1258 N SANBORN AVE 90029

Certificate Information: 1258 N SANBORN AVE 90029

Application / Permit
25014-10000-01368
Plan Check / Job No.
B25LA12088
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
Eplan: Major remodel and addition to (E) 1 story duplex. Rear Building.
Permit Issued
Issued on 6/3/2026
Issuing Office
Current Status
Issued on 6/3/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/9/2025 APPLICANT
Assigned to Plan Check Engineer 4/24/2025 RACHEL BEYENE
Corrections Issued 5/5/2025 RACHEL BEYENE
Quality Review Completed 5/20/2025 HERNAN ARREOLA
Applicant returned to address corrections 8/20/2025 RACHEL BEYENE
Applicant returned to address corrections 9/4/2025 RACHEL BEYENE
Applicant returned to address corrections 9/11/2025 RACHEL BEYENE
Applicant returned to address corrections 5/14/2026 RACHEL BEYENE
Plan Check Approved 5/26/2026 RAHEL BEYENE
Issued 6/3/2026 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 6/27/2025 XOCHITL ARQUIETA
Eng Process Fee Ord 176,300 Cleared 7/12/2025 JESSICA OPINION
Sewer availability Cleared 7/12/2025 JESSICA OPINION
"Q" conditions Cleared 7/15/2025 JACQUELINE TORRES
Grading Pre-Inspection Cleared 9/11/2025 RAHEL BEYENE
Tenant Habitability Plan Cleared 5/21/2026 KORNEL LELEA

Contact Information

Contractor Adu Rc Builders; Lic. No.: 1080967-B       ,
Contractor Ca Construction Group Inc; Lic. No.: 1080967-B       ,
Engineer Aalam,, Yahya; Lic. No.: C94318 3111 4TH ST APT 401      SANTA MONICA, CA 90405
Engineer Nalbandian,, Serop Krekor; Lic. No.: M39801 1236 N COLUMBUS AVE UNIT 4      GLENDALE, CA 91202

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 7/23/2026 Partial Approval HAMIK HARTOUNIAN
Deputy Drilled-In Anchors 7/29/2026 No Result Entered ALIZAH MAYAGOITIA
Excavation/Setback/Form/Re-Bar 7/30/2026 Partial Approval DAVID WILLIAMS
Footing/Foundation/Slab 7/30/2026 Partial Approval DAVID WILLIAMS