1768 E 103RD PL 90002
Certificate Information: 1768 E 103RD PL 90002
- Application / Permit
- 25014-10000-01554
- Plan Check / Job No.
- B25LA13812
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN. 1ST AND 2ND FLOOR ADDITION TO EXISTING 1-STORY DETACHED ADU PER LAMC 12.22 A.33(b)(1) "COMPLY WITH DEPARTMENT ORDER effective date 06/14/2023. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
- Permit Issued
- Issued on 8/13/2025
- Issuing Office
- Current Status
- CofO in Progress on 6/2/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/18/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/8/2025 | ALEXANDER JOO |
| Corrections Issued | 5/12/2025 | ALEXANDER JOO |
| Quality Review Completed | 5/15/2025 | GARO TELMI |
| Applicant returned to address corrections | 6/30/2025 | ALEXANDER JOO |
| Applicant returned to address corrections | 7/29/2025 | ALEXANDER JOO |
| Applicant returned to address corrections | 8/5/2025 | ALEXANDER JOO |
| Plan Check Approved | 8/13/2025 | ALEXANDER JOO |
| Issued | 8/13/2025 | APPLICANT |
| CofO in Progress | 6/2/2026 | KEITH EDGHILL |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 5/22/2025 | MICHAEL BROWN |
| Miscellaneous | Cleared | 6/16/2025 | JACQUELINE TORRES |
| Eng Process Fee Ord 176,300 | Cleared | 8/6/2025 | MICHAEL BROWN |
| Sewer availability | Cleared | 8/7/2025 | MICHAEL BROWN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Southerland,, Richard Charles; Lic. No.: C88965 | 2335 E COLORADO BLVD SUITE 115, # 170 PASADENA, CA 91107 |
Inspector Information
| KELLY WARNER, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
| PAUL BECKER, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
| KEITH EDGHILL, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
| DANIEL GONZALEZ, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/25/2025 | Conditional Approval | ANSON MAGLASANG |
| Footing/Foundation/Slab | 8/26/2025 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 8/26/2025 | Approved | ANTHONY EGSON |
| Sewer | 8/26/2025 | Partial Approval | ANTHONY EGSON |
| Footing/Foundation/Slab | 8/29/2025 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 9/9/2025 | Corrections Issued | KEITH EDGHILL |
| Pre-Inspection | 9/9/2025 | Approved | KEITH EDGHILL |
| Footing/Foundation/Slab | 9/11/2025 | Partial Approval | KEITH EDGHILL |
| Floor/Roof Diaphrgm/Shear Wall | 10/9/2025 | Conditional Approval | KEITH EDGHILL |
| Insulation | 10/9/2025 | Not Ready for Inspection | KEITH EDGHILL |
| BUILDING-Rough-Frame | 10/22/2025 | No Access for Inspection | KEITH EDGHILL |
| Green Building Rough | 10/22/2025 | No Access for Inspection | KEITH EDGHILL |
| Wood Frame | 10/22/2025 | No Access for Inspection | KEITH EDGHILL |
| Wood Frame | 10/23/2025 | Corrections Issued | KEITH EDGHILL |
| Floor/Roof Diaphrgm/Shear Wall | 1/27/2026 | Approved | KEITH EDGHILL |
| BUILDING-Rough-Frame | 2/13/2026 | Approved | KEITH EDGHILL |
| ELECTRICAL-Rough | 2/13/2026 | Approved | KEITH EDGHILL |
| Green Building Rough | 2/13/2026 | Approved | KEITH EDGHILL |
| HVAC-Rough | 2/13/2026 | Approved | KEITH EDGHILL |
| PLUMBING-Rough | 2/13/2026 | Corrections Issued | KEITH EDGHILL |
| Interior/Exterior Lathing | 2/25/2026 | Partial Approval | KEITH EDGHILL |
| PLUMBING-Rough | 2/25/2026 | Approved | KEITH EDGHILL |
| Shower Pan | 2/25/2026 | Approved | KEITH EDGHILL |
| Insulation | 3/9/2026 | Approved | KEITH EDGHILL |
| Interior/Exterior Lathing | 3/9/2026 | Approved | KEITH EDGHILL |
| Drywall Nailing | 3/19/2026 | Approved | KEITH EDGHILL |
| ELECTRICAL-Final | 5/18/2026 | Approved | KEITH EDGHILL |
| Final | 5/18/2026 | Corrections Issued | KEITH EDGHILL |
| Footing/Foundation/Slab | 5/18/2026 | Approved | KEITH EDGHILL |
| Green Building Final | 5/18/2026 | Corrections Issued | KEITH EDGHILL |
| HVAC-Final | 5/18/2026 | Approved | KEITH EDGHILL |
| PLUMBING-Final | 5/18/2026 | Approved | KEITH EDGHILL |
| SGSOV-Seismic Gas S/O Valve | 5/18/2026 | SGSOV Not Ready | KEITH EDGHILL |
| Smoke Detectors | 5/18/2026 | Corrections Issued | KEITH EDGHILL |
| Final | 5/21/2026 | Not Ready for Inspection | KEITH EDGHILL |
| Green Building Final | 5/21/2026 | Corrections Issued | KEITH EDGHILL |
| SGSOV-Seismic Gas S/O Valve | 5/21/2026 | SGSOV Not Ready | KEITH EDGHILL |
| Smoke Detectors | 5/21/2026 | Approved | KEITH EDGHILL |
| Final | 5/27/2026 | Not Ready for Inspection | KEITH EDGHILL |
| Green Building Final | 5/27/2026 | Not Ready for Inspection | KEITH EDGHILL |
| SGSOV-Seismic Gas S/O Valve | 5/27/2026 | SGSOV Not Ready | KEITH EDGHILL |
| Final | 6/1/2026 | OK to Issue CofO | KEITH EDGHILL |
| Gas Test | 6/1/2026 | Approved | KEITH EDGHILL |
| Green Building Final | 6/1/2026 | Approved | KEITH EDGHILL |
| SGSOV-Seismic Gas S/O Valve | 6/1/2026 | SGSOV Approved | KEITH EDGHILL |