3642 S ROSEWOOD AVE 90066

Certificate Information: 3642 S ROSEWOOD AVE 90066

Application / Permit
25014-10000-01655
Plan Check / Job No.
B25LA14887
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan. Convert existing 1-story garage + new addition on second floor to create 2-story ADU. 1 car-garage to remain at 1st floor per LAMC 12.22 A.33(b)(1)3
Permit Issued
Issued on 6/24/2025
Issuing Office
Current Status
CofO Issued on 4/9/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/15/2025 APPLICANT
Assigned to Plan Check Engineer 5/8/2025 JOSEPH RAFOLS
Corrections Issued 5/12/2025 JOSEPH RAFOLS
Quality Review Completed 6/4/2025 HERNAN ARREOLA
Plan Check Approved 6/16/2025 JOSEPH RAFOLS
No Progress 6/23/2025 JOSEPH RAFOLS
Plan Check Approved 6/23/2025 JOSEPH RAFOLS
Issued 6/24/2025 APPLICANT
CofO in Progress 4/3/2026 DAKOTA LOW
Permit Finaled 4/9/2026 RICHARD STEINBACH
CofO Issued 4/9/2026 RICHARD STEINBACH
Permit Finaled 4/9/2026 RICHARD STEINBACH

Permit Application Clearance Information

Specific Plan Cleared 5/20/2025 RICHARD WOO
Grading Pre-Inspection Cleared 5/20/2025 LANNY MERRICK
Address approval Cleared 5/22/2025 SAFA JAVANMARDI
Roof/Waste drainage to street Cleared 5/22/2025 SAFA JAVANMARDI
Sewer availability Cleared 5/23/2025 SAFA JAVANMARDI
Eng Process Fee Ord 176,300 Cleared 5/27/2025 SAFA JAVANMARDI

Contact Information

Architect Maru,, Keyur N; Lic. No.: C38310 6169 ATHENA STREET      CHINO, CA 91710
Architect Maru,, Keyur N; Lic. No.: NA38310       ,
Contractor Caruso'S Construction Inc; Lic. No.: 946650-B       ,
Contractor Caruso'S; Lic. No.: 946650-B       ,
Engineer Almalla,, Dean; Lic. No.: C58024 15053 VENTURA BLVD STE 205      SHERMAN OAKS, CA 91403

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 7/30/2025 Approved WILBER ROSALES
Underground Mechanical 7/30/2025 Approved WILBER ROSALES
Deputy Drilled-In Anchors 8/6/2025 Conditional Approval JAYLIN GRAVITTE
Excavation/Setback/Form/Re-Bar 8/8/2025 Approved WILBER ROSALES
Grounding or Bonding 8/8/2025 Approved WILBER ROSALES
Floor/Roof Diaphrgm/Shear Wall 8/15/2025 Partial Approval WILBER ROSALES
Floor/Roof Diaphrgm/Shear Wall 10/15/2025 Approved WILBER ROSALES
ELECTRICAL-Rough 10/28/2025 Approved WILBER ROSALES
HVAC-Rough 10/28/2025 Approved WILBER ROSALES
PLUMBING-Rough 10/28/2025 Approved WILBER ROSALES
Underground Mechanical 10/28/2025 Approved WILBER ROSALES
BUILDING-Rough-Frame 12/10/2025 Approved WILBER ROSALES
Green Building Rough 12/10/2025 Approved WILBER ROSALES
Interior/Exterior Lathing 12/10/2025 Partial Approval WILBER ROSALES
Insulation 12/12/2025 Approved RUBEN RIVAS
Drywall Nailing 12/16/2025 Approved WILBER ROSALES
Shower Pan 12/16/2025 Approved WILBER ROSALES
ELECTRICAL-Final 2/20/2026 Not Ready for Inspection DAKOTA LOW
Final 2/20/2026 Not Ready for Inspection DAKOTA LOW
Footing/Foundation/Slab 2/20/2026 Approved DAKOTA LOW
Gas Test 2/20/2026 Approved DAKOTA LOW
Green Building Final 2/20/2026 Not Ready for Inspection DAKOTA LOW
Grounding or Bonding 2/20/2026 Approved DAKOTA LOW
HVAC-Final 2/20/2026 Not Ready for Inspection DAKOTA LOW
PLUMBING-Final 2/20/2026 Not Ready for Inspection DAKOTA LOW
SGSOV-Seismic Gas S/O Valve 2/20/2026 SGSOV Not Ready DAKOTA LOW
Service/Power Release 2/20/2026 Not Ready for Inspection DAKOTA LOW
Smoke Detectors 2/20/2026 Not Ready for Inspection DAKOTA LOW
ELECTRICAL-Final 3/2/2026 Approved DAKOTA LOW
Final 3/2/2026 Corrections Issued DAKOTA LOW
Green Building Final 3/2/2026 Corrections Issued DAKOTA LOW
Grounding or Bonding 3/2/2026 Approved DAKOTA LOW
HVAC-Final 3/2/2026 Corrections Issued DAKOTA LOW
PLUMBING-Final 3/2/2026 Corrections Issued DAKOTA LOW
SGSOV-Seismic Gas S/O Valve 3/2/2026 SGSOV Not Ready DAKOTA LOW
Service/Power Release 3/2/2026 Not Ready for Inspection DAKOTA LOW
Smoke Detectors 3/2/2026 Approved DAKOTA LOW
ELECTRICAL-Final 3/23/2026 Approved DAKOTA LOW
Final 3/23/2026 Not Ready for Inspection DAKOTA LOW
Green Building Final 3/23/2026 Not Ready for Inspection DAKOTA LOW
HVAC-Final 3/23/2026 Corrections Issued DAKOTA LOW
PLUMBING-Final 3/23/2026 Corrections Issued DAKOTA LOW
SGSOV-Seismic Gas S/O Valve 3/23/2026 SGSOV Not Ready DAKOTA LOW
Final 4/2/2026 OK to Issue CofO DAKOTA LOW
Green Building Final 4/2/2026 Approved DAKOTA LOW
HVAC-Final 4/2/2026 Approved DAKOTA LOW
PLUMBING-Final 4/2/2026 Approved DAKOTA LOW
SGSOV-Seismic Gas S/O Valve 4/2/2026 SGSOV Approved DAKOTA LOW
Service/Power Release 4/2/2026 Approved DAKOTA LOW