4535-4537 E MONT EAGLE PL 90041

Certificate Information: 4535-4537 E MONT EAGLE PL 90041

Application / Permit
25014-10000-01654
Plan Check / Job No.
B25LA14880
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Eplan. Convert the existing attached garage to a Junior Accessory Dwelling Unit GC 66323(a)(1) and 66333 & new attached covered patio
Permit Issued
Issued on 6/6/2025
Issuing Office
Current Status
CofO Issued on 5/4/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/16/2025 APPLICANT
Assigned to Plan Check Engineer 4/18/2025 ALEC MOUSAKHANIAN
Corrections Issued 4/19/2025 ALEC MOUSAKHANIAN
Applicant returned to address corrections 5/21/2025 ALEC MOUSAKHANIAN
Plan Check Approved 6/5/2025 ALEC MOUSAKHANIAN
Issued 6/6/2025 APPLICANT
CofO in Progress 5/1/2026 NICHOLAS LOPEZ
Permit Finaled 5/4/2026 DEROLD HAUFF
CofO Issued 5/4/2026 DEROLD HAUFF
Permit Finaled 5/4/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/30/2025 SAFA JAVANMARDI
Sewer availability Cleared 4/30/2025 SAFA JAVANMARDI
Eng Process Fee Ord 176,300 Cleared 5/1/2025 SAFA JAVANMARDI
Roof/Waste drainage to street Cleared 5/20/2025 SAFA JAVANMARDI
Grading Pre-Inspection Cleared 5/21/2025 ALEC MOUSAKHANIAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/31/2025 Partial Approval NICHOLAS LOPEZ
Underground Mechanical 7/31/2025 Partial Approval NICHOLAS LOPEZ
Footing/Foundation/Slab 8/8/2025 Approved NICHOLAS LOPEZ
ELECTRICAL-Rough 9/18/2025 Approved NICHOLAS LOPEZ
Floor/Roof Diaphrgm/Shear Wall 9/18/2025 Corrections Issued NICHOLAS LOPEZ
HVAC-Rough 9/18/2025 Corrections Issued NICHOLAS LOPEZ
PLUMBING-Rough 9/18/2025 Approved NICHOLAS LOPEZ
BUILDING-Rough-Frame 9/24/2025 Approved NICHOLAS LOPEZ
Green Building Rough 9/24/2025 Approved NICHOLAS LOPEZ
HVAC-Rough 9/24/2025 Approved NICHOLAS LOPEZ
Interior/Exterior Lathing 9/24/2025 Partial Approval NICHOLAS LOPEZ
Insulation 9/29/2025 Approved GEM DE OCAMPO
Drywall Nailing 10/7/2025 Corrections Issued NICHOLAS LOPEZ
Drywall Nailing 10/8/2025 Approved REGINA MENDEZ
Interior/Exterior Lathing 10/8/2025 Approved REGINA MENDEZ
Shower Pan 10/14/2025 Approved REGINA MENDEZ
ELECTRICAL-Final 1/30/2026 Corrections Issued NICHOLAS LOPEZ
Final 1/30/2026 Corrections Issued NICHOLAS LOPEZ
Green Building Final 1/30/2026 Approved NICHOLAS LOPEZ
HVAC-Final 1/30/2026 Corrections Issued NICHOLAS LOPEZ
PLUMBING-Final 1/30/2026 Approved NICHOLAS LOPEZ
SGSOV-Seismic Gas S/O Valve 1/30/2026 SGSOV Not Ready NICHOLAS LOPEZ
Smoke Detectors 1/30/2026 Approved NICHOLAS LOPEZ
Final 2/4/2026 Corrections Issued NICHOLAS LOPEZ
SGSOV-Seismic Gas S/O Valve 2/4/2026 SGSOV Approved NICHOLAS LOPEZ
Final 2/6/2026 Corrections Issued NICHOLAS LOPEZ
Final 4/2/2026 Not Ready for Inspection NICHOLAS LOPEZ
Final 5/1/2026 OK to Issue CofO NICHOLAS LOPEZ