8225 S HANDLEY AVE 90045

Certificate Information: 8225 S HANDLEY AVE 90045

Application / Permit
25014-10000-01626
Plan Check / Job No.
B25LA14667
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) PATIO TO HABITABLE SPACE AND INTERIOR REMODEL TO 2-STORY SINGLE-FAMILY DWELLING
Permit Issued
Issued on 5/2/2025
Issuing Office
Current Status
CofO Issued on 10/30/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/14/2025 APPLICANT
Assigned to Plan Check Engineer 4/17/2025 ALEC MOUSAKHANIAN
Corrections Issued 4/18/2025 ALEC MOUSAKHANIAN
Plan Check Approved 4/29/2025 ALEC MOUSAKHANIAN
Issued 5/2/2025 APPLICANT
CofO in Progress 10/28/2025 JESUS PINEDA
Permit Finaled 10/30/2025 RICHARD STEINBACH
CofO Issued 10/30/2025 RICHARD STEINBACH
Permit Finaled 10/30/2025 RICHARD STEINBACH

Permit Application Clearance Information

Specific Plan Cleared 4/22/2025 HAMID GHAEMMAGHAMI
Grading Pre-Inspection Cleared 4/22/2025 LANNY MERRICK
Roof/Waste drainage to street Cleared 4/25/2025 JILVER MAZARIEGOS
Sewer availability Cleared 4/25/2025 JILVER MAZARIEGOS
Eng Process Fee Ord 176,300 Cleared 4/28/2025 JILVER MAZARIEGOS

Contact Information

Contractor Reyes Luis Construction Inc; Lic. No.: 986151-B       ,
Engineer Kim,, Taewon; Lic. No.: NA80632       ,

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/24/2025 Corrections Issued RUBEN RIVAS
METHANE-Barrier 6/24/2025 Partial Approval RUBEN RIVAS
METHANE-Subgrade 6/24/2025 Partial Approval RUBEN RIVAS
Footing/Foundation/Slab 6/27/2025 Corrections Issued RUBEN RIVAS
ELECTRICAL-Rough 7/9/2025 Corrections Issued ANTHONY EGSON
HVAC-Rough 7/9/2025 Corrections Issued ANTHONY EGSON
PLUMBING-Rough 7/9/2025 Not Ready for Inspection ANTHONY EGSON
BUILDING-Rough-Frame 7/15/2025 Corrections Issued ANTHONY EGSON
ELECTRICAL-Rough 7/15/2025 Approved ANTHONY EGSON
HVAC-Rough 7/15/2025 Corrections Issued ANTHONY EGSON
PLUMBING-Rough 7/15/2025 Approved ANTHONY EGSON
BUILDING-Rough-Frame 7/22/2025 Approved JESUS PINEDA
Footing/Foundation/Slab 7/22/2025 Approved JESUS PINEDA
HVAC-Rough 7/22/2025 Approved JESUS PINEDA
Insulation 7/24/2025 Approved MICHAEL ALLEN
Interior/Exterior Lathing 7/24/2025 Approved MICHAEL ALLEN
Shower Pan 7/24/2025 Not Ready for Inspection MICHAEL ALLEN
Drywall Nailing 7/28/2025 Approved BOBBY KEY
Interior/Exterior Lathing 7/28/2025 Approved BOBBY KEY
Shower Pan 7/28/2025 Approved BOBBY KEY
Special/Order Compliance 7/28/2025 Partial Inspection HERBERT GIRON
Special/Order Compliance 7/28/2025 Partial Inspection JAYLIN GRAVITTE
Special/Order Compliance 7/28/2025 Partial Inspection TEMISTOCLES CAAL
Final 10/24/2025 Corrections Issued JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 10/24/2025 SGSOV Approved JESUS PINEDA
Smoke Detectors 10/24/2025 Approved JESUS PINEDA
Final 10/28/2025 OK to Issue CofO JESUS PINEDA