4538 W FRANKLIN AVE 90027
Certificate Information: 4538 W FRANKLIN AVE 90027
- Application / Permit
- 25014-10000-01361
- Plan Check / Job No.
- B25LA12003
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan CONVERT EXISTING 2-CAR GARAGE TO AN ADU, WITH 2ND STORY ADDITION. DETACHED ADU LAMC 12.22 A.33 (c) and (d).
- Permit Issued
- Issued on 11/19/2025
- Issuing Office
- Current Status
- Issued on 11/19/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/27/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/10/2025 | ADRIANA LOPEZ |
| Corrections Issued | 4/30/2025 | ADRIANA LOPEZ |
| Quality Review Completed | 5/19/2025 | JOSE RODRIGUEZ |
| Applicant returned to address corrections | 6/30/2025 | ADRIANA LOPEZ |
| Applicant returned to address corrections | 8/19/2025 | ADRIANA LOPEZ |
| Applicant returned to address corrections | 9/23/2025 | ADRIANA LOPEZ |
| Plan Check Approved | 11/4/2025 | ADRIANA LOPEZ |
| Issued | 11/19/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 5/30/2025 | SAFA JAVANMARDI |
| Roof/Waste drainage to street | Cleared | 6/2/2025 | SAFA JAVANMARDI |
| Eng Process Fee Ord 176,300 | Cleared | 6/4/2025 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 6/4/2025 | SAFA JAVANMARDI |
| Grading Pre-Inspection | Cleared | 6/9/2025 | JONATHAN HOM |
| GPI Written Notices | Cleared | 8/19/2025 | ADRIANA LOPEZ |
| Specific Plan | Cleared | 10/10/2025 | NASHYA JENSEN |
| ZI | Cleared | 10/10/2025 | NASHYA JENSEN |
Contact Information
| Contractor | Sb Construction & Remodeling Inc; Lic. No.: 1061509-B | , |
| Engineer | Melchor,, Oscar Elias; Lic. No.: NA76828 | , |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/22/2025 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 3/5/2026 | Corrections Issued | JEFFREY MEAD |
| PLUMBING-Rough | 3/5/2026 | Approved | JEFFREY MEAD |
| Footing/Foundation/Slab | 4/1/2026 | Approved | ENRIQUE MIRELES |
| Wood Frame | 4/17/2026 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 4/29/2026 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 5/27/2026 | Not Ready for Inspection | ENRIQUE MIRELES |
| HVAC-Rough | 5/27/2026 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 5/27/2026 | Approved | ENRIQUE MIRELES |
| Insulation | 6/1/2026 | Approved | ENRIQUE MIRELES |