1182 N ANGELO DR 90210
Certificate Information: 1182 N ANGELO DR 90210
- Application / Permit
- 25014-10000-01296
- Plan Check / Job No.
- B25LA11245
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- One-story ground floor addition and interior remodel to (E) SFD
- Permit Issued
- Issued on 6/23/2025
- Issuing Office
- Current Status
- CofO Issued on 2/20/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/1/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/17/2025 | GEORGE JOLAKIAN |
| Corrections Issued | 4/21/2025 | GEORGE JOLAKIAN |
| Quality Review Completed | 5/2/2025 | HERNAN ARREOLA |
| Plan Check Approved | 6/16/2025 | GEORGE JOLAKIAN |
| Issued | 6/23/2025 | APPLICANT |
| CofO in Progress | 2/9/2026 | EVAN COOPER |
| Permit Finaled | 2/20/2026 | RICHARD STEINBACH |
| CofO Issued | 2/20/2026 | RICHARD STEINBACH |
| Permit Finaled | 2/20/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 4/22/2025 | JEREMY CHOK |
| BHO/Hillside ordinance | Cleared | 4/22/2025 | JEREMY CHOK |
| BHO/Hillside ordinance | Cleared | 4/22/2025 | JEREMY CHOK |
| Eng Process Fee Ord 176,300 | Cleared | 4/22/2025 | JEREMY CHOK |
| Roof/Waste drainage to street | Cleared | 4/22/2025 | JEREMY CHOK |
| Sewer availability | Cleared | 4/22/2025 | JEREMY CHOK |
| Grading Pre-Inspection | Cleared | 6/13/2025 | GEORGE JOLAKIAN |
Contact Information
| Contractor | Evan House Construction Inc; Lic. No.: 1087223-B | , |
| Engineer | Kile,, Johnny C; Lic. No.: C92658 | 3627 W 64TH STREET LOS ANGELES, CA 90043 |
Inspector Information
| CARLOS MATAMOROS, (310) 914-3878 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/10/2025 | Corrections Issued | SEAN HAUPT |
| ELECTRICAL-Rough | 7/14/2025 | Not Ready for Inspection | STEPHANIE SWANSON |
| PLUMBING-Rough | 7/14/2025 | Partial Approval | STEPHANIE SWANSON |
| Sewer | 7/14/2025 | Not Ready for Inspection | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 7/16/2025 | Approved | HENRY KIM |
| Special/Order Compliance | 7/16/2025 | Corrections Issued | HENRY KIM |
| ELECTRICAL-Rough | 7/17/2025 | Not Ready for Inspection | SEAN HAUPT |
| Gas Test | 8/4/2025 | Corrections Issued | SEAN HAUPT |
| PLUMBING-Rough | 8/4/2025 | Not Ready for Inspection | SEAN HAUPT |
| Wood Frame | 8/4/2025 | Not Ready for Inspection | SEAN HAUPT |
| ELECTRICAL-Rough | 8/11/2025 | Partial Approval | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 8/13/2025 | Not Ready for Inspection | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 8/19/2025 | Partial Approval | SEAN HAUPT |
| BUILDING-Rough-Frame | 8/25/2025 | Approved | SEAN HAUPT |
| Green Building Rough | 8/25/2025 | Approved | SEAN HAUPT |
| HVAC-Rough | 8/25/2025 | Approved | SEAN HAUPT |
| PLUMBING-Rough | 8/25/2025 | Approved | SEAN HAUPT |
| Insulation | 9/2/2025 | Approved | SEAN HAUPT |
| ELECTRICAL-Rough | 9/3/2025 | Corrections Issued | SEAN HAUPT |
| Drywall Nailing | 9/10/2025 | Partial Approval | SEAN HAUPT |
| Pre-Inspection | 9/19/2025 | Partial Approval | DANIEL VERA |
| Interior/Exterior Lathing | 9/22/2025 | Partial Approval | SEAN HAUPT |
| Pre-Inspection | 9/22/2025 | Partial Approval | SEAN HAUPT |
| Shower Pan | 9/22/2025 | Not Ready for Inspection | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 9/30/2025 | Approved | DANIEL VERA |
| Drywall Nailing | 10/8/2025 | Not Ready for Inspection | JAYLIN GRAVITTE |
| Interior/Exterior Lathing | 10/8/2025 | Approved | JAYLIN GRAVITTE |
| Special/Order Compliance | 10/8/2025 | Partial Approval | GEM DE OCAMPO |
| ELECTRICAL-Final | 1/21/2026 | Not Ready for Inspection | CARLOS MATAMOROS |
| PLUMBING-Final | 1/21/2026 | Not Ready for Inspection | CARLOS MATAMOROS |
| ELECTRICAL-Final | 1/26/2026 | Not Ready for Inspection | CARLOS MATAMOROS |
| HVAC-Final | 1/26/2026 | Corrections Issued | CARLOS MATAMOROS |
| PLUMBING-Final | 1/26/2026 | Not Ready for Inspection | CARLOS MATAMOROS |
| Smoke Detectors | 1/26/2026 | Not Ready for Inspection | CARLOS MATAMOROS |
| HVAC-Final | 1/29/2026 | Approved | CARLOS MATAMOROS |
| PLUMBING-Final | 1/29/2026 | Approved | CARLOS MATAMOROS |
| Drywall Nailing | 2/9/2026 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 2/9/2026 | Approved | EVAN COOPER |
| Final | 2/9/2026 | OK to Issue CofO | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 2/9/2026 | SGSOV Approved | EVAN COOPER |
| Smoke Detectors | 2/9/2026 | Approved | EVAN COOPER |