1475 1/2 N WESTERLY TER 90026
Certificate Information: 1475 1/2 N WESTERLY TER 90026
- Application / Permit
- 25014-10000-01214
- Plan Check / Job No.
- B25LA10575
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- addition and remodel of SFD
- Permit Issued
- Issued on 3/3/2026
- Issuing Office
- Current Status
- Issued on 3/3/2026
Permit Application Status History
| Submitted | 4/9/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/24/2025 | ARSALAN SHABESTARI |
| Corrections Issued | 5/2/2025 | ARSALAN SHABESTARI |
| Quality Review Completed | 5/14/2025 | GARO TELMI |
| Applicant returned to address corrections | 11/18/2025 | ARSALAN SHABESTARI |
| Plan Check Approved | 3/3/2026 | ARSALAN SHABESTARI |
| Issued | 3/3/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 6/9/2025 | JESSICA OPINION |
| Sewer availability | Cleared | 6/9/2025 | JESSICA OPINION |
| Eng Process Fee Ord 176,300 | Cleared | 6/11/2025 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 6/11/2025 | CELINA MORENO |
| Hydrant and Access approval | Cleared | 7/2/2025 | JERRY KAO |
| Construction near power lines | Cleared | 10/31/2025 | RIDWAN HARDY |
| Construction within easement | Cleared | 10/31/2025 | RIDWAN HARDY |
| GPI Written Notices | Cleared | 1/27/2026 | ARSALAN SHABESTARI |
| Grading Pre-Inspection | Cleared | 1/27/2026 | ARSALAN SHABESTARI |
Contact Information
| Contractor | Potato Construction Inc; Lic. No.: 1003152-B | , |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| No Data Available. |