14212 W SYLVAN ST 1-2 91401
Certificate Information: 14212 W SYLVAN ST 1-2 91401
- Application / Permit
- 25014-10000-01347
- Plan Check / Job No.
- B24VN25291
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: Addition to existing garage and convert to 2-ADUs
- Permit Issued
- Issued on 7/18/2025
- Issuing Office
- Current Status
- CofO Issued on 4/7/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/26/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/9/2025 | ARSALAN SHABESTARI |
| Assigned to Zoning Architect | 1/9/2025 | HAYDON CHAN |
| Corrections Issued | 1/14/2025 | ARSALAN SHABESTARI |
| Quality Review Completed | 1/28/2025 | HERNAN ARREOLA |
| Applicant returned to address corrections | 6/12/2025 | ARSALAN SHABESTARI |
| Plan Check Approved | 6/30/2025 | ARSALAN SHABESTARI |
| Issued | 7/18/2025 | APPLICANT |
| CofO in Progress | 2/18/2026 | VINCENT HANLEY |
| Permit Finaled | 4/7/2026 | RUBEN SALAS |
| CofO Issued | 4/7/2026 | RUBEN SALAS |
| Permit Finaled | 4/7/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 4/21/2025 | PATRICK PEREZ |
| Address approval | Cleared | 4/29/2025 | JOHN LIN |
| Roof/Waste drainage to street | Cleared | 4/29/2025 | JOHN LIN |
| Eng Process Fee Ord 176,300 | Cleared | 5/1/2025 | JOHN LIN |
| Sewer availability | Cleared | 5/1/2025 | JOHN LIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Gosen,, James; Lic. No.: NA43590 | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/5/2025 | Partial Approval | RYAN SALAZAR |
| Deputy Drilled-In Anchors | 9/9/2025 | Conditional Approval | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 9/9/2025 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 9/29/2025 | Approved | RYAN SALAZAR |
| ELECTRICAL-Rough | 9/29/2025 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 9/29/2025 | Approved | RYAN SALAZAR |
| Green Building Rough | 9/29/2025 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 9/29/2025 | Approved | RYAN SALAZAR |
| Insulation | 10/8/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Interior/Exterior Lathing | 10/8/2025 | Partial Approval | WAYNE REGESTER |
| Shower Pan | 10/8/2025 | Corrections Issued | WAYNE REGESTER |
| Insulation | 10/9/2025 | Approved | RYAN SALAZAR |
| Shower Pan | 10/9/2025 | Approved | RYAN SALAZAR |
| Drywall Nailing | 10/14/2025 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 10/14/2025 | Approved | RYAN SALAZAR |
| Sewer | 11/20/2025 | Approved | DAVID ANDERSON |
| Underground Mechanical | 11/20/2025 | Partial Approval | DAVID ANDERSON |
| ELECTRICAL-Rough | 12/22/2025 | Not Ready for Inspection | RYAN SALAZAR |
| HVAC-Rough | 12/22/2025 | Not Ready for Inspection | RYAN SALAZAR |
| PLUMBING-Rough | 12/22/2025 | Not Ready for Inspection | RYAN SALAZAR |
| Wood Frame | 12/22/2025 | Not Ready for Inspection | RYAN SALAZAR |
| ELECTRICAL-Final | 2/2/2026 | Approved | KIRK SANDERS |
| Final | 2/2/2026 | Corrections Issued | KIRK SANDERS |
| Green Building Final | 2/2/2026 | Approved | KIRK SANDERS |
| HVAC-Final | 2/2/2026 | Approved | KIRK SANDERS |
| PLUMBING-Final | 2/2/2026 | Corrections Issued | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 2/2/2026 | SGSOV Not Ready | KIRK SANDERS |
| Smoke Detectors | 2/2/2026 | Approved | KIRK SANDERS |
| Gas Test | 2/10/2026 | Approved | VINCENT HANLEY |
| Final | 2/17/2026 | OK to Issue CofO | VINCENT HANLEY |
| PLUMBING-Final | 2/17/2026 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 2/17/2026 | SGSOV Approved | VINCENT HANLEY |