2648 S BUTLER AVE 90064

Certificate Information: 2648 S BUTLER AVE 90064

Application / Permit
25014-10000-01242
Plan Check / Job No.
B25LA10892
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN Convert detached garage into a detached Accessory Dwelling Unit (ADU) per LAMC 12.22 A.33(b)(1). Patio cover addition on 1st floor and new 2nd floor addition for recreation room.
Permit Issued
Issued on 7/14/2025
Issuing Office
Current Status
CofO Issued on 12/30/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/20/2025 APPLICANT
Assigned to Plan Check Engineer 4/3/2025 JESSE VIDUYA
Corrections Issued 4/11/2025 JESSE VIDUYA
Quality Review Completed 4/18/2025 HERNAN ARREOLA
Applicant returned to address corrections 6/26/2025 JESSE VIDUYA
Applicant returned to address corrections 7/2/2025 JESSE VIDUYA
Plan Check Approved 7/14/2025 JESSE VIDUYA
Issued 7/14/2025 APPLICANT
CofO in Progress 12/8/2025 MICHAEL ALLEN
Permit Finaled 12/30/2025 RICHARD STEINBACH
CofO Issued 12/30/2025 RICHARD STEINBACH
Permit Finaled 12/30/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 4/21/2025 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 4/21/2025 COLIN LOREDO
Roof/Waste drainage to street Cleared 4/21/2025 COLIN LOREDO
Sewer availability Cleared 4/21/2025 COLIN LOREDO
Specific Plan Cleared 4/28/2025 RICHARD WOO
Construction near power lines Cleared 6/16/2025 RIDWAN HARDY

Contact Information

Architect Dembsky,, Amit; Lic. No.: NA30383       ,
Contractor Quality First Builders Inc; Lic. No.: 990316-B       ,
Engineer Rhee,, Kyle; Lic. No.: C78215 2753 WAVERLY DR 403      LOS ANGELES, CA 90039
Engineer Rhee,, Kyle; Lic. No.: NA78215       ,

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/12/2025 Partial Approval ARAM AVEDISIAN
Sewer 8/12/2025 Approved ARAM AVEDISIAN
Deputy Drilled-In Anchors 8/14/2025 Approved KIRK SANDERS
Footing/Foundation/Slab 8/14/2025 Partial Approval KIRK SANDERS
Footing/Foundation/Slab 8/18/2025 Approved KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 8/27/2025 Corrections Issued JAYLIN GRAVITTE
Deputy Wood Construction 8/28/2025 Conditional Approval KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 9/2/2025 Corrections Issued EVAN COOPER
ELECTRICAL-Rough 9/9/2025 Partial Approval MEL KHACHATOURIAN
HVAC-Rough 9/9/2025 Partial Approval MEL KHACHATOURIAN
PLUMBING-Rough 9/9/2025 Approved MEL KHACHATOURIAN
Floor/Roof Diaphrgm/Shear Wall 9/11/2025 Approved STEPHANIE SWANSON
Interior/Exterior Lathing 9/19/2025 Partial Approval KIRK SANDERS
PLUMBING-Rough 9/19/2025 Approved KIRK SANDERS
Green Building Rough 9/23/2025 Approved MICHAEL ALLEN
Insulation 9/23/2025 Approved MICHAEL ALLEN
BUILDING-Rough-Frame 9/24/2025 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 9/24/2025 Approved ARAM AVEDISIAN
MERV13>=Rough 9/24/2025 Approved ARAM AVEDISIAN
Drywall Nailing 9/26/2025 Approved CARLOS MATAMOROS
Shower Pan 9/26/2025 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 9/29/2025 Approved KIRK SANDERS
Final 11/26/2025 Corrections Issued KIRK SANDERS
Green Building Final 11/26/2025 Approved KIRK SANDERS
MERV13>=Final 11/26/2025 Approved KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 11/26/2025 SGSOV Approved KIRK SANDERS
Smoke Detectors 11/26/2025 Approved KIRK SANDERS
ELECTRICAL-Final 12/5/2025 Approved MICHAEL ALLEN
Final 12/5/2025 OK to Issue CofO MICHAEL ALLEN
HVAC-Final 12/5/2025 Approved MICHAEL ALLEN
PLUMBING-Final 12/5/2025 Approved MICHAEL ALLEN