1626 N CLEAR VIEW DR 90210

Certificate Information: 1626 N CLEAR VIEW DR 90210

Application / Permit
25014-10000-01287
Plan Check / Job No.
B25LA11153
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD 13'-8" x 13'-2" (166 S.F.) TO THE MIDDLE OF THE (E) SINGLE FAMILY DWELLING
Permit Issued
Issued on 5/1/2025
Issuing Office
Current Status
Issued on 5/1/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/24/2025 APPLICANT
Assigned to Plan Check Engineer 3/26/2025 GIOVANNY CHAVEZ
Corrections Issued 3/26/2025 GIOVANNY CHAVEZ
Plan Check Approved 4/28/2025 ANGELICA MARTINEZ
Issued 5/1/2025 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/28/2025 XOCHITL ARQUIETA
Grading Pre-Inspection Cleared 4/28/2025 GIOVANNY CHAVEZ
Roof/Waste drainage to street Cleared 4/28/2025 XOCHITL ARQUIETA

Contact Information

Contractor Owner-Builder       ,
Engineer Khanlou,, Amir; Lic. No.: C87550 2603 BASIL LN      LOS ANGELES, CA 90077

Inspector Information

CARLOS MATAMOROS, (310) 914-3878 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/7/2025 Partial Approval SEAN HAUPT
Pre-Inspection 6/3/2025 Partial Approval SEAN HAUPT
Wood Frame 6/3/2025 Not Ready for Inspection SEAN HAUPT
Green Building Rough 6/16/2025 Corrections Issued SEAN HAUPT
Reinforced Concrete Frame 6/16/2025 Partial Approval SEAN HAUPT
Wood Frame 6/16/2025 Not Ready for Inspection SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 6/23/2025 Approved STEPHANIE SWANSON
Green Building Rough 6/23/2025 Not Ready for Inspection STEPHANIE SWANSON
Deputy Drilled-In Anchors 7/30/2025 Partial Approval SEAN HAUPT
Green Building Rough 8/15/2025 Approved SEAN HAUPT
Interior/Exterior Lathing 8/15/2025 Approved SEAN HAUPT
Wood Frame 8/15/2025 Approved SEAN HAUPT
Insulation 9/5/2025 Approved DANIEL VERA
Drywall Nailing 9/18/2025 Approved SEAN HAUPT
Footing/Foundation/Slab 5/1/2026 Approved CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 5/1/2026 SGSOV Not Ready CARLOS MATAMOROS