANQUEZ
Construction near power lines Cleared 6/30/2025 RIDWAN HARDY
Trees in Parkway Cleared 7/2/2025 BRANDON WONG

Contact Information

Contractor Owner-Builder       ,
Engineer Moeini,, Soheil; Lic. No.: C84000 11022 SANTA MONICA BLVD STE 440      LOS ANGELES, CA 90025

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 8/26/2025 Approved MICHAEL ALLEN
Footing/Foundation/Slab 9/4/2025 Corrections Issued JESUS RODRIGUEZ
Footing/Foundation/Slab 9/5/2025 Approved JESUS RODRIGUEZ
Footing/Foundation/Slab 9/8/2025 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 10/1/2025 Corrections Issued JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 10/29/2025 Corrections Issued JESUS RODRIGUEZ
Green Building Rough 12/8/2025 Not Ready for Inspection RUBEN RIVAS
Rough-Elec/Plmb/HVAC 12/8/2025 Approved RUBEN RIVAS
BUILDING-Rough-Frame 1/26/2026 Corrections Issued RUBEN RIVAS
Green Building Rough 1/26/2026 Approved RUBEN RIVAS
Interior/Exterior Lathing 1/26/2026 Partial Approval RUBEN RIVAS
BUILDING-Rough-Frame 1/29/2026 Approved RUBEN RIVAS
Floor/Roof Diaphrgm/Shear Wall 1/29/2026 Approved RUBEN RIVAS
Insulation 2/3/2026 Approved RUBEN RIVAS
Drywall Nailing 2/10/2026 Approved RUBEN RIVAS
Shower Pan 2/10/2026 Approved RUBEN RIVAS
Interior/Exterior Lathing 2/17/2026 Order to Comply Issued RUBEN RIVAS
Pre-Inspection 3/16/2026 Approved MICHAEL ALLEN
ELECTRICAL-Final 5/26/2026 Corrections Issued ARAM AVEDISIAN
HVAC-Final 5/26/2026 Approved ARAM AVEDISIAN
PLUMBING-Final 5/26/2026 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 5/26/2026 SGSOV Approved ARAM AVEDISIAN
Smoke Detectors 5/26/2026 Approved ARAM AVEDISIAN
ELECTRICAL-Final 5/28/2026 Approved RUBEN RIVAS
Final 7/9/2026 Partial Inspection RUBEN RIVAS
Green Building Final 7/9/2026 Approved RUBEN RIVAS
Service/Power Release 7/14/2026 Approved RUBEN RIVAS
Drywall Nailing 7/15/2026 Approved DAVID FEILER
Final 7/15/2026 OK to Issue CofO DAVID FEILER