3422 W HOLLYDALE DR 90039

Certificate Information: 3422 W HOLLYDALE DR 90039

Application / Permit
25014-10000-01225
Plan Check / Job No.
B25LA10648
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL AND ADDITION TO (E) SFD. INCLUDES REFRAMING OF (E) PORTION OF ROOF TO MATCH ADJACENT ADDITION.
Permit Issued
Issued on 4/15/2025
Issuing Office
Current Status
CofO Issued on 11/9/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/19/2025 APPLICANT
Assigned to Plan Check Engineer 3/24/2025 LAWRENCE QUIRANTE
Corrections Issued 3/24/2025 LAWRENCE QUIRANTE
Building Plans Picked Up 3/28/2025 APPLICANT
Issued 4/15/2025 APPLICANT
CofO in Progress 10/31/2025 NICHOLAS LOPEZ
Permit Finaled 11/9/2025 DEROLD HAUFF
CofO Issued 11/9/2025 DEROLD HAUFF
Permit Finaled 11/9/2025 DEROLD HAUFF

Permit Application Clearance Information

Specific Plan Cleared 3/27/2025 CLAUDE GOODING
Roof/Waste drainage to street Cleared 4/11/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 4/15/2025 BIAINA HARITUNIAN

Contact Information

Contractor Tarte Design Build Llc; Lic. No.: 1120612-B 1557 SILVERWOOD TERRACE      LOS ANGELES, CA 90026
Engineer Dominguez,, Refugio; Lic. No.: C50820 254 COTTONWOOD ST      ONTARIO, CA 91761

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 6/23/2025 Approved JOSH MEISTER
Excavation/Setback/Form/Re-Bar 6/26/2025 Approved DAVID WILLIAMS
Footing/Foundation/Slab 6/26/2025 Approved DAVID WILLIAMS
Deputy Drilled-In Anchors 7/14/2025 Conditional Approval NICHOLAS LOPEZ
Interior/Exterior Lathing 7/18/2025 Partial Approval REGINA MENDEZ
BUILDING-Rough-Frame 8/1/2025 Not Ready for Inspection BRENDAN MORELLI
ELECTRICAL-Rough 8/1/2025 Corrections Issued BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 8/1/2025 Partial Approval BRENDAN MORELLI
Green Building Rough 8/1/2025 Not Ready for Inspection BRENDAN MORELLI
HVAC-Rough 8/1/2025 Corrections Issued BRENDAN MORELLI
PLUMBING-Rough 8/1/2025 Corrections Issued BRENDAN MORELLI
Deputy Drilled-In Anchors 8/5/2025 Conditional Approval NICHOLAS LOPEZ
BUILDING-Rough-Frame 8/7/2025 Approved NICHOLAS LOPEZ
ELECTRICAL-Rough 8/7/2025 Approved NICHOLAS LOPEZ
Green Building Rough 8/7/2025 Approved NICHOLAS LOPEZ
HVAC-Rough 8/7/2025 Approved NICHOLAS LOPEZ
Interior/Exterior Lathing 8/7/2025 Approved NICHOLAS LOPEZ
PLUMBING-Rough 8/7/2025 Approved NICHOLAS LOPEZ
Insulation 8/12/2025 Approved GEM DE OCAMPO
Drywall Nailing 8/20/2025 Approved REGINA MENDEZ
Interior/Exterior Lathing 8/20/2025 Approved REGINA MENDEZ
Shower Pan 8/20/2025 Approved REGINA MENDEZ
ELECTRICAL-Final 10/27/2025 Approved NICHOLAS LOPEZ
Final 10/27/2025 Corrections Issued NICHOLAS LOPEZ
Green Building Final 10/27/2025 Not Ready for Inspection NICHOLAS LOPEZ
HVAC-Final 10/27/2025 Approved NICHOLAS LOPEZ
PLUMBING-Final 10/27/2025 Corrections Issued NICHOLAS LOPEZ
SGSOV-Seismic Gas S/O Valve 10/27/2025 SGSOV Approved NICHOLAS LOPEZ
Service/Power Release 10/27/2025 Not Required NICHOLAS LOPEZ
Smoke Detectors 10/27/2025 Approved NICHOLAS LOPEZ
Final 10/30/2025 OK to Issue CofO NICHOLAS LOPEZ
Green Building Final 10/30/2025 Approved NICHOLAS LOPEZ
PLUMBING-Final 10/30/2025 Approved NICHOLAS LOPEZ