1182 N ANGELO DR 90210

Certificate Information: 1182 N ANGELO DR 90210

Application / Permit
25014-10000-01296
Plan Check / Job No.
B25LA11245
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
One-story ground floor addition and interior remodel to (E) SFD
Permit Issued
Issued on 6/23/2025
Issuing Office
Current Status
CofO Issued on 2/20/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/1/2025 APPLICANT
Assigned to Plan Check Engineer 4/17/2025 GEORGE JOLAKIAN
Corrections Issued 4/21/2025 GEORGE JOLAKIAN
Quality Review Completed 5/2/2025 HERNAN ARREOLA
Plan Check Approved 6/16/2025 GEORGE JOLAKIAN
Issued 6/23/2025 APPLICANT
CofO in Progress 2/9/2026 EVAN COOPER
Permit Finaled 2/20/2026 RICHARD STEINBACH
CofO Issued 2/20/2026 RICHARD STEINBACH
Permit Finaled 2/20/2026 RICHARD STEINBACH

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 4/22/2025 JEREMY CHOK
BHO/Hillside ordinance Cleared 4/22/2025 JEREMY CHOK
BHO/Hillside ordinance Cleared 4/22/2025 JEREMY CHOK
Eng Process Fee Ord 176,300 Cleared 4/22/2025 JEREMY CHOK
Roof/Waste drainage to street Cleared 4/22/2025 JEREMY CHOK
Sewer availability Cleared 4/22/2025 JEREMY CHOK
Grading Pre-Inspection Cleared 6/13/2025 GEORGE JOLAKIAN

Contact Information

Contractor Evan House Construction Inc; Lic. No.: 1087223-B       ,
Engineer Kile,, Johnny C; Lic. No.: C92658 3627 W 64TH STREET      LOS ANGELES, CA 90043

Inspector Information

CARLOS MATAMOROS, (310) 914-3878 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/10/2025 Corrections Issued SEAN HAUPT
ELECTRICAL-Rough 7/14/2025 Not Ready for Inspection STEPHANIE SWANSON
PLUMBING-Rough 7/14/2025 Partial Approval STEPHANIE SWANSON
Sewer 7/14/2025 Not Ready for Inspection STEPHANIE SWANSON
Footing/Foundation/Slab 7/16/2025 Approved HENRY KIM
Special/Order Compliance 7/16/2025 Corrections Issued HENRY KIM
ELECTRICAL-Rough 7/17/2025 Not Ready for Inspection SEAN HAUPT
Gas Test 8/4/2025 Corrections Issued SEAN HAUPT
PLUMBING-Rough 8/4/2025 Not Ready for Inspection SEAN HAUPT
Wood Frame 8/4/2025 Not Ready for Inspection SEAN HAUPT
ELECTRICAL-Rough 8/11/2025 Partial Approval SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 8/13/2025 Not Ready for Inspection SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 8/19/2025 Partial Approval SEAN HAUPT
BUILDING-Rough-Frame 8/25/2025 Approved SEAN HAUPT
Green Building Rough 8/25/2025 Approved SEAN HAUPT
HVAC-Rough 8/25/2025 Approved SEAN HAUPT
PLUMBING-Rough 8/25/2025 Approved SEAN HAUPT
Insulation 9/2/2025 Approved SEAN HAUPT
ELECTRICAL-Rough 9/3/2025 Corrections Issued SEAN HAUPT
Drywall Nailing 9/10/2025 Partial Approval SEAN HAUPT
Pre-Inspection 9/19/2025 Partial Approval DANIEL VERA
Interior/Exterior Lathing 9/22/2025 Partial Approval SEAN HAUPT
Pre-Inspection 9/22/2025 Partial Approval SEAN HAUPT
Shower Pan 9/22/2025 Not Ready for Inspection SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 9/30/2025 Approved DANIEL VERA
Drywall Nailing 10/8/2025 Not Ready for Inspection JAYLIN GRAVITTE
Interior/Exterior Lathing 10/8/2025 Approved JAYLIN GRAVITTE
Special/Order Compliance 10/8/2025 Partial Approval GEM DE OCAMPO
ELECTRICAL-Final 1/21/2026 Not Ready for Inspection CARLOS MATAMOROS
PLUMBING-Final 1/21/2026 Not Ready for Inspection CARLOS MATAMOROS
ELECTRICAL-Final 1/26/2026 Not Ready for Inspection CARLOS MATAMOROS
HVAC-Final 1/26/2026 Corrections Issued CARLOS MATAMOROS
PLUMBING-Final 1/26/2026 Not Ready for Inspection CARLOS MATAMOROS
Smoke Detectors 1/26/2026 Not Ready for Inspection CARLOS MATAMOROS
HVAC-Final 1/29/2026 Approved CARLOS MATAMOROS
PLUMBING-Final 1/29/2026 Approved CARLOS MATAMOROS
Drywall Nailing 2/9/2026 Approved EVAN COOPER
ELECTRICAL-Final 2/9/2026 Approved EVAN COOPER
Final 2/9/2026 OK to Issue CofO EVAN COOPER
SGSOV-Seismic Gas S/O Valve 2/9/2026 SGSOV Approved EVAN COOPER
Smoke Detectors 2/9/2026 Approved EVAN COOPER