1745 1/4-1/2 W 70TH ST 90047
Certificate Information: 1745 1/4-1/2 W 70TH ST 90047
- Application / Permit
- 25014-10000-01670
- Plan Check / Job No.
- B25LA15009
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *ePlan* 2-story ground floor addition to existing 1-story garage to create 2 ADUs attached to garage per GC 66323(a)(4)
- Permit Issued
- Issued on 11/7/2025
- Issuing Office
- Current Status
- Issued on 11/7/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/7/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/29/2025 | MATTHEW TORRES |
| Corrections Issued | 6/2/2025 | MATTHEW TORRES |
| Quality Review Completed | 6/10/2025 | GARO TELMI |
| Applicant returned to address corrections | 10/14/2025 | MATTHEW TORRES |
| Applicant returned to address corrections | 10/30/2025 | MATTHEW TORRES |
| Plan Check Approved | 11/6/2025 | MATTHEW TORRES |
| Issued | 11/7/2025 | APPLICANT |
Permit Application Clearance Information
| Construction near power lines | Cleared | 10/6/2025 | RIDWAN HARDY |
| Address approval | Cleared | 10/8/2025 | JEFF LOREDO |
| Roof/Waste drainage to street | Cleared | 10/8/2025 | JEFF LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 10/9/2025 | JEFF LOREDO |
| Sewer availability | Cleared | 10/9/2025 | JEFF LOREDO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 22814 DOLOROSA ST WOODLAND HILLS, CA 91367 |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/5/2026 | Corrections Issued | BARRY HACHE |
| Excavation/Setback/Form/Re-Bar | 3/16/2026 | Corrections Issued | BARRY HACHE |
| PLUMBING-Rough | 3/16/2026 | Not Ready for Inspection | BARRY HACHE |
| Deputy Drilled-In Anchors | 3/23/2026 | Conditional Approval | BARRY HACHE |
| BUILDING-Rough-Frame | 5/29/2026 | Not Ready for Inspection | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 5/29/2026 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 5/29/2026 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 5/29/2026 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 7/13/2026 | Approved | BARRY HACHE |