24641 W GILMORE ST 91307
Certificate Information: 24641 W GILMORE ST 91307
- Application / Permit
- 25014-10000-01541
- Plan Check / Job No.
- B25LA13666
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition and Remodel to (E) Single Family Dwelling . Work per wood frame prescriptive provisions .
- Permit Issued
- Issued on 4/15/2025
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/19/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/8/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/8/2025 | JOHN MESIAS |
| Corrections Issued | 4/8/2025 | JOHN MESIAS |
| Plan Check Approved | 4/15/2025 | GEORGE ALVAREZ |
| Issued | 4/15/2025 | APPLICANT |
| CofO in Progress | 2/2/2026 | GEVORK IPCHYAN |
| Permit Finaled | 2/19/2026 | JOHN JANSON |
| CofO Issued | 2/19/2026 | JOHN JANSON |
| Permit Finaled | 2/19/2026 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/8/2025 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 4/8/2025 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 4/8/2025 | LEE GUILBEAUX |
| Grading Pre-Inspection | Cleared | 4/10/2025 | MICHAEL TEMPLE |
Contact Information
| Contractor | Abraham Building & Consulting Inc; Lic. No.: 1046696-B | 356 E AVENIDA DE LOS ARBOLES B33 THOUSAND OAKS, CA 91360 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 9/12/2025 | Approved | GEVORK IPCHYAN |
| Excavation/Setback/Form/Re-Bar | 9/16/2025 | Approved | GEVORK IPCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/24/2025 | Approved | JON MCHUGH |
| BUILDING-Rough-Frame | 10/3/2025 | Approved | GEVORK IPCHYAN |
| ELECTRICAL-Rough | 10/3/2025 | Approved | GEVORK IPCHYAN |
| Green Building Rough | 10/3/2025 | Approved | GEVORK IPCHYAN |
| HVAC-Rough | 10/3/2025 | Approved | GEVORK IPCHYAN |
| Interior/Exterior Lathing | 10/3/2025 | Partial Approval | GEVORK IPCHYAN |
| PLUMBING-Rough | 10/3/2025 | Approved | GEVORK IPCHYAN |
| Shower Pan | 10/3/2025 | Approved | GEVORK IPCHYAN |
| Insulation | 10/6/2025 | Approved | GEVORK IPCHYAN |
| Interior/Exterior Lathing | 10/6/2025 | Partial Approval | GEVORK IPCHYAN |
| Drywall Nailing | 10/8/2025 | Approved | GEVORK IPCHYAN |
| Final | 11/14/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| Footing/Foundation/Slab | 11/14/2025 | Approved | GEVORK IPCHYAN |
| Green Building Final | 11/14/2025 | Partial Approval | GEVORK IPCHYAN |
| SGSOV-Seismic Gas S/O Valve | 11/14/2025 | SGSOV Approved | GEVORK IPCHYAN |
| Smoke Detectors | 11/14/2025 | Approved | GEVORK IPCHYAN |
| ELECTRICAL-Final | 1/30/2026 | Approved | GEVORK IPCHYAN |
| Final | 1/30/2026 | OK to Issue CofO | GEVORK IPCHYAN |
| Green Building Final | 1/30/2026 | Approved | GEVORK IPCHYAN |
| HVAC-Final | 1/30/2026 | Approved | GEVORK IPCHYAN |
| PLUMBING-Final | 1/30/2026 | Approved | GEVORK IPCHYAN |