- Work Description
- MAJOR ALTERATION AND ADDITION TO (E) SINGLE FAMILY DWELLING, INCLUDING REMODEL AND RECONFIGURE FLOOR PLAN LAYOUT, REFRAME ROOF WITH ROOF TRUSSES. FIRE SPRINKLER THROUGHOUT THE BUILDING
- Permit Issued
- Issued on 10/3/2025
- Issuing Office
- Metro
- Current Status
- Issued on 10/3/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/27/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/28/2025 | LUKE GONZALES |
| Corrections Issued | 3/29/2025 | LUKE GONZALES |
| Building Plans Picked Up | 4/3/2025 | APPLICANT |
| Plan Check Approved | 10/3/2025 | MINA HABILI |
| Issued | 10/3/2025 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/14/2025 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 4/14/2025 | WALLIE JONG |
| Sewer availability | Cleared | 4/14/2025 | WALLIE JONG |
| Miscellaneous | Cleared | 9/24/2025 | NIKTA MOUSAVI |
| Flood clearance | Cleared | 9/29/2025 | TUYEN LE |
| GPI Written Notices | Cleared | 10/2/2025 | LANNY MERRICK |
| Grading Pre-Inspection | Cleared | 10/3/2025 | LUKE GONZALES |
Contact Information
| Contractor | Buzz - Ann Construction; Lic. No.: 777980-B | P O BOX 18661 LOS ANGELES, CA 900180661 |
| Engineer | Hernandez,, Arturo; Lic. No.: C72517 | 8653 SHAKESPEARE LANE FRISCO, TX 75034 |
| Engineer | Pham,, Duc Huy; Lic. No.: C33819 | 16691 MYTINGER LN HUNTINGTON BEACH, CA 92647 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 10/30/2025 | Corrections Issued | KIRK SANDERS |
| Deputy Drilled-In Anchors | 10/30/2025 | Conditional Approval | DAVID FEILER |
| Footing/Foundation/Slab | 10/30/2025 | Corrections Issued | KIRK SANDERS |
| BUILDING-Rough-Frame | 12/11/2025 | Corrections Issued | KIRK SANDERS |
| Excavation/Setback/Form/Re-Bar | 12/11/2025 | Approved | KIRK SANDERS |
| Footing/Foundation/Slab | 12/11/2025 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 1/13/2026 | Partial Approval | KIRK SANDERS |
| PLUMBING-Rough | 1/13/2026 | Partial Approval | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 1/26/2026 | Partial Approval | ARAM AVEDISIAN |
| Insulation | 1/26/2026 | Partial Approval | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/13/2026 | Partial Approval | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 3/24/2026 | Partial Approval | RYAN SALAZAR |
| ELECTRICAL-Rough | 3/24/2026 | Approved | RYAN SALAZAR |
| FLOOD-Proofing Certificate | 3/24/2026 | Approved | RYAN SALAZAR |
| Green Building Rough | 3/24/2026 | Not Ready for Inspection | RYAN SALAZAR |
| HVAC-Rough | 3/24/2026 | Conditional Approval | RYAN SALAZAR |
| PLUMBING-Rough | 3/24/2026 | Approved | RYAN SALAZAR |
| Wood Frame | 3/24/2026 | Approved | RYAN SALAZAR |
| Green Building Rough | 5/7/2026 | Approved | MICHAEL LEWIS |
| HVAC-Rough | 5/7/2026 | Approved | MICHAEL LEWIS |
| Insulation | 5/7/2026 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 5/7/2026 | Approved | MICHAEL LEWIS |
| PLUMBING-Rough | 5/7/2026 | Corrections Issued | MICHAEL LEWIS |
| Shower Pan | 5/7/2026 | Corrections Issued | MICHAEL LEWIS |
| ELECTRICAL-Rough | 5/12/2026 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 5/12/2026 | Approved | ANTHONY EGSON |
| Shower Pan | 5/12/2026 | Approved | ANTHONY EGSON |
| Drywall Nailing | 5/19/2026 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 5/22/2026 | Partial Approval | ARAM AVEDISIAN |