3751 S EDGEHILL DR 90018
Certificate Information: 3751 S EDGEHILL DR 90018
- Application / Permit
- 25014-10000-01617
- Plan Check / Job No.
- B25LA14613
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: Addition and new uncovered deck at rear of existing S.F.D.
- Permit Issued
- Issued on 5/1/2025
- Issuing Office
- Current Status
- CofO Issued on 3/2/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/14/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/16/2025 | JOHNPAUL ISIP |
| Corrections Issued | 4/17/2025 | JOHNPAUL ISIP |
| Plan Check Approved | 4/30/2025 | CAROLEAN BASMA |
| Issued | 5/1/2025 | APPLICANT |
| CofO in Progress | 3/2/2026 | LUIS CASTRO |
| Permit Finaled | 3/2/2026 | DEROLD HAUFF |
| CofO Issued | 3/2/2026 | DEROLD HAUFF |
| Permit Finaled | 3/2/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 4/23/2025 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 4/24/2025 | CINDY QI |
Contact Information
| Contractor | Valencia Construction Company; Lic. No.: 1015167-B | , |
| Engineer | Ramirez, Cid, Jose Carlos; Lic. No.: C91046 | 5164 N RATON CIR LONG BEACH, CA 90807 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/7/2025 | Approved | LUIS CASTRO |
| Excavation/Setback/Form/Re-Bar | 5/7/2025 | Approved | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 5/21/2025 | Partial Approval | LUIS CASTRO |
| PLUMBING-Rough | 5/21/2025 | Partial Approval | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 5/27/2025 | Partial Approval | LUIS CASTRO |
| ELECTRICAL-Rough | 9/24/2025 | Approved | BRENDAN MORELLI |
| HVAC-Rough | 9/24/2025 | Corrections Issued | BRENDAN MORELLI |
| Wood Frame | 9/24/2025 | Not Ready for Inspection | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 10/2/2025 | Corrections Issued | LUIS CASTRO |
| ELECTRICAL-Rough | 10/2/2025 | Approved | LUIS CASTRO |
| Green Building Rough | 10/2/2025 | Not Ready for Inspection | LUIS CASTRO |
| HVAC-Rough | 10/2/2025 | Approved | LUIS CASTRO |
| PLUMBING-Rough | 10/6/2025 | Not Ready for Inspection | LUIS CASTRO |
| PLUMBING-Rough | 10/7/2025 | Corrections Issued | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 10/9/2025 | Corrections Issued | LUIS CASTRO |
| PLUMBING-Rough | 10/9/2025 | Approved | LUIS CASTRO |
| Shower Pan | 10/28/2025 | Approved | LUIS CASTRO |
| BUILDING-Rough-Frame | 10/30/2025 | Corrections Issued | LUIS CASTRO |
| Deputy Wood Construction | 10/30/2025 | Partial Approval | LUIS CASTRO |
| Green Building Rough | 10/30/2025 | Not Ready for Inspection | LUIS CASTRO |
| Interior/Exterior Lathing | 11/13/2025 | Approved | LUIS CASTRO |
| Insulation | 11/19/2025 | Partial Approval | LUIS CASTRO |
| Drywall Nailing | 12/2/2025 | Approved | LUIS CASTRO |
| Green Building Rough | 12/2/2025 | Approved | LUIS CASTRO |
| ELECTRICAL-Final | 2/12/2026 | Corrections Issued | LUIS CASTRO |
| HVAC-Final | 2/12/2026 | Approved | LUIS CASTRO |
| PLUMBING-Final | 2/12/2026 | Approved | LUIS CASTRO |
| Service/Power Release | 2/12/2026 | Not Ready for Inspection | LUIS CASTRO |
| BUILDING-Rough-Frame | 2/24/2026 | Approved | LUIS CASTRO |
| ELECTRICAL-Final | 2/24/2026 | Approved | LUIS CASTRO |
| Final | 2/24/2026 | Corrections Issued | LUIS CASTRO |
| Footing/Foundation/Slab | 2/24/2026 | Approved | LUIS CASTRO |
| Green Building Final | 2/24/2026 | Approved | LUIS CASTRO |
| HVAC-Final | 2/24/2026 | Approved | LUIS CASTRO |
| PLUMBING-Final | 2/24/2026 | Approved | LUIS CASTRO |
| SGSOV-Seismic Gas S/O Valve | 2/24/2026 | SGSOV Approved | LUIS CASTRO |
| Smoke Detectors | 2/24/2026 | Approved | LUIS CASTRO |
| Final | 2/27/2026 | OK to Issue CofO | LUIS CASTRO |