1761 N SILVER LAKE BLVD 90026
Certificate Information: 1761 N SILVER LAKE BLVD 90026
- Application / Permit
- 25014-10000-01482
- Plan Check / Job No.
- B25LA13085
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- [ePlan] 2ND FLOOR ADDITION TO (E) (2)-STORY SFD WITH INT. AND EXT. STRUCTURAL REMODEL.
- Permit Issued
- Issued on 8/4/2025
- Issuing Office
- Current Status
- CofO Issued on 5/21/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/4/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/24/2025 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 5/1/2025 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 5/14/2025 | GARO TELMI |
| Applicant returned to address corrections | 6/10/2025 | MAHNAZ NOURHASHEMI |
| Applicant returned to address corrections | 7/6/2025 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 8/1/2025 | MAHNAZ NOURHASHEMI |
| Issued | 8/4/2025 | APPLICANT |
| CofO in Progress | 5/20/2026 | HAMIK HARTOUNIAN |
| Permit Finaled | 5/21/2026 | DEROLD HAUFF |
| CofO Issued | 5/21/2026 | DEROLD HAUFF |
| Permit Finaled | 5/21/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/5/2025 | DAVID LOPEZ |
| Roof/Waste drainage to street | Cleared | 5/5/2025 | DAVID LOPEZ |
| Tenant Habitability Plan | Cleared | 5/7/2025 | KORNEL LELEA |
| Grading Pre-Inspection | Cleared | 6/10/2025 | MAHNAZ NOURHASHEMI |
| GPI Written Notices | Cleared | 8/1/2025 | MAHNAZ NOURHASHEMI |
Contact Information
| Contractor | The Fix Construction Co; Lic. No.: 1049919-B | , |
| Contractor | The Fix Inc; Lic. No.: 1049919-B | , |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21731 VENTURA BLVD SUITE 110 WOODLAND HILLS, CA 91364 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 11/20/2025 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 11/20/2025 | Approved | HAMIK HARTOUNIAN |
| HVAC-Final | 12/26/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Wood Frame | 12/26/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/20/2026 | Corrections Issued | WILLIAM SIERRA |
| BUILDING-Rough-Frame | 2/9/2026 | Corrections Issued | HAMIK HARTOUNIAN |
| HVAC-Rough | 2/9/2026 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 2/13/2026 | Partial Approval | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 2/13/2026 | Partial Approval | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 2/23/2026 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Insulation | 2/23/2026 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 2/25/2026 | Approved | HAMIK HARTOUNIAN |
| Insulation | 2/25/2026 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 3/4/2026 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 3/4/2026 | Partial Approval | HAMIK HARTOUNIAN |
| Shower Pan | 3/4/2026 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Final | 4/22/2026 | Approved | HAMIK HARTOUNIAN |
| Final | 4/22/2026 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 4/22/2026 | Approved | HAMIK HARTOUNIAN |
| HVAC-Final | 4/22/2026 | Corrections Issued | HAMIK HARTOUNIAN |
| PLUMBING-Final | 4/22/2026 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 4/22/2026 | SGSOV Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 4/22/2026 | Approved | HAMIK HARTOUNIAN |
| Final | 5/12/2026 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Final | 5/15/2026 | Partial Inspection | HAMIK HARTOUNIAN |
| Final | 5/20/2026 | OK to Issue CofO | HAMIK HARTOUNIAN |