5109 E RANGE VIEW AVE 90042

Certificate Information: 5109 E RANGE VIEW AVE 90042

Application / Permit
25014-10000-01259
Plan Check / Job No.
B25LA11064
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Eplan Remodel with 17'4" x 9'8" (167 sqft) addition to single family home.
Permit Issued
Issued on 7/1/2025
Issuing Office
Current Status
Issued on 7/1/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/23/2025 APPLICANT
Assigned to Plan Check Engineer 3/25/2025 NGHI SU
Corrections Issued 3/26/2025 NGHI SU
Applicant returned to address corrections 4/22/2025 SUNMIN LEE
Applicant returned to address corrections 5/13/2025 NGHI SU
Applicant returned to address corrections 5/23/2025 NGHI SU
Plan Check Approved 6/15/2025 NGHI SU
Issued 7/1/2025 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 4/12/2025 SAFA JAVANMARDI
Eng Process Fee Ord 176,300 Cleared 4/16/2025 SAFA JAVANMARDI
Grading Pre-Inspection Cleared 4/24/2025 MICHAEL TEMPLE

Contact Information

Contractor Sky Builders Inc; Lic. No.: 1079863-B       ,
Contractor Sky Builders Z H R Inc; Lic. No.: 1079863-B       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/29/2025 Corrections Issued ALIZAH MAYAGOITIA
Footing/Foundation/Slab 8/1/2025 Approved DAVID WILLIAMS
Deputy Drilled-In Anchors 8/5/2025 Conditional Approval DAVID WILLIAMS
Floor/Roof Diaphrgm/Shear Wall 8/6/2025 Partial Approval REGINA MENDEZ
Floor/Roof Diaphrgm/Shear Wall 8/8/2025 Not Ready for Inspection REGINA MENDEZ
Insulation 8/8/2025 Partial Approval REGINA MENDEZ
Floor/Roof Diaphrgm/Shear Wall 11/6/2025 Partial Approval DAVID WILLIAMS
Wood Frame 11/6/2025 Not Ready for Inspection DAVID WILLIAMS
BUILDING-Rough-Frame 12/5/2025 Not Ready for Inspection JEFFREY MEAD
Floor/Roof Diaphrgm/Shear Wall 12/5/2025 Not Ready for Inspection JEFFREY MEAD
Green Building Rough 12/5/2025 Not Ready for Inspection JEFFREY MEAD
HVAC-Rough 12/5/2025 Corrections Issued JEFFREY MEAD
PLUMBING-Rough 12/5/2025 Approved JEFFREY MEAD
Wood Frame 12/5/2025 Not Ready for Inspection JEFFREY MEAD
ELECTRICAL-Rough 12/12/2025 Corrections Issued DAVID WILLIAMS
Floor/Roof Diaphrgm/Shear Wall 12/12/2025 Approved DAVID WILLIAMS
HVAC-Rough 12/12/2025 Approved DAVID WILLIAMS
ELECTRICAL-Rough 12/29/2025 Approved DAVID WILLIAMS
BUILDING-Rough-Frame 1/9/2026 Approved DAVID WILLIAMS
Green Building Rough 1/9/2026 Approved DAVID WILLIAMS
Insulation 1/12/2026 Approved DAVID WILLIAMS
Special/Order Compliance 1/12/2026 Not Ready for Inspection DAVID WILLIAMS
Interior/Exterior Lathing 1/26/2026 Approved GEM DE OCAMPO
Shower Pan 1/26/2026 Approved GEM DE OCAMPO
Interior/Exterior Lathing 1/28/2026 Corrections Issued GEM DE OCAMPO
Interior/Exterior Lathing 1/29/2026 Approved LILIANA PORTILLO
Drywall Nailing 2/12/2026 Approved GEM DE OCAMPO