4538 W FRANKLIN AVE 90027

Certificate Information: 4538 W FRANKLIN AVE 90027

Application / Permit
25014-10000-01361
Plan Check / Job No.
B25LA12003
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan CONVERT EXISTING 2-CAR GARAGE TO AN ADU, WITH 2ND STORY ADDITION. DETACHED ADU LAMC 12.22 A.33 (c) and (d).
Permit Issued
Issued on 11/19/2025
Issuing Office
Current Status
Issued on 11/19/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/27/2025 APPLICANT
Assigned to Plan Check Engineer 4/10/2025 ADRIANA LOPEZ
Corrections Issued 4/30/2025 ADRIANA LOPEZ
Quality Review Completed 5/19/2025 JOSE RODRIGUEZ
Applicant returned to address corrections 6/30/2025 ADRIANA LOPEZ
Applicant returned to address corrections 8/19/2025 ADRIANA LOPEZ
Applicant returned to address corrections 9/23/2025 ADRIANA LOPEZ
Plan Check Approved 11/4/2025 ADRIANA LOPEZ
Issued 11/19/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 5/30/2025 SAFA JAVANMARDI
Roof/Waste drainage to street Cleared 6/2/2025 SAFA JAVANMARDI
Eng Process Fee Ord 176,300 Cleared 6/4/2025 SAFA JAVANMARDI
Sewer availability Cleared 6/4/2025 SAFA JAVANMARDI
Grading Pre-Inspection Cleared 6/9/2025 JONATHAN HOM
GPI Written Notices Cleared 8/19/2025 ADRIANA LOPEZ
Specific Plan Cleared 10/10/2025 NASHYA JENSEN
ZI Cleared 10/10/2025 NASHYA JENSEN

Contact Information

Contractor Sb Construction & Remodeling Inc; Lic. No.: 1061509-B       ,
Engineer Melchor,, Oscar Elias; Lic. No.: NA76828       ,

Inspector Information

ENRIQUE MIRELES, (213) 202-3438 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/22/2025 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 3/5/2026 Corrections Issued JEFFREY MEAD
PLUMBING-Rough 3/5/2026 Approved JEFFREY MEAD
Footing/Foundation/Slab 4/1/2026 Approved ENRIQUE MIRELES
Wood Frame 4/17/2026 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 4/29/2026 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 5/27/2026 Not Ready for Inspection ENRIQUE MIRELES
HVAC-Rough 5/27/2026 Approved ENRIQUE MIRELES
PLUMBING-Rough 5/27/2026 Approved ENRIQUE MIRELES
Insulation 6/1/2026 Approved ENRIQUE MIRELES