3751 S EDGEHILL DR 90018

Certificate Information: 3751 S EDGEHILL DR 90018

Application / Permit
25014-10000-01617
Plan Check / Job No.
B25LA14613
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: Addition and new uncovered deck at rear of existing S.F.D.
Permit Issued
Issued on 5/1/2025
Issuing Office
Current Status
CofO Issued on 3/2/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/14/2025 APPLICANT
Assigned to Plan Check Engineer 4/16/2025 JOHNPAUL ISIP
Corrections Issued 4/17/2025 JOHNPAUL ISIP
Plan Check Approved 4/30/2025 CAROLEAN BASMA
Issued 5/1/2025 APPLICANT
CofO in Progress 3/2/2026 LUIS CASTRO
Permit Finaled 3/2/2026 DEROLD HAUFF
CofO Issued 3/2/2026 DEROLD HAUFF
Permit Finaled 3/2/2026 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 4/23/2025 CINDY QI
Eng Process Fee Ord 176,300 Cleared 4/24/2025 CINDY QI

Contact Information

Contractor Valencia Construction Company; Lic. No.: 1015167-B       ,
Engineer Ramirez, Cid, Jose Carlos; Lic. No.: C91046 5164 N RATON CIR      LONG BEACH, CA 90807

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/7/2025 Approved LUIS CASTRO
Excavation/Setback/Form/Re-Bar 5/7/2025 Approved LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 5/21/2025 Partial Approval LUIS CASTRO
PLUMBING-Rough 5/21/2025 Partial Approval LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 5/27/2025 Partial Approval LUIS CASTRO
ELECTRICAL-Rough 9/24/2025 Approved BRENDAN MORELLI
HVAC-Rough 9/24/2025 Corrections Issued BRENDAN MORELLI
Wood Frame 9/24/2025 Not Ready for Inspection BRENDAN MORELLI
BUILDING-Rough-Frame 10/2/2025 Corrections Issued LUIS CASTRO
ELECTRICAL-Rough 10/2/2025 Approved LUIS CASTRO
Green Building Rough 10/2/2025 Not Ready for Inspection LUIS CASTRO
HVAC-Rough 10/2/2025 Approved LUIS CASTRO
PLUMBING-Rough 10/6/2025 Not Ready for Inspection LUIS CASTRO
PLUMBING-Rough 10/7/2025 Corrections Issued LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 10/9/2025 Corrections Issued LUIS CASTRO
PLUMBING-Rough 10/9/2025 Approved LUIS CASTRO
Shower Pan 10/28/2025 Approved LUIS CASTRO
BUILDING-Rough-Frame 10/30/2025 Corrections Issued LUIS CASTRO
Deputy Wood Construction 10/30/2025 Partial Approval LUIS CASTRO
Green Building Rough 10/30/2025 Not Ready for Inspection LUIS CASTRO
Interior/Exterior Lathing 11/13/2025 Approved LUIS CASTRO
Insulation 11/19/2025 Partial Approval LUIS CASTRO
Drywall Nailing 12/2/2025 Approved LUIS CASTRO
Green Building Rough 12/2/2025 Approved LUIS CASTRO
ELECTRICAL-Final 2/12/2026 Corrections Issued LUIS CASTRO
HVAC-Final 2/12/2026 Approved LUIS CASTRO
PLUMBING-Final 2/12/2026 Approved LUIS CASTRO
Service/Power Release 2/12/2026 Not Ready for Inspection LUIS CASTRO
BUILDING-Rough-Frame 2/24/2026 Approved LUIS CASTRO
ELECTRICAL-Final 2/24/2026 Approved LUIS CASTRO
Final 2/24/2026 Corrections Issued LUIS CASTRO
Footing/Foundation/Slab 2/24/2026 Approved LUIS CASTRO
Green Building Final 2/24/2026 Approved LUIS CASTRO
HVAC-Final 2/24/2026 Approved LUIS CASTRO
PLUMBING-Final 2/24/2026 Approved LUIS CASTRO
SGSOV-Seismic Gas S/O Valve 2/24/2026 SGSOV Approved LUIS CASTRO
Smoke Detectors 2/24/2026 Approved LUIS CASTRO
Final 2/27/2026 OK to Issue CofO LUIS CASTRO