8025 N MCDERMOTT AVE 91335
Certificate Information: 8025 N MCDERMOTT AVE 91335
- Application / Permit
- 25014-10000-01268
- Plan Check / Job No.
- B25LA11114
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan : NEW ADDITION TO REAR PORTION OF (E) SFD
- Permit Issued
- Issued on 4/15/2025
- Issuing Office
- Current Status
- CofO Issued on 8/12/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/24/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/26/2025 | MOHAMMAD ESMAILI |
| Corrections Issued | 3/27/2025 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 4/7/2025 | MOHAMMAD ESMAILI |
| Plan Check Approved | 4/15/2025 | MOHAMMAD ESMAILI |
| Issued | 4/15/2025 | APPLICANT |
| CofO in Progress | 7/28/2025 | JUAN ALVARADO |
| Permit Finaled | 8/12/2025 | JOHN JANSON |
| CofO Issued | 8/12/2025 | JOHN JANSON |
| Permit Finaled | 8/12/2025 | JOHN JANSON |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 4/2/2025 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 4/3/2025 | BIAINA HARITUNIAN |
Contact Information
| Contractor | R L Remodeling Inc; Lic. No.: 885032-B | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/1/2025 | Conditional Approval | ARUTYUN MADATYAN |
| Excavation/Setback/Form/Re-Bar | 5/2/2025 | Corrections Issued | ARUTYUN MADATYAN |
| Excavation/Setback/Form/Re-Bar | 5/8/2025 | Approved | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/23/2025 | Corrections Issued | ARUTYUN MADATYAN |
| ELECTRICAL-Rough | 6/2/2025 | Approved | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/2/2025 | Approved | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 6/10/2025 | Approved | ARUTYUN MADATYAN |
| Green Building Rough | 6/10/2025 | Approved | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 6/10/2025 | Partial Approval | ARUTYUN MADATYAN |
| Insulation | 6/13/2025 | Approved | ARUTYUN MADATYAN |
| Drywall Nailing | 6/18/2025 | Approved | GEVORK IPCHYAN |
| Final | 7/10/2025 | Corrections Issued | JUAN ALVARADO |
| Footing/Foundation/Slab | 7/10/2025 | Approved | JUAN ALVARADO |
| Green Building Final | 7/10/2025 | Approved | JUAN ALVARADO |
| SGSOV-Seismic Gas S/O Valve | 7/10/2025 | SGSOV Approved | JUAN ALVARADO |
| Smoke Detectors | 7/10/2025 | Corrections Issued | JUAN ALVARADO |
| Final | 7/18/2025 | OK to Issue CofO | JUAN ALVARADO |
| Smoke Detectors | 7/18/2025 | Approved | JUAN ALVARADO |
| ELECTRICAL-Final | 7/29/2025 | Approved | JUAN ALVARADO |
| HVAC-Final | 7/29/2025 | Approved | JUAN ALVARADO |
| PLUMBING-Final | 7/29/2025 | Approved | JUAN ALVARADO |