5213 S GRAMERCY PL 90062

Certificate Information: 5213 S GRAMERCY PL 90062

Application / Permit
25014-10000-01454
Plan Check / Job No.
B25LA12876
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Garage Conversion into ADU and Addition PER LAMC 12.22 A.33 (c) AND (d)
Permit Issued
Issued on 10/21/2025
Issuing Office
Current Status
Issued on 10/21/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/3/2025 APPLICANT
Assigned to Plan Check Engineer 4/8/2025 DANIEL SANJUAN
Corrections Issued 4/8/2025 DANIEL SANJUAN
Plan Check Approved 9/20/2025 ADAM HEGAZI
Issued 10/21/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 5/17/2025 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 5/17/2025 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 5/17/2025 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 5/20/2025 LEE GUILBEAUX
Sewer availability Cleared 5/20/2025 LEE GUILBEAUX
Construction near power lines Cleared 8/27/2025 RIDWAN HARDY

Contact Information

Contractor Mav Construction Inc; Lic. No.: 1079264-B       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/9/2026 Conditional Approval BARRY HACHE
Footing/Foundation/Slab 2/10/2026 Corrections Issued BARRY HACHE
PLUMBING-Rough 2/10/2026 Not Ready for Inspection BARRY HACHE
Sewer 2/10/2026 Approved BARRY HACHE
Footing/Foundation/Slab 2/17/2026 Corrections Issued BARRY HACHE
Gas Test 2/17/2026 Not Ready for Inspection BARRY HACHE
Footing/Foundation/Slab 2/24/2026 Corrections Issued BARRY HACHE
PLUMBING-Rough 2/24/2026 Corrections Issued BARRY HACHE
Underground Mechanical 2/24/2026 Approved BARRY HACHE
Footing/Foundation/Slab 2/26/2026 Approved BARRY HACHE
PLUMBING-Rough 2/26/2026 Partial Approval BARRY HACHE
Sewer 2/26/2026 Approved BARRY HACHE
ELECTRICAL-Rough 4/8/2026 Corrections Issued MICHAEL LEWIS
HVAC-Rough 4/8/2026 Corrections Issued MICHAEL LEWIS
PLUMBING-Rough 4/8/2026 Corrections Issued MICHAEL LEWIS
ELECTRICAL-Rough 4/14/2026 Not Ready for Inspection RAUL BARAJAS
HVAC-Rough 4/14/2026 Not Ready for Inspection RAUL BARAJAS
PLUMBING-Rough 4/14/2026 Corrections Issued RAUL BARAJAS
BUILDING-Rough-Frame 4/22/2026 Approved RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 4/22/2026 Conditional Approval RAUL BARAJAS
Green Building Rough 4/22/2026 Approved RAUL BARAJAS
Insulation 4/29/2026 Corrections Issued ALEX COLIN
Interior/Exterior Lathing 4/29/2026 Partial Approval ALEX COLIN
Drywall Nailing 5/5/2026 Approved STUART CHAPMAN
Insulation 5/5/2026 Approved STUART CHAPMAN