3718 W EDENHURST AVE 90039

Certificate Information: 3718 W EDENHURST AVE 90039

Application / Permit
25014-10000-01479
Plan Check / Job No.
B25LA13076
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan: convert 360 ft detached into an Accessory Dwelling Unit with Addition of 200 SF Per Ordinance and LAMC 12.22 A33(c) &(d).
Permit Issued
Issued on 5/28/2025
Issuing Office
Current Status
CofO Issued on 2/13/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/4/2025 APPLICANT
Assigned to Plan Check Engineer 4/8/2025 SUNMIN LEE
Corrections Issued 4/8/2025 SUNMIN LEE
Plan Check Approved 5/27/2025 ZAW HAN
Issued 5/28/2025 APPLICANT
CofO in Progress 2/11/2026 CHARLES BOGHOSKHAN
Permit Finaled 2/13/2026 DEROLD HAUFF
CofO Issued 2/13/2026 DEROLD HAUFF
Permit Finaled 2/13/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/9/2025 RYAN CASTRO
Roof/Waste drainage to street Cleared 4/9/2025 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 4/14/2025 RYAN CASTRO
Sewer availability Cleared 4/14/2025 RYAN CASTRO
ZI Cleared 4/22/2025 DAVID URITA

Contact Information

Architect Dembsky,, Amit; Lic. No.: NA30383       ,
Contractor Villa Remodeling & Painting Inc; Lic. No.: 1075941-B       ,

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/14/2025 Corrections Issued NICHOLAS LOPEZ
Deputy Drilled-In Anchors 8/28/2025 Conditional Approval REGINA MENDEZ
Footing/Foundation/Slab 8/28/2025 Approved NICHOLAS LOPEZ
PLUMBING-Rough 9/9/2025 Partial Approval NICHOLAS LOPEZ
Footing/Foundation/Slab 9/12/2025 Approved NICHOLAS LOPEZ
Floor/Roof Diaphrgm/Shear Wall 9/26/2025 Partial Approval NICHOLAS LOPEZ
ELECTRICAL-Rough 10/17/2025 Approved NICHOLAS LOPEZ
Floor/Roof Diaphrgm/Shear Wall 10/17/2025 Approved NICHOLAS LOPEZ
PLUMBING-Rough 10/17/2025 Approved NICHOLAS LOPEZ
Sewer 10/17/2025 Approved NICHOLAS LOPEZ
Underground Mechanical 10/17/2025 Approved NICHOLAS LOPEZ
BUILDING-Rough-Frame 10/30/2025 Approved NICHOLAS LOPEZ
Green Building Rough 10/30/2025 Approved NICHOLAS LOPEZ
HVAC-Rough 10/30/2025 Approved NICHOLAS LOPEZ
Interior/Exterior Lathing 10/30/2025 Approved NICHOLAS LOPEZ
Insulation 11/7/2025 Approved NICHOLAS LOPEZ
Drywall Nailing 11/14/2025 Approved NICHOLAS LOPEZ
ELECTRICAL-Final 1/23/2026 Corrections Issued NICHOLAS LOPEZ
Final 1/23/2026 Corrections Issued NICHOLAS LOPEZ
Green Building Final 1/23/2026 Not Ready for Inspection NICHOLAS LOPEZ
HVAC-Final 1/23/2026 Approved NICHOLAS LOPEZ
PLUMBING-Final 1/23/2026 Approved NICHOLAS LOPEZ
SGSOV-Seismic Gas S/O Valve 1/23/2026 SGSOV Not Ready NICHOLAS LOPEZ
Smoke Detectors 1/23/2026 Approved NICHOLAS LOPEZ
Final 2/10/2026 OK to Issue CofO NICHOLAS LOPEZ
Green Building Final 2/10/2026 Approved NICHOLAS LOPEZ
SGSOV-Seismic Gas S/O Valve 2/10/2026 SGSOV Approved NICHOLAS LOPEZ