2648 S BUTLER AVE 90064
Certificate Information: 2648 S BUTLER AVE 90064
- Application / Permit
- 25014-10000-01242
- Plan Check / Job No.
- B25LA10892
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN Convert detached garage into a detached Accessory Dwelling Unit (ADU) per LAMC 12.22 A.33(b)(1). Patio cover addition on 1st floor and new 2nd floor addition for recreation room.
- Permit Issued
- Issued on 7/14/2025
- Issuing Office
- Current Status
- CofO Issued on 12/30/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/20/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/3/2025 | JESSE VIDUYA |
| Corrections Issued | 4/11/2025 | JESSE VIDUYA |
| Quality Review Completed | 4/18/2025 | HERNAN ARREOLA |
| Applicant returned to address corrections | 6/26/2025 | JESSE VIDUYA |
| Applicant returned to address corrections | 7/2/2025 | JESSE VIDUYA |
| Plan Check Approved | 7/14/2025 | JESSE VIDUYA |
| Issued | 7/14/2025 | APPLICANT |
| CofO in Progress | 12/8/2025 | MICHAEL ALLEN |
| Permit Finaled | 12/30/2025 | RICHARD STEINBACH |
| CofO Issued | 12/30/2025 | RICHARD STEINBACH |
| Permit Finaled | 12/30/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 4/21/2025 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 4/21/2025 | COLIN LOREDO |
| Roof/Waste drainage to street | Cleared | 4/21/2025 | COLIN LOREDO |
| Sewer availability | Cleared | 4/21/2025 | COLIN LOREDO |
| Specific Plan | Cleared | 4/28/2025 | RICHARD WOO |
| Construction near power lines | Cleared | 6/16/2025 | RIDWAN HARDY |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: NA30383 | , |
| Contractor | Quality First Builders Inc; Lic. No.: 990316-B | , |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
| Engineer | Rhee,, Kyle; Lic. No.: NA78215 | , |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/12/2025 | Partial Approval | ARAM AVEDISIAN |
| Sewer | 8/12/2025 | Approved | ARAM AVEDISIAN |
| Deputy Drilled-In Anchors | 8/14/2025 | Approved | KIRK SANDERS |
| Footing/Foundation/Slab | 8/14/2025 | Partial Approval | KIRK SANDERS |
| Footing/Foundation/Slab | 8/18/2025 | Approved | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 8/27/2025 | Corrections Issued | JAYLIN GRAVITTE |
| Deputy Wood Construction | 8/28/2025 | Conditional Approval | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 9/2/2025 | Corrections Issued | EVAN COOPER |
| ELECTRICAL-Rough | 9/9/2025 | Partial Approval | MEL KHACHATOURIAN |
| HVAC-Rough | 9/9/2025 | Partial Approval | MEL KHACHATOURIAN |
| PLUMBING-Rough | 9/9/2025 | Approved | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/11/2025 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 9/19/2025 | Partial Approval | KIRK SANDERS |
| PLUMBING-Rough | 9/19/2025 | Approved | KIRK SANDERS |
| Green Building Rough | 9/23/2025 | Approved | MICHAEL ALLEN |
| Insulation | 9/23/2025 | Approved | MICHAEL ALLEN |
| BUILDING-Rough-Frame | 9/24/2025 | Approved | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/24/2025 | Approved | ARAM AVEDISIAN |
| MERV13>=Rough | 9/24/2025 | Approved | ARAM AVEDISIAN |
| Drywall Nailing | 9/26/2025 | Approved | CARLOS MATAMOROS |
| Shower Pan | 9/26/2025 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 9/29/2025 | Approved | KIRK SANDERS |
| Final | 11/26/2025 | Corrections Issued | KIRK SANDERS |
| Green Building Final | 11/26/2025 | Approved | KIRK SANDERS |
| MERV13>=Final | 11/26/2025 | Approved | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 11/26/2025 | SGSOV Approved | KIRK SANDERS |
| Smoke Detectors | 11/26/2025 | Approved | KIRK SANDERS |
| ELECTRICAL-Final | 12/5/2025 | Approved | MICHAEL ALLEN |
| Final | 12/5/2025 | OK to Issue CofO | MICHAEL ALLEN |
| HVAC-Final | 12/5/2025 | Approved | MICHAEL ALLEN |
| PLUMBING-Final | 12/5/2025 | Approved | MICHAEL ALLEN |