4516-4518 N MARY ELLEN AVE 91423
Certificate Information: 4516-4518 N MARY ELLEN AVE 91423
- Application / Permit
- 25014-10000-01500
- Plan Check / Job No.
- B25LA13183
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO (E) ONE STORY SFD TO BECOME A ONE STORY SFD W/ ATTACHED JUNIOR ADU PER GC & 66323(a)(1) AND 66333. NFPA 13D FIRE SPRINKLERS REQUIRED THROUGHOUT.
- Permit Issued
- Issued on 6/27/2025
- Issuing Office
- Current Status
- CofO in Progress on 7/28/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/4/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/10/2025 | SERGIO GUTIERREZ |
| Corrections Issued | 4/14/2025 | SERGIO GUTIERREZ |
| Quality Review Completed | 4/17/2025 | GARO TELMI |
| Applicant returned to address corrections | 5/29/2025 | SERGIO GUTIERREZ |
| Plan Check Approved | 6/26/2025 | SERGIO GUTIERREZ |
| Issued | 6/27/2025 | APPLICANT |
| CofO in Progress | 7/28/2026 | CHRISTOPHE COCHRAN |
Permit Application Clearance Information
| Address approval | Cleared | 4/16/2025 | RYAN CASTRO |
| Roof/Waste drainage to street | Cleared | 4/16/2025 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 4/17/2025 | RYAN CASTRO |
| Sewer availability | Cleared | 4/17/2025 | RYAN CASTRO |
| ZI | Cleared | 4/21/2025 | MATHEW QUAN |
| Hydrant and Access approval | Cleared | 4/22/2025 | PATRICK PEREZ |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: NA30383 | , |
| Contractor | Precise Home Builders Inc; Lic. No.: 515469-B | , |
| Engineer | Khakurel,, Samit; Lic. No.: NA96131 | , |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/11/2025 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 8/1/2025 | Partial Approval | CHRISTOPHE COCHRAN |
| Underground Mechanical | 8/1/2025 | Approved | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/8/2025 | Partial Approval | CHRISTOPHE COCHRAN |
| Insulation | 8/8/2025 | Partial Approval | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/9/2025 | Partial Approval | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 10/9/2025 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 10/15/2025 | Corrections Issued | JUAN VALENZUELA |
| HVAC-Rough | 10/15/2025 | Corrections Issued | JUAN VALENZUELA |
| HVAC-Rough | 10/20/2025 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 10/23/2025 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 10/27/2025 | Corrections Issued | CHRISTOPHE COCHRAN |
| Deputy Wood Construction | 10/27/2025 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 10/27/2025 | Approved | CHRISTOPHE COCHRAN |
| Green Building Rough | 10/27/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 10/31/2025 | Corrections Issued | MISAEL ESPARZA |
| Green Building Rough | 10/31/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Interior/Exterior Lathing | 10/31/2025 | Partial Approval | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 11/10/2025 | Corrections Issued | CHRISTOPHE COCHRAN |
| Green Building Rough | 11/10/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Insulation | 11/10/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 11/13/2025 | Approved | CHRISTOPHE COCHRAN |
| Green Building Rough | 11/13/2025 | Approved | CHRISTOPHE COCHRAN |
| Insulation | 11/13/2025 | Approved | CHRISTOPHE COCHRAN |
| Drywall Nailing | 11/18/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Drywall Nailing | 11/19/2025 | Approved | JACK KARGODORIAN |
| Shower Pan | 12/1/2025 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 12/4/2025 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Final | 3/11/2026 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| HVAC-Final | 3/11/2026 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Final | 3/11/2026 | Corrections Issued | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 3/23/2026 | SGSOV Not Ready | MATTHEW NELSON |
| ELECTRICAL-Final | 3/25/2026 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Final | 3/25/2026 | Corrections Issued | CHRISTOPHE COCHRAN |
| Green Building Final | 3/25/2026 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| PLUMBING-Final | 3/25/2026 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 3/25/2026 | SGSOV Approved | CHRISTOPHE COCHRAN |
| Smoke Detectors | 3/25/2026 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Final | 4/7/2026 | Corrections Issued | CHRISTOPHE COCHRAN |
| PLUMBING-Final | 4/7/2026 | Corrections Issued | CHRISTOPHE COCHRAN |
| ELECTRICAL-Final | 4/24/2026 | Approved | CHRISTOPHE COCHRAN |
| Final | 4/24/2026 | OK to Issue CofO | CHRISTOPHE COCHRAN |
| Green Building Final | 4/24/2026 | Approved | CHRISTOPHE COCHRAN |