3714 S ARLINGTON AVE 90018
Certificate Information: 3714 S ARLINGTON AVE 90018
- Application / Permit
- 25014-10000-01471
- Plan Check / Job No.
- B25LA13030
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERSION OF EXISTING GARAGE TO A DETACHED ACCESSORY DWELLING UNIT
- Permit Issued
- Issued on 6/4/2025
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/17/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/3/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/9/2025 | LUKE GONZALES |
| Corrections Issued | 4/10/2025 | LUKE GONZALES |
| Building Plans Picked Up | 4/11/2025 | APPLICANT |
| Applicant returned to address corrections | 4/25/2025 | CARLOS MONTES |
| Plan Check Approved | 6/4/2025 | SUNMIN LEE |
| Issued | 6/4/2025 | APPLICANT |
| CofO in Progress | 10/16/2025 | SABAS ALONSO |
| Permit Finaled | 10/17/2025 | DEROLD HAUFF |
| CofO Issued | 10/17/2025 | DEROLD HAUFF |
| Permit Finaled | 10/17/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/18/2025 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 4/18/2025 | RYAN CASTRO |
| Roof/Waste drainage to street | Cleared | 4/18/2025 | RYAN CASTRO |
| Tenant Habitability Plan | Cleared | 4/23/2025 | KORNEL LELEA |
| Sewer availability | Cleared | 4/29/2025 | JEANIE LAM |
| HPOZ | Cleared | 5/20/2025 | DANIEL MATA |
| Construction near power lines | Cleared | 6/3/2025 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Muwanes,, David; Lic. No.: C77659 | PO BOX 670 SANTA MONICA, CA 90406 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/6/2025 | Approved | MICHAEL LEWIS |
| Footing/Foundation/Slab | 6/20/2025 | Not Ready for Inspection | SABAS ALONSO |
| Deputy Drilled-In Anchors | 6/23/2025 | Conditional Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 6/24/2025 | Partial Inspection | SABAS ALONSO |
| Footing/Foundation/Slab | 6/27/2025 | Partial Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 7/10/2025 | Approved | SABAS ALONSO |
| Underground Mechanical | 7/10/2025 | Partial Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 7/22/2025 | Approved | SABAS ALONSO |
| Underground Mechanical | 7/22/2025 | Approved | SABAS ALONSO |
| ELECTRICAL-Rough | 8/11/2025 | Corrections Issued | SABAS ALONSO |
| HVAC-Rough | 8/11/2025 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 8/11/2025 | Corrections Issued | SABAS ALONSO |
| ELECTRICAL-Rough | 8/13/2025 | Approved | ANTHONY RAMOS |
| Interior/Exterior Lathing | 8/13/2025 | Partial Approval | ANTHONY RAMOS |
| ELECTRICAL-Rough | 8/14/2025 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 8/28/2025 | Approved | BARRY HACHE |
| Green Building Rough | 8/28/2025 | Approved | BARRY HACHE |
| PLUMBING-Rough | 8/28/2025 | Approved | BARRY HACHE |
| Insulation | 9/4/2025 | Approved | RONNIE MEDINA |
| Drywall Nailing | 9/9/2025 | Approved | RONNIE MEDINA |
| Interior/Exterior Lathing | 9/9/2025 | Approved | RONNIE MEDINA |
| Drywall Nailing | 9/12/2025 | Approved | RONNIE MEDINA |
| Sewer | 9/25/2025 | Corrections Issued | SABAS ALONSO |
| ELECTRICAL-Final | 10/8/2025 | Approved | SABAS ALONSO |
| Final | 10/8/2025 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 10/8/2025 | Approved | SABAS ALONSO |
| HVAC-Final | 10/8/2025 | Not Ready for Inspection | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 10/8/2025 | SGSOV Approved | SABAS ALONSO |
| Smoke Detectors | 10/8/2025 | Approved | SABAS ALONSO |
| Final | 10/10/2025 | Not Ready for Inspection | SABAS ALONSO |
| Final | 10/16/2025 | OK to Issue CofO | SABAS ALONSO |