7410 S DUNFIELD AVE 90045
Certificate Information: 7410 S DUNFIELD AVE 90045
- Application / Permit
- 25014-10000-01439
- Plan Check / Job No.
- B25LA12774
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL AND ADDITION TO (E) 1 STORY SFD TO CREATE 2 STORY SFD W/ ATT GARAGE.
- Permit Issued
- Issued on 7/14/2025
- Issuing Office
- Metro
- Current Status
- Issued on 7/14/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/2/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/17/2025 | HERNAN ARREOLA |
| Corrections Issued | 4/28/2025 | HERNAN ARREOLA |
| Quality Review Completed | 4/29/2025 | KEN GILL |
| Building Plans Picked Up | 5/6/2025 | APPLICANT |
| Plan Check Approved | 7/14/2025 | HERNAN ARREOLA |
| Issued | 7/14/2025 | APPLICANT |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 5/22/2025 | MICHAEL TEMPLE |
| Permit | Cleared | 5/23/2025 | MICHAEL BROWN |
| Roof/Waste drainage to street | Cleared | 5/23/2025 | MICHAEL BROWN |
| Eng Process Fee Ord 176,300 | Cleared | 5/27/2025 | MICHAEL BROWN |
| Sewer availability | Cleared | 5/27/2025 | MICHAEL BROWN |
| GPI Written Notices | Cleared | 7/2/2025 | HERNAN ARREOLA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yenjai,, Seree; Lic. No.: C73151 | 3249 SHADYLAWN DRIVE DUARTE, CA 91010 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Interior/Exterior Lathing | 6/9/2026 |
Inspection Request History
| Footing/Foundation/Slab | 8/25/2025 | Partial Approval | RUBEN RIVAS |
| Deputy Drilled-In Anchors | 8/29/2025 | Conditional Approval | DAVID FEILER |
| Deputy Steel/Welding | 9/2/2025 | Partial Approval | RUBEN RIVAS |
| Footing/Foundation/Slab | 9/2/2025 | Approved | RUBEN RIVAS |
| Floor/Roof Diaphrgm/Shear Wall | 9/12/2025 | Partial Approval | RUBEN RIVAS |
| Underground Mechanical | 9/12/2025 | Approved | RUBEN RIVAS |
| Floor/Roof Diaphrgm/Shear Wall | 9/17/2025 | Partial Approval | MICHAEL ALLEN |
| Floor/Roof Diaphrgm/Shear Wall | 10/6/2025 | Partial Approval | RUBEN RIVAS |
| PLUMBING-Rough | 12/11/2025 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/23/2025 | Partial Approval | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/12/2026 | Corrections Issued | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/14/2026 | Not Ready for Inspection | ANTHONY EGSON |
| Footing/Foundation/Slab | 2/13/2026 | Approved | ANTHONY EGSON |
| ELECTRICAL-Rough | 3/26/2026 | Approved | ANTHONY EGSON |
| HVAC-Rough | 4/9/2026 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 4/15/2026 | Partial Approval | MICHAEL ALLEN |
| Green Building Rough | 4/15/2026 | Partial Approval | MICHAEL ALLEN |
| Final | 4/28/2026 | Corrections Issued | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 4/28/2026 | Partial Approval | TEMISTOCLES CAAL |
| Special/Order Compliance | 4/28/2026 | Partial Inspection | BOBBY KEY |
| Insulation | 5/12/2026 | Approved | MORRIS JACKSON |
| Verify Sprinkler Sign Off | 5/12/2026 | Approved | MORRIS JACKSON |
| BUILDING-Rough-Frame | 5/19/2026 | Approved | MORRIS JACKSON |
| Drywall Nailing | 5/19/2026 | Approved | MORRIS JACKSON |
| Green Building Rough | 5/19/2026 | Approved | MORRIS JACKSON |
| Shower Pan | 5/19/2026 | Approved | MORRIS JACKSON |