5213 S GRAMERCY PL 90062
Certificate Information: 5213 S GRAMERCY PL 90062
- Application / Permit
- 25014-10000-01454
- Plan Check / Job No.
- B25LA12876
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Garage Conversion into ADU and Addition PER LAMC 12.22 A.33 (c) AND (d)
- Permit Issued
- Issued on 10/21/2025
- Issuing Office
- Current Status
- Issued on 10/21/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/3/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/8/2025 | DANIEL SANJUAN |
| Corrections Issued | 4/8/2025 | DANIEL SANJUAN |
| Plan Check Approved | 9/20/2025 | ADAM HEGAZI |
| Issued | 10/21/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 5/17/2025 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 5/17/2025 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 5/17/2025 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 5/20/2025 | LEE GUILBEAUX |
| Sewer availability | Cleared | 5/20/2025 | LEE GUILBEAUX |
| Construction near power lines | Cleared | 8/27/2025 | RIDWAN HARDY |
Contact Information
| Contractor | Mav Construction Inc; Lic. No.: 1079264-B | , |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/9/2026 | Conditional Approval | BARRY HACHE |
| Footing/Foundation/Slab | 2/10/2026 | Corrections Issued | BARRY HACHE |
| PLUMBING-Rough | 2/10/2026 | Not Ready for Inspection | BARRY HACHE |
| Sewer | 2/10/2026 | Approved | BARRY HACHE |
| Footing/Foundation/Slab | 2/17/2026 | Corrections Issued | BARRY HACHE |
| Gas Test | 2/17/2026 | Not Ready for Inspection | BARRY HACHE |
| Footing/Foundation/Slab | 2/24/2026 | Corrections Issued | BARRY HACHE |
| PLUMBING-Rough | 2/24/2026 | Corrections Issued | BARRY HACHE |
| Underground Mechanical | 2/24/2026 | Approved | BARRY HACHE |
| Footing/Foundation/Slab | 2/26/2026 | Approved | BARRY HACHE |
| PLUMBING-Rough | 2/26/2026 | Partial Approval | BARRY HACHE |
| Sewer | 2/26/2026 | Approved | BARRY HACHE |
| ELECTRICAL-Rough | 4/8/2026 | Corrections Issued | MICHAEL LEWIS |
| HVAC-Rough | 4/8/2026 | Corrections Issued | MICHAEL LEWIS |
| PLUMBING-Rough | 4/8/2026 | Corrections Issued | MICHAEL LEWIS |
| ELECTRICAL-Rough | 4/14/2026 | Not Ready for Inspection | RAUL BARAJAS |
| HVAC-Rough | 4/14/2026 | Not Ready for Inspection | RAUL BARAJAS |
| PLUMBING-Rough | 4/14/2026 | Corrections Issued | RAUL BARAJAS |
| BUILDING-Rough-Frame | 4/22/2026 | Approved | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 4/22/2026 | Conditional Approval | RAUL BARAJAS |
| Green Building Rough | 4/22/2026 | Approved | RAUL BARAJAS |
| Insulation | 4/29/2026 | Corrections Issued | ALEX COLIN |
| Interior/Exterior Lathing | 4/29/2026 | Partial Approval | ALEX COLIN |
| Drywall Nailing | 5/5/2026 | Approved | STUART CHAPMAN |
| Insulation | 5/5/2026 | Approved | STUART CHAPMAN |