6654 W COLGATE AVE 90048

Certificate Information: 6654 W COLGATE AVE 90048

Application / Permit
25014-10000-01278
Plan Check / Job No.
B25LA11131
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: ADDITION AND CONVERT (E) GARAGE AND STORAGE TO ACCESSORY DWELLING UNIT PER GC 66323(a)(2)
Permit Issued
Issued on 6/4/2025
Issuing Office
Current Status
Issued on 6/4/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/23/2025 APPLICANT
Assigned to Plan Check Engineer 3/25/2025 DANIEL YIP
Corrections Issued 3/25/2025 DANIEL YIP
Plan Check Approved 5/16/2025 DANIEL YIP
Issued 6/4/2025 APPLICANT

Permit Application Clearance Information

ZI Cleared 3/28/2025 ASHLEY RODARTE
Address approval Cleared 3/29/2025 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 3/29/2025 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 3/29/2025 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 4/2/2025 LEE GUILBEAUX
Sewer availability Cleared 4/2/2025 LEE GUILBEAUX
Construction within easement Cleared 5/14/2025 RIDWAN HARDY

Contact Information

Contractor Fronen Construction Inc; Lic. No.: 1053555-B       ,
Engineer Erdelyi,, Peter Tibor; Lic. No.: NA26962       ,

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/1/2025 Approved EVAN COOPER
METHANE-Barrier 11/14/2025 Not Ready for Inspection EVAN COOPER
METHANE-Subgrade 11/14/2025 Not Ready for Inspection EVAN COOPER
Special/Order Compliance 11/17/2025 Corrections Issued EVAN COOPER
Excavation/Setback/Form/Re-Bar 11/19/2025 Partial Approval EVAN COOPER
Footing/Foundation/Slab 11/19/2025 Partial Approval EVAN COOPER
METHANE-Barrier 11/19/2025 Approved EVAN COOPER
METHANE-Subgrade 11/19/2025 Approved EVAN COOPER
Excavation/Setback/Form/Re-Bar 12/3/2025 Partial Approval EVAN COOPER
Footing/Foundation/Slab 12/3/2025 Partial Approval EVAN COOPER
PLUMBING-Rough 12/8/2025 Partial Approval EVAN COOPER
Excavation/Setback/Form/Re-Bar 1/13/2026 Approved WILBER ROSALES
Footing/Foundation/Slab 1/13/2026 Approved WILBER ROSALES
BUILDING-Rough-Frame 2/18/2026 Not Ready for Inspection WILBER ROSALES
Floor/Roof Diaphrgm/Shear Wall 2/18/2026 Corrections Issued WILBER ROSALES
Green Building Rough 2/18/2026 Not Ready for Inspection WILBER ROSALES
METHANE-Rough 2/18/2026 Not Ready for Inspection WILBER ROSALES
Wood Frame 2/18/2026 Not Ready for Inspection WILBER ROSALES
Deputy Wood Construction 2/19/2026 Conditional Approval WILBER ROSALES
Floor/Roof Diaphrgm/Shear Wall 3/25/2026 Partial Approval WILBER ROSALES
HVAC-Rough 3/25/2026 Approved WILBER ROSALES
PLUMBING-Rough 3/25/2026 Approved WILBER ROSALES
ELECTRICAL-Rough 4/1/2026 Corrections Issued WILBER ROSALES
BUILDING-Rough-Frame 4/28/2026 No Access for Inspection WILBER ROSALES
Floor/Roof Diaphrgm/Shear Wall 4/28/2026 No Access for Inspection WILBER ROSALES
Green Building Rough 4/28/2026 No Access for Inspection WILBER ROSALES
Interior/Exterior Lathing 4/28/2026 No Access for Inspection WILBER ROSALES
METHANE-Rough 4/28/2026 No Access for Inspection WILBER ROSALES
Wood Frame 4/28/2026 No Access for Inspection WILBER ROSALES
BUILDING-Rough-Frame 5/4/2026 Approved WILBER ROSALES
Floor/Roof Diaphrgm/Shear Wall 5/4/2026 Approved WILBER ROSALES
Green Building Rough 5/4/2026 Approved WILBER ROSALES
Interior/Exterior Lathing 5/4/2026 Partial Approval WILBER ROSALES
METHANE-Rough 5/4/2026 Approved WILBER ROSALES
Insulation 5/7/2026 Approved WILBER ROSALES
Drywall Nailing 5/12/2026 Approved WILBER ROSALES
Sewer 5/13/2026 Approved WILBER ROSALES
Underground Mechanical 5/13/2026 Approved WILBER ROSALES
Interior/Exterior Lathing 5/22/2026 Partial Approval ARAM AVEDISIAN
Shower Pan 5/22/2026 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 5/27/2026 Partial Approval ANTHONY EGSON