10530 W PUTNEY ROAD 90064

Certificate Information: 10530 W PUTNEY ROAD 90064

Application / Permit
25014-10000-01307
Plan Check / Job No.
B25LA11426
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN. CONVERT PORTION OF (E) GARAGE TO ADU AND ADDITION TO ADU TO BUILD A ........SF ADU. PER LAMC 12.22 A.33(b)(1)
Permit Issued
Issued on 1/11/2026
Issuing Office
Current Status
Issued on 1/11/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/26/2025 APPLICANT
Assigned to Plan Check Engineer 3/28/2025 ALFREDO JARA
Corrections Issued 3/29/2025 ALFREDO JARA
Applicant returned to address corrections 9/11/2025 KAVIAN REFAHI
Plan Check Approved 10/17/2025 KAVIAN REFAHI
Issued 1/11/2026 APPLICANT

Permit Application Clearance Information

Address approval Cleared 4/9/2025 SAFA JAVANMARDI
Eng Process Fee Ord 176,300 Cleared 4/12/2025 SAFA JAVANMARDI
Roof/Waste drainage to street Cleared 4/12/2025 SAFA JAVANMARDI
Grading Pre-Inspection Cleared 4/25/2025 LANNY MERRICK
Sewer availability Cleared 4/26/2025 SAFA JAVANMARDI
Specific Plan Cleared 6/16/2025 PEDRO AYALA
Specific Plan Cleared 6/16/2025 PEDRO AYALA
Construction near power lines Cleared 8/21/2025 RIDWAN HARDY
GPI Written Notices Cleared 9/12/2025 ALFREDO JARA

Contact Information

Contractor Eberia Construction Inc; Lic. No.: 701330-B       ,
Engineer Yaprak,, Taskin Tolga; Lic. No.: C72927 562 31ST ST      MANHATTAN BEACH, CA 90266
Engineer Yaprak,, Taskin Tolga; Lic. No.: NA72927       ,

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

ELECTRICAL-Rough 6/9/2026   
Underground Mechanical 6/9/2026   

Inspection Request History

Underground Mechanical 1/21/2026 Approved MICHAEL ALLEN
Excavation/Setback/Form/Re-Bar 2/9/2026 Approved WILBER ROSALES
Footing/Foundation/Slab 2/9/2026 Approved WILBER ROSALES
METHANE-Barrier 2/9/2026 Approved WILBER ROSALES
METHANE-Subgrade 2/9/2026 Approved WILBER ROSALES
Floor/Roof Diaphrgm/Shear Wall 3/9/2026 Corrections Issued ASHLEY THOMPSON
Special/Order Compliance 3/9/2026 Corrections Issued ASHLEY THOMPSON
Floor/Roof Diaphrgm/Shear Wall 3/12/2026 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Rough 4/8/2026 Approved ASHLEY THOMPSON
HVAC-Rough 4/8/2026 Corrections Issued ASHLEY THOMPSON
PLUMBING-Rough 4/8/2026 Approved ASHLEY THOMPSON
Deputy Drilled-In Anchors 4/30/2026 Conditional Approval HERBERT GIRON
Deputy Wood Construction 4/30/2026 Conditional Approval DANIEL VERA
Floor/Roof Diaphrgm/Shear Wall 5/8/2026 Approved ASHLEY THOMPSON
BUILDING-Rough-Frame 5/19/2026 Approved WILBER ROSALES
Green Building Rough 5/19/2026 Approved WILBER ROSALES
HVAC-Rough 5/19/2026 Approved WILBER ROSALES
Interior/Exterior Lathing 5/19/2026 Partial Approval WILBER ROSALES
METHANE-Rough 5/19/2026 Approved WILBER ROSALES
Insulation 6/1/2026 Partial Approval ARAM AVEDISIAN