7923 S GLIDER AVE 90045
Certificate Information: 7923 S GLIDER AVE 90045
- Application / Permit
- 25014-10000-01273
- Plan Check / Job No.
- B25LA11124
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- *Eplan.* (E) 1-story SFD: (N) 2nd story ADU addition and (N) 1st story rear add. ADU per LAMC 12.22 A.33 (c) and (e). "COMPLY WITH DEPARTMENT ORDER effective date 06/11/2024. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE." CEIS Case Number is 1006644.
- Permit Issued
- Issued on 8/19/2025
- Issuing Office
- Metro
- Current Status
- Issued on 8/19/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/25/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/10/2025 | RAHEL BEYENE |
| Corrections Issued | 5/2/2025 | HUAN LE |
| Quality Review Completed | 5/16/2025 | HERNAN ARREOLA |
| Applicant returned to address corrections | 8/7/2025 | RAHEL BEYENE |
| Plan Check Approved | 8/12/2025 | RAHEL BEYENE |
| Issued | 8/19/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 6/21/2025 | KIMBERLY HERNANDEZ |
| Roof/Waste drainage to street | Cleared | 6/21/2025 | KIMBERLY HERNANDEZ |
| Eng Process Fee Ord 176,300 | Cleared | 7/19/2025 | LIAM ODONOVAN |
| Sewer availability | Cleared | 7/19/2025 | LIAM ODONOVAN |
| Specific Plan | Cleared | 7/19/2025 | PEDRO AYALA |
Contact Information
| Architect | Rodriguez,Daniel, Alberto; Lic. No.: NA37840 | , |
| Contractor | Terra Firma Landscaping Inc; Lic. No.: 994585-B | 6534 S VICTORIA AVE LOS ANGELES, CA 90043 |
| Engineer | Yamini,, Soly; Lic. No.: C33719 | 540 WARNER AVE LOS ANGELES, CA 90024 |
Inspector Information
| ROBERT GARTH, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN MATTILLO, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PEDRO RIVERA, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| EUSEBIO GUZMAN, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PAUL REECE, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| ANDREW BEELI, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/7/2025 | Conditional Approval | ANDREW BEELI |
| Footing/Foundation/Slab | 10/9/2025 | Corrections Issued | ANDREW BEELI |
| Footing/Foundation/Slab | 10/10/2025 | Approved | ANDREW BEELI |
| PLUMBING-Rough | 11/4/2025 | Corrections Issued | ANDREW BEELI |
| BUILDING-Rough-Frame | 11/25/2025 | Not Ready for Inspection | ANDREW BEELI |
| Floor/Roof Diaphrgm/Shear Wall | 11/25/2025 | Approved | ANDREW BEELI |
| Green Building Rough | 11/25/2025 | Not Ready for Inspection | ANDREW BEELI |
| PLUMBING-Rough | 11/25/2025 | Not Ready for Inspection | ANDREW BEELI |
| Deputy Wood Construction | 12/16/2025 | Partial Approval | ANDREW BEELI |
| BUILDING-Rough-Frame | 12/17/2025 | Conditional Approval | RYAN BARNES |
| Green Building Rough | 12/17/2025 | Approved | RYAN BARNES |
| BUILDING-Rough-Frame | 1/16/2026 | Corrections Issued | ANDREW BEELI |
| ELECTRICAL-Rough | 1/16/2026 | Partial Approval | ANDREW BEELI |
| Green Building Final | 1/16/2026 | Corrections Issued | ANDREW BEELI |
| Green Building Rough | 1/16/2026 | Approved | ANDREW BEELI |
| Pre-Inspection | 1/16/2026 | Approved | ANDREW BEELI |
| ELECTRICAL-Rough | 1/26/2026 | Approved | RYAN BARNES |
| HVAC-Rough | 1/26/2026 | Approved | RYAN BARNES |
| PLUMBING-Rough | 1/26/2026 | Approved | RYAN BARNES |
| PLUMBING-Rough | 1/30/2026 | Corrections Issued | ANDREW BEELI |
| SGSOV-Seismic Gas S/O Valve | 1/30/2026 | SGSOV Not Ready | ANDREW BEELI |
| BUILDING-Rough-Frame | 2/13/2026 | Partial Approval | ANDREW BEELI |
| Green Building Rough | 2/13/2026 | Approved | ANDREW BEELI |
| Insulation | 2/13/2026 | Partial Approval | ANDREW BEELI |
| Interior/Exterior Lathing | 2/13/2026 | Approved | ANDREW BEELI |
| PLUMBING-Rough | 2/13/2026 | Approved | ANDREW BEELI |
| Drywall Nailing | 2/19/2026 | Approved | ANDREW BEELI |
| BUILDING-Rough-Frame | 5/19/2026 | Approved | ANDREW BEELI |
| Final | 5/19/2026 | Corrections Issued | ANDREW BEELI |
| Green Building Final | 5/19/2026 | Corrections Issued | ANDREW BEELI |
| SGSOV-Seismic Gas S/O Valve | 5/19/2026 | SGSOV Approved | ANDREW BEELI |
| Smoke Detectors | 5/19/2026 | Approved | ANDREW BEELI |
| ELECTRICAL-Final | 5/26/2026 | Approved | ANDREW BEELI |
| Final | 5/26/2026 | Partial Approval | ANDREW BEELI |
| Green Building Final | 5/26/2026 | Approved | ANDREW BEELI |
| HVAC-Final | 5/26/2026 | Approved | ANDREW BEELI |
| PLUMBING-Final | 5/26/2026 | Approved | ANDREW BEELI |