1611 S STEARNS DR 90035
Certificate Information: 1611 S STEARNS DR 90035
- Application / Permit
- 25014-10000-01240
- Plan Check / Job No.
- B25LA10849
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL AND ADDITION TO EXISTING SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 5/1/2025
- Issuing Office
- Current Status
- CofO Issued on 11/29/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/20/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/25/2025 | SUNMIN LEE |
| Corrections Issued | 3/25/2025 | SUNMIN LEE |
| Applicant returned to address corrections | 4/17/2025 | SUNMIN LEE |
| Plan Check Approved | 4/23/2025 | CARLOS MONTES |
| Issued | 5/1/2025 | APPLICANT |
| CofO in Progress | 11/26/2025 | BRENDAN MORELLI |
| Permit Finaled | 11/29/2025 | DEROLD HAUFF |
| CofO Issued | 11/29/2025 | DEROLD HAUFF |
| Permit Finaled | 11/29/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/22/2025 | CINDY QI |
| Roof/Waste drainage to street | Cleared | 4/22/2025 | CINDY QI |
| Sewer availability | Cleared | 4/22/2025 | CINDY QI |
Contact Information
| Contractor | Panda Homes Design And Construction; Lic. No.: 1071366-B | , |
| Engineer | Gonzalez,, Daniel; Lic. No.: C87405 | 216 N VERNON AVE AZUSA, CA 91702 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/23/2025 | Conditional Approval | ARTHUR NEGRETE |
| Excavation/Setback/Form/Re-Bar | 5/27/2025 | Approved | ARTHUR NEGRETE |
| Footing/Foundation/Slab | 5/27/2025 | Approved | ARTHUR NEGRETE |
| METHANE-Barrier | 5/27/2025 | Approved | ARTHUR NEGRETE |
| METHANE-Subgrade | 5/27/2025 | Approved | ARTHUR NEGRETE |
| Floor/Roof Diaphrgm/Shear Wall | 7/8/2025 | Approved | ARTHUR NEGRETE |
| HVAC-Rough | 7/8/2025 | Approved | ARTHUR NEGRETE |
| METHANE-Rough | 7/8/2025 | Approved | ARTHUR NEGRETE |
| PLUMBING-Rough | 7/8/2025 | Approved | ARTHUR NEGRETE |
| BUILDING-Rough-Frame | 7/10/2025 | Approved | ARTHUR NEGRETE |
| ELECTRICAL-Rough | 7/10/2025 | Approved | ARTHUR NEGRETE |
| Floor/Roof Diaphrgm/Shear Wall | 7/10/2025 | Approved | ARTHUR NEGRETE |
| Green Building Rough | 7/10/2025 | Approved | ARTHUR NEGRETE |
| Interior/Exterior Lathing | 7/10/2025 | Approved | ARTHUR NEGRETE |
| Insulation | 7/16/2025 | Corrections Issued | ALEX COLIN |
| Shower Pan | 7/16/2025 | Corrections Issued | ALEX COLIN |
| Drywall Nailing | 7/28/2025 | Approved | GEM DE OCAMPO |
| Non Compliance | 7/28/2025 | Not Required | GEM DE OCAMPO |
| Shower Pan | 7/28/2025 | Corrections Issued | GEM DE OCAMPO |
| Shower Pan | 8/26/2025 | Approved | ARTHUR NEGRETE |
| Final | 11/25/2025 | Conditional Approval | JOSH MEISTER |
| Green Building Final | 11/25/2025 | Approved | JOSH MEISTER |
| SGSOV-Seismic Gas S/O Valve | 11/25/2025 | SGSOV Approved | JOSH MEISTER |
| Smoke Detectors | 11/25/2025 | Approved | JOSH MEISTER |
| Final | 11/26/2025 | OK to Issue CofO | BRENDAN MORELLI |